Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Ishaan works twice as fast as Kabir. Together they finish a job in 4 days. How many days would Kabir take alone?
- 2.Kabir can finish a job in 5 days and Tara in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 3.Zoya can finish a job in 16 days and Kabir in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 4.Ananya can finish a job in 16 days and Kavya in 8 days. Ananya works alone for 14 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 5.Dev works three times as fast as Saanvi. Together they finish a job in 2 days. How many days would Saanvi take alone?
- 6.Zoya can finish a job in 10 days and Sneha in 22 days. Zoya works alone for 5 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 7.Diya works three times as fast as Pooja. Together they finish a job in 8 days. How many days would Pooja take alone?
- 8.Ananya works twice as fast as Priya. Together they finish a job in 3 days. How many days would Priya take alone?
- 9.Nisha can finish a job in 10 days and Arjun in 6 days. What fraction of the job do they finish if they work together for 1 day? =
- 10.Karan can finish a job in 8 days and Ananya in 12 days. Karan works alone for 4 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 11.Arjun can finish a job in 4 days and Rahul in 24 days. Arjun works alone for 1 day and then stops. Rahul finishes the rest. How many days does Rahul take?
- 12.Ishaan can finish a job in 4 days and Priya in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Rohan can finish a job in 9 days and Ishaan in 12 days. What fraction of the job do they finish if they work together for 1 day? =
- 14.Meera and Karan together finish a job in 8 days. Meera alone takes 10 days. How many days would Karan take alone?
- 15.Kavya can finish a job in 8 days and Arjun in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Pooja and Manav together finish a job in 4 days. Pooja alone takes 8 days. How many days would Manav take alone?
- 17.Farhan and Kabir together finish a job in 3 days. Farhan alone takes 6 days. How many days would Kabir take alone?
- 18.Meera works twice as fast as Ishaan. Together they finish a job in 3 days. How many days would Ishaan take alone?
- 19.Karan and Kabir together finish a job in 10 days. Karan alone takes 12 days. How many days would Kabir take alone?
- 20.Arjun can finish a job in 4 days and Vivaan in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Saanvi can finish a job in 10 days and Aarav in 14 days. What fraction of the job do they finish if they work together for 1 day? =
- 22.Nisha can finish a job in 5 days and Karan in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 23.Aarav can finish a job in 14 days and Isha in 28 days. Aarav works alone for 7 days and then stops. Isha finishes the rest. How many days does Isha take?
- 24.Vivaan can finish a job in 20 days and Rahul in 12 days. Vivaan works alone for 5 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 25.Pooja can finish a job in 6 days and Saanvi in 19 days. What fraction of the job do they finish if they work together for 3 days? =
- 26.Diya can finish a job in 4 days and Nisha in 24 days. Diya works alone for 2 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 27.Ananya can finish a job in 12 days and Diya in 9 days. What fraction of the job do they finish if they work together for 3 days? =
- 28.Saanvi can finish a job in 7 days and Nisha in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 29.Vivaan works three times as fast as Priya. Together they finish a job in 2 days. How many days would Priya take alone?
- 30.Nisha works twice as fast as Aarav. Together they finish a job in 2 days. How many days would Aarav take alone?
- 31.Pooja can finish a job in 10 days and Aarav in 22 days. Pooja works alone for 5 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 32.Kavya can finish a job in 9 days and Rahul in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Rohan can finish a job in 16 days and Meera in 24 days. Rohan works alone for 12 days and then stops. Meera finishes the rest. How many days does Meera take?
- 34.Karan can finish a job in 20 days and Meera in 6 days. Karan works alone for 10 days and then stops. Meera finishes the rest. How many days does Meera take?
- 35.Ishaan and Dev together finish a job in 4 days. Ishaan alone takes 6 days. How many days would Dev take alone?
- 36.Vivaan and Dev together finish a job in 12 days. Vivaan alone takes 24 days. How many days would Dev take alone?
- 37.Diya works twice as fast as Nisha. Together they finish a job in 5 days. How many days would Nisha take alone?
- 38.Aarav can finish a job in 5 days and Priya in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 39.Arjun can finish a job in 10 days and Sneha in 7 days. What fraction of the job do they finish if they work together for 1 day? =
- 40.Ishaan can finish a job in 17 days and Pooja in 10 days. What fraction of the job do they finish if they work together for 2 days? =
Answer key
- 12
- 21/40
- 15/56
- 1
- 8
- 11
- 32
- 9
- 4/15
- 6
- 18
- 76/23
- 7/36
- 40
- 24/11
- 8
- 6
- 9
- 60
- 12/7
- 6/35
- 19/35
- 14
- 9
- 25/38
- 12
- 7/12
- 3/7
- 8
- 6
- 11
- 117/22
- 6
- 3
- 12
- 24
- 15
- 21/40
- 17/70
- 27/85