Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Kabir can finish a job in 20 days and Dev in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Ananya can finish a job in 3 days and Arjun in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 3.Manav can finish a job in 4 days and Kabir in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Arjun works three times as fast as Diya. Together they finish a job in 11 days. How many days would Diya take alone?
- 5.Manav can finish a job in 5 days and Ananya in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Diya can finish a job in 9 days and Kavya in 21 days. Diya works alone for 6 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 7.Pooja works twice as fast as Kavya. Together they finish a job in 6 days. How many days would Kavya take alone?
- 8.Kavya can finish a job in 22 days and Pooja in 8 days. Kavya works alone for 11 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 9.Zoya can finish a job in 12 days and Ishaan in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 10.Ananya can finish a job in 11 days and Vivaan in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Sneha can finish a job in 14 days and Pooja in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 12.Vivaan can finish a job in 28 days and Farhan in 12 days. Vivaan works alone for 7 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 13.Rohan can finish a job in 5 days and Manav in 17 days. What fraction of the job do they finish if they work together for 3 days? =
- 14.Aditya can finish a job in 6 days and Saanvi in 12 days. Aditya works alone for 1 day and then stops. Saanvi finishes the rest. How many days does Saanvi take?
- 15.Meera can finish a job in 13 days and Arjun in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Rahul can finish a job in 15 days and Kavya in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Kabir can finish a job in 8 days and Nisha in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Karan can finish a job in 11 days and Meera in 10 days. What fraction of the job do they finish if they work together for 3 days? =
- 19.Aarav can finish a job in 4 days and Nisha in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 20.Dev can finish a job in 18 days and Diya in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Arjun and Isha together finish a job in 3 days. Arjun alone takes 4 days. How many days would Isha take alone?
- 22.Pooja can finish a job in 8 days and Dev in 10 days. What fraction of the job do they finish if they work together for 3 days? =
- 23.Kavya and Farhan together finish a job in 3 days. Kavya alone takes 4 days. How many days would Farhan take alone?
- 24.Nisha can finish a job in 16 days and Ishaan in 28 days. Nisha works alone for 12 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 25.Aarav can finish a job in 16 days and Farhan in 20 days. Aarav works alone for 4 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 26.Ananya and Aditya together finish a job in 4 days. Ananya alone takes 5 days. How many days would Aditya take alone?
- 27.Farhan can finish a job in 9 days and Zoya in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 28.Diya works twice as fast as Zoya. Together they finish a job in 5 days. How many days would Zoya take alone?
- 29.Karan and Kabir together finish a job in 12 days. Karan alone takes 16 days. How many days would Kabir take alone?
- 30.Arjun can finish a job in 11 days and Rahul in 22 days. Arjun works alone for 4 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 31.Kabir can finish a job in 19 days and Rahul in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 32.Pooja and Kavya together finish a job in 2 days. Pooja alone takes 3 days. How many days would Kavya take alone?
- 33.Vivaan and Farhan together finish a job in 2 days. Vivaan alone takes 3 days. How many days would Farhan take alone?
- 34.Pooja can finish a job in 4 days and Arjun in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Manav and Vivaan together finish a job in 10 days. Manav alone takes 15 days. How many days would Vivaan take alone?
- 36.Dev works three times as fast as Meera. Together they finish a job in 3 days. How many days would Meera take alone?
- 37.Kabir can finish a job in 4 days and Arjun in 12 days. What fraction of the job do they finish if they work together for 1 day? =
- 38.Isha can finish a job in 4 days and Meera in 14 days. What fraction of the job do they finish if they work together for 1 day? =
- 39.Isha works three times as fast as Aditya. Together they finish a job in 4 days. How many days would Aditya take alone?
- 40.Farhan and Zoya together finish a job in 8 days. Farhan alone takes 9 days. How many days would Zoya take alone?
Answer key
- 60/23
- 5/2
- 68/21
- 44
- 10/7
- 7
- 18
- 4
- 3/4
- 187/28
- 6/35
- 9
- 66/85
- 10
- 221/30
- 30/7
- 40/7
- 63/110
- 12/5
- 72/13
- 12
- 27/40
- 12
- 7
- 15
- 20
- 14/45
- 15
- 48
- 14
- 29/190
- 6
- 6
- 8/3
- 30
- 12
- 1/3
- 9/28
- 16
- 72