Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Meera and Kavya together finish a job in 2 days. Meera alone takes 6 days. How many days would Kavya take alone?
- 2.Rohan and Karan together finish a job in 3 days. Rohan alone takes 4 days. How many days would Karan take alone?
- 3.Kavya works twice as fast as Dev. Together they finish a job in 9 days. How many days would Dev take alone?
- 4.Tara works three times as fast as Sneha. Together they finish a job in 9 days. How many days would Sneha take alone?
- 5.Rohan works three times as fast as Diya. Together they finish a job in 12 days. How many days would Diya take alone?
- 6.Sneha can finish a job in 18 days and Kavya in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 7.Dev can finish a job in 10 days and Isha in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Manav works twice as fast as Rohan. Together they finish a job in 11 days. How many days would Rohan take alone?
- 9.Rahul can finish a job in 12 days and Nisha in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Arjun can finish a job in 18 days and Meera in 6 days. Arjun works alone for 12 days and then stops. Meera finishes the rest. How many days does Meera take?
- 11.Diya and Rohan together finish a job in 3 days. Diya alone takes 6 days. How many days would Rohan take alone?
- 12.Isha and Priya together finish a job in 7 days. Isha alone takes 14 days. How many days would Priya take alone?
- 13.Rohan and Dev together finish a job in 2 days. Rohan alone takes 6 days. How many days would Dev take alone?
- 14.Isha and Saanvi together finish a job in 2 days. Isha alone takes 6 days. How many days would Saanvi take alone?
- 15.Vivaan and Rohan together finish a job in 6 days. Vivaan alone takes 7 days. How many days would Rohan take alone?
- 16.Isha works twice as fast as Kabir. Together they finish a job in 9 days. How many days would Kabir take alone?
- 17.Aarav can finish a job in 14 days and Ananya in 18 days. Aarav works alone for 7 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 18.Aarav works twice as fast as Isha. Together they finish a job in 3 days. How many days would Isha take alone?
- 19.Nisha can finish a job in 9 days and Rahul in 27 days. Nisha works alone for 6 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 20.Priya can finish a job in 19 days and Rohan in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 21.Tara can finish a job in 16 days and Zoya in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Manav works three times as fast as Dev. Together they finish a job in 8 days. How many days would Dev take alone?
- 23.Nisha can finish a job in 16 days and Rahul in 9 days. What fraction of the job do they finish if they work together for 1 day? =
- 24.Vivaan can finish a job in 14 days and Ishaan in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 25.Meera works three times as fast as Aarav. Together they finish a job in 8 days. How many days would Aarav take alone?
- 26.Meera works twice as fast as Dev. Together they finish a job in 2 days. How many days would Dev take alone?
- 27.Diya can finish a job in 8 days and Farhan in 16 days. Diya works alone for 4 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 28.Sneha can finish a job in 13 days and Manav in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Kabir and Sneha together finish a job in 2 days. Kabir alone takes 4 days. How many days would Sneha take alone?
- 30.Arjun and Rahul together finish a job in 5 days. Arjun alone takes 6 days. How many days would Rahul take alone?
- 31.Saanvi can finish a job in 14 days and Vivaan in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Dev can finish a job in 20 days and Meera in 12 days. What fraction of the job do they finish if they work together for 2 days? =
- 33.Tara and Sneha together finish a job in 2 days. Tara alone takes 3 days. How many days would Sneha take alone?
- 34.Nisha and Pooja together finish a job in 12 days. Nisha alone takes 20 days. How many days would Pooja take alone?
- 35.Priya can finish a job in 15 days and Kabir in 9 days. What fraction of the job do they finish if they work together for 3 days? =
- 36.Ananya can finish a job in 11 days and Aditya in 4 days. What fraction of the job do they finish if they work together for 1 day? =
- 37.Arjun can finish a job in 15 days and Kavya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Vivaan can finish a job in 14 days and Pooja in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Dev can finish a job in 20 days and Manav in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Aarav can finish a job in 18 days and Pooja in 19 days. What fraction of the job do they finish if they work together for 3 days? =
Answer key
- 3
- 12
- 27
- 36
- 48
- 23/90
- 5/3
- 33
- 48/7
- 2
- 6
- 14
- 3
- 3
- 42
- 27
- 9
- 9
- 9
- 25/38
- 304/35
- 32
- 25/144
- 16/63
- 32
- 6
- 8
- 260/33
- 4
- 30
- 28/9
- 4/15
- 6
- 30
- 8/15
- 15/44
- 90/11
- 238/31
- 140/27
- 37/114