Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Sneha works three times as fast as Meera. Together they finish a job in 4 days. How many days would Meera take alone?
- 2.Dev can finish a job in 16 days and Saanvi in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 3.Kabir and Vivaan together finish a job in 15 days. Kabir alone takes 20 days. How many days would Vivaan take alone?
- 4.Nisha can finish a job in 4 days and Tara in 12 days. Nisha works alone for 1 day and then stops. Tara finishes the rest. How many days does Tara take?
- 5.Diya can finish a job in 16 days and Rohan in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Nisha can finish a job in 19 days and Tara in 4 days. What fraction of the job do they finish if they work together for 1 day? =
- 7.Dev works three times as fast as Rahul. Together they finish a job in 12 days. How many days would Rahul take alone?
- 8.Sneha can finish a job in 8 days and Diya in 4 days. What fraction of the job do they finish if they work together for 2 days? =
- 9.Vivaan can finish a job in 6 days and Isha in 24 days. Vivaan works alone for 5 days and then stops. Isha finishes the rest. How many days does Isha take?
- 10.Sneha can finish a job in 8 days and Rahul in 16 days. Sneha works alone for 7 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 11.Zoya can finish a job in 15 days and Saanvi in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Sneha can finish a job in 13 days and Tara in 14 days. What fraction of the job do they finish if they work together for 1 day? =
- 13.Sneha can finish a job in 4 days and Arjun in 20 days. Sneha works alone for 2 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 14.Pooja can finish a job in 11 days and Aarav in 22 days. Pooja works alone for 4 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 15.Zoya can finish a job in 17 days and Manav in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Meera works twice as fast as Nisha. Together they finish a job in 9 days. How many days would Nisha take alone?
- 17.Sneha can finish a job in 7 days and Vivaan in 14 days. Sneha works alone for 5 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 18.Rohan can finish a job in 11 days and Meera in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Tara works three times as fast as Farhan. Together they finish a job in 9 days. How many days would Farhan take alone?
- 20.Manav can finish a job in 19 days and Isha in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Ishaan can finish a job in 4 days and Arjun in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Ananya and Rohan together finish a job in 8 days. Ananya alone takes 10 days. How many days would Rohan take alone?
- 23.Kabir works twice as fast as Ishaan. Together they finish a job in 2 days. How many days would Ishaan take alone?
- 24.Sneha can finish a job in 12 days and Rahul in 8 days. What fraction of the job do they finish if they work together for 1 day? =
- 25.Isha works twice as fast as Dev. Together they finish a job in 3 days. How many days would Dev take alone?
- 26.Ishaan and Isha together finish a job in 12 days. Ishaan alone takes 15 days. How many days would Isha take alone?
- 27.Arjun can finish a job in 16 days and Zoya in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Tara can finish a job in 19 days and Ananya in 5 days. What fraction of the job do they finish if they work together for 3 days? =
- 29.Dev and Nisha together finish a job in 2 days. Dev alone takes 6 days. How many days would Nisha take alone?
- 30.Rohan can finish a job in 18 days and Karan in 24 days. Rohan works alone for 6 days and then stops. Karan finishes the rest. How many days does Karan take?
- 31.Nisha and Diya together finish a job in 7 days. Nisha alone takes 8 days. How many days would Diya take alone?
- 32.Meera works three times as fast as Aarav. Together they finish a job in 2 days. How many days would Aarav take alone?
- 33.Karan works twice as fast as Priya. Together they finish a job in 7 days. How many days would Priya take alone?
- 34.Karan works twice as fast as Diya. Together they finish a job in 9 days. How many days would Diya take alone?
- 35.Karan can finish a job in 14 days and Rohan in 20 days. What fraction of the job do they finish if they work together for 2 days? =
- 36.Kabir can finish a job in 13 days and Rohan in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 37.Priya can finish a job in 3 days and Manav in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Kavya and Nisha together finish a job in 9 days. Kavya alone takes 10 days. How many days would Nisha take alone?
- 39.Pooja and Diya together finish a job in 18 days. Pooja alone takes 30 days. How many days would Diya take alone?
- 40.Arjun and Diya together finish a job in 2 days. Arjun alone takes 6 days. How many days would Diya take alone?
Answer key
- 16
- 16/5
- 60
- 9
- 112/15
- 23/76
- 48
- 3/4
- 4
- 2
- 30/17
- 27/182
- 10
- 14
- 136/25
- 27
- 4
- 154/25
- 36
- 228/31
- 12/7
- 40
- 6
- 5/24
- 9
- 60
- 16/5
- 72/95
- 3
- 16
- 56
- 8
- 21
- 27
- 17/70
- 29/104
- 18/7
- 90
- 45
- 3
Free quantitative aptitude lessons, practice and worksheets at talentjr.in/quantitative-aptitude