Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Arjun and Sneha together finish a job in 4 days. Arjun alone takes 5 days. How many days would Sneha take alone?
- 2.Nisha can finish a job in 20 days and Priya in 5 days. What fraction of the job do they finish if they work together for 3 days? =
- 3.Ishaan and Priya together finish a job in 4 days. Ishaan alone takes 5 days. How many days would Priya take alone?
- 4.Karan can finish a job in 5 days and Rahul in 25 days. Karan works alone for 2 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 5.Pooja can finish a job in 16 days and Vivaan in 24 days. Pooja works alone for 12 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 6.Dev works twice as fast as Ananya. Together they finish a job in 11 days. How many days would Ananya take alone?
- 7.Karan can finish a job in 6 days and Priya in 12 days. Karan works alone for 4 days and then stops. Priya finishes the rest. How many days does Priya take?
- 8.Rohan can finish a job in 4 days and Karan in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 9.Aarav works twice as fast as Zoya. Together they finish a job in 11 days. How many days would Zoya take alone?
- 10.Rohan and Saanvi together finish a job in 2 days. Rohan alone takes 6 days. How many days would Saanvi take alone?
- 11.Vivaan works twice as fast as Rahul. Together they finish a job in 5 days. How many days would Rahul take alone?
- 12.Pooja can finish a job in 4 days and Arjun in 28 days. Pooja works alone for 3 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 13.Isha can finish a job in 5 days and Dev in 25 days. Isha works alone for 3 days and then stops. Dev finishes the rest. How many days does Dev take?
- 14.Saanvi can finish a job in 16 days and Pooja in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Ananya works twice as fast as Arjun. Together they finish a job in 9 days. How many days would Arjun take alone?
- 16.Pooja can finish a job in 18 days and Vivaan in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 17.Aditya can finish a job in 19 days and Sneha in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Saanvi can finish a job in 15 days and Dev in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 19.Saanvi can finish a job in 9 days and Aarav in 27 days. Saanvi works alone for 3 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 20.Kabir works twice as fast as Karan. Together they finish a job in 11 days. How many days would Karan take alone?
- 21.Sneha works twice as fast as Meera. Together they finish a job in 7 days. How many days would Meera take alone?
- 22.Sneha can finish a job in 7 days and Vivaan in 18 days. What fraction of the job do they finish if they work together for 1 day? =
- 23.Meera can finish a job in 15 days and Manav in 12 days. What fraction of the job do they finish if they work together for 1 day? =
- 24.Meera can finish a job in 9 days and Rohan in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 25.Karan can finish a job in 4 days and Dev in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 26.Ishaan can finish a job in 24 days and Isha in 16 days. Ishaan works alone for 6 days and then stops. Isha finishes the rest. How many days does Isha take?
- 27.Meera can finish a job in 19 days and Isha in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Rohan can finish a job in 5 days and Arjun in 25 days. Rohan works alone for 3 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 29.Zoya and Arjun together finish a job in 3 days. Zoya alone takes 4 days. How many days would Arjun take alone?
- 30.Isha can finish a job in 18 days and Karan in 30 days. Isha works alone for 12 days and then stops. Karan finishes the rest. How many days does Karan take?
- 31.Saanvi can finish a job in 7 days and Nisha in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Meera can finish a job in 6 days and Priya in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 33.Aarav and Pooja together finish a job in 4 days. Aarav alone takes 5 days. How many days would Pooja take alone?
- 34.Ishaan and Arjun together finish a job in 2 days. Ishaan alone takes 3 days. How many days would Arjun take alone?
- 35.Rohan can finish a job in 24 days and Ananya in 21 days. Rohan works alone for 8 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 36.Aditya and Kabir together finish a job in 7 days. Aditya alone takes 8 days. How many days would Kabir take alone?
- 37.Aarav can finish a job in 7 days and Aditya in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Tara can finish a job in 20 days and Saanvi in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Nisha can finish a job in 8 days and Kabir in 15 days. What fraction of the job do they finish if they work together for 2 days? =
- 40.Kabir can finish a job in 11 days and Karan in 13 days. What fraction of the job do they finish if they work together for 2 days? =
Answer key
- 20
- 3/4
- 20
- 15
- 6
- 33
- 4
- 36/13
- 33
- 3
- 15
- 7
- 10
- 80/9
- 27
- 31/78
- 76/23
- 29/105
- 18
- 33
- 21
- 25/126
- 3/20
- 14/45
- 36/11
- 12
- 228/31
- 10
- 12
- 10
- 105/22
- 10/21
- 20
- 6
- 14
- 56
- 42/13
- 60/23
- 23/60
- 48/143