Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Farhan can finish a job in 25 days and Pooja in 30 days. Farhan works alone for 5 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 2.Aarav can finish a job in 26 days and Dev in 14 days. Aarav works alone for 13 days and then stops. Dev finishes the rest. How many days does Dev take?
- 3.Arjun can finish a job in 19 days and Isha in 11 days. What fraction of the job do they finish if they work together for 3 days? =
- 4.Aarav and Tara together finish a job in 2 days. Aarav alone takes 3 days. How many days would Tara take alone?
- 5.Nisha and Farhan together finish a job in 6 days. Nisha alone takes 8 days. How many days would Farhan take alone?
- 6.Kavya and Rohan together finish a job in 2 days. Kavya alone takes 3 days. How many days would Rohan take alone?
- 7.Ishaan can finish a job in 7 days and Dev in 28 days. Ishaan works alone for 1 day and then stops. Dev finishes the rest. How many days does Dev take?
- 8.Ananya can finish a job in 30 days and Aarav in 4 days. Ananya works alone for 15 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 9.Meera can finish a job in 18 days and Dev in 15 days. What fraction of the job do they finish if they work together for 2 days? =
- 10.Nisha can finish a job in 6 days and Aarav in 18 days. Nisha works alone for 2 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 11.Karan can finish a job in 17 days and Vivaan in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Ananya can finish a job in 2 days and Aditya in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Nisha can finish a job in 9 days and Meera in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Farhan can finish a job in 17 days and Karan in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Kabir can finish a job in 8 days and Dev in 20 days. What fraction of the job do they finish if they work together for 2 days? =
- 16.Kabir works three times as fast as Ananya. Together they finish a job in 5 days. How many days would Ananya take alone?
- 17.Rahul can finish a job in 9 days and Karan in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Meera can finish a job in 18 days and Isha in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Rahul can finish a job in 10 days and Aarav in 18 days. Rahul works alone for 5 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 20.Rahul can finish a job in 17 days and Vivaan in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Aarav can finish a job in 10 days and Tara in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Farhan can finish a job in 13 days and Ananya in 10 days. What fraction of the job do they finish if they work together for 3 days? =
- 23.Tara can finish a job in 14 days and Diya in 28 days. Tara works alone for 1 day and then stops. Diya finishes the rest. How many days does Diya take?
- 24.Kabir can finish a job in 14 days and Isha in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 25.Farhan can finish a job in 12 days and Manav in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 26.Meera can finish a job in 6 days and Manav in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Zoya can finish a job in 9 days and Kavya in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 28.Rahul can finish a job in 9 days and Pooja in 24 days. Rahul works alone for 6 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 29.Manav can finish a job in 19 days and Isha in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 30.Dev works twice as fast as Aarav. Together they finish a job in 8 days. How many days would Aarav take alone?
- 31.Manav can finish a job in 14 days and Zoya in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Rohan can finish a job in 15 days and Sneha in 10 days. Rohan works alone for 9 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 33.Kavya and Meera together finish a job in 4 days. Kavya alone takes 5 days. How many days would Meera take alone?
- 34.Isha works three times as fast as Tara. Together they finish a job in 9 days. How many days would Tara take alone?
- 35.Farhan can finish a job in 5 days and Meera in 25 days. Farhan works alone for 1 day and then stops. Meera finishes the rest. How many days does Meera take?
- 36.Kabir can finish a job in 12 days and Ishaan in 30 days. Kabir works alone for 6 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 37.Ananya works twice as fast as Tara. Together they finish a job in 7 days. How many days would Tara take alone?
- 38.Pooja can finish a job in 14 days and Zoya in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Tara can finish a job in 11 days and Meera in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Isha works twice as fast as Saanvi. Together they finish a job in 2 days. How many days would Saanvi take alone?
Answer key
- 24
- 7
- 90/209
- 6
- 24
- 6
- 24
- 2
- 11/45
- 12
- 119/24
- 3/2
- 36/7
- 170/27
- 7/20
- 20
- 45/8
- 234/31
- 9
- 204/29
- 35/6
- 69/130
- 26
- 15/56
- 36/5
- 15/4
- 19/90
- 8
- 37/171
- 24
- 126/23
- 4
- 20
- 36
- 20
- 15
- 21
- 14/3
- 55/16
- 6
Free quantitative aptitude lessons, practice and worksheets at talentjr.in/quantitative-aptitude