Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Karan can finish a job in 14 days and Sneha in 28 days. Karan works alone for 2 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 2.Pooja works three times as fast as Aarav. Together they finish a job in 11 days. How many days would Aarav take alone?
- 3.Meera can finish a job in 20 days and Aditya in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Manav can finish a job in 16 days and Rohan in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Vivaan can finish a job in 5 days and Saanvi in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 6.Aditya can finish a job in 2 days and Nisha in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Tara works twice as fast as Nisha. Together they finish a job in 8 days. How many days would Nisha take alone?
- 8.Priya can finish a job in 8 days and Ishaan in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 9.Saanvi can finish a job in 10 days and Manav in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Meera can finish a job in 28 days and Arjun in 14 days. Meera works alone for 4 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 11.Kabir can finish a job in 17 days and Priya in 15 days. What fraction of the job do they finish if they work together for 3 days? =
- 12.Karan can finish a job in 12 days and Saanvi in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Saanvi works twice as fast as Tara. Together they finish a job in 9 days. How many days would Tara take alone?
- 14.Farhan works three times as fast as Aarav. Together they finish a job in 3 days. How many days would Aarav take alone?
- 15.Zoya can finish a job in 10 days and Priya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Manav can finish a job in 7 days and Nisha in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Arjun can finish a job in 6 days and Kavya in 24 days. Arjun works alone for 3 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 18.Arjun can finish a job in 30 days and Zoya in 8 days. Arjun works alone for 15 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 19.Dev and Rohan together finish a job in 2 days. Dev alone takes 3 days. How many days would Rohan take alone?
- 20.Manav and Aarav together finish a job in 3 days. Manav alone takes 6 days. How many days would Aarav take alone?
- 21.Diya can finish a job in 14 days and Arjun in 28 days. Diya works alone for 3 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 22.Aarav works three times as fast as Meera. Together they finish a job in 10 days. How many days would Meera take alone?
- 23.Pooja and Kabir together finish a job in 3 days. Pooja alone takes 6 days. How many days would Kabir take alone?
- 24.Zoya and Aarav together finish a job in 6 days. Zoya alone takes 18 days. How many days would Aarav take alone?
- 25.Pooja works three times as fast as Rohan. Together they finish a job in 3 days. How many days would Rohan take alone?
- 26.Arjun can finish a job in 4 days and Zoya in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Rohan can finish a job in 28 days and Nisha in 21 days. Rohan works alone for 8 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 28.Arjun can finish a job in 8 days and Aditya in 20 days. What fraction of the job do they finish if they work together for 2 days? =
- 29.Meera can finish a job in 15 days and Sneha in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 30.Karan can finish a job in 4 days and Aditya in 8 days. Karan works alone for 1 day and then stops. Aditya finishes the rest. How many days does Aditya take?
- 31.Priya can finish a job in 5 days and Tara in 4 days. What fraction of the job do they finish if they work together for 1 day? =
- 32.Ishaan can finish a job in 16 days and Manav in 15 days. What fraction of the job do they finish if they work together for 1 day? =
- 33.Zoya and Isha together finish a job in 12 days. Zoya alone takes 20 days. How many days would Isha take alone?
- 34.Manav can finish a job in 15 days and Tara in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Diya can finish a job in 6 days and Vivaan in 30 days. Diya works alone for 4 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 36.Dev can finish a job in 15 days and Farhan in 20 days. What fraction of the job do they finish if they work together for 1 day? =
- 37.Aditya can finish a job in 12 days and Priya in 8 days. Aditya works alone for 3 days and then stops. Priya finishes the rest. How many days does Priya take?
- 38.Meera works twice as fast as Dev. Together they finish a job in 2 days. How many days would Dev take alone?
- 39.Arjun can finish a job in 25 days and Karan in 5 days. Arjun works alone for 20 days and then stops. Karan finishes the rest. How many days does Karan take?
- 40.Aditya can finish a job in 16 days and Diya in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
Answer key
- 24
- 44
- 140/27
- 48/7
- 3/10
- 3/2
- 24
- 152/27
- 170/27
- 12
- 32/85
- 4
- 27
- 12
- 45/7
- 91/20
- 12
- 4
- 6
- 6
- 22
- 40
- 6
- 9
- 12
- 36/13
- 15
- 7/20
- 60/19
- 6
- 9/20
- 31/240
- 30
- 6
- 10
- 7/60
- 6
- 6
- 1
- 112/23