Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Zoya can finish a job in 6 days and Aarav in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Nisha and Manav together finish a job in 12 days. Nisha alone takes 20 days. How many days would Manav take alone?
- 3.Rahul works three times as fast as Kavya. Together they finish a job in 5 days. How many days would Kavya take alone?
- 4.Zoya can finish a job in 4 days and Rohan in 10 days. Zoya works alone for 2 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 5.Rohan and Zoya together finish a job in 3 days. Rohan alone takes 6 days. How many days would Zoya take alone?
- 6.Isha can finish a job in 7 days and Zoya in 28 days. Isha works alone for 3 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 7.Arjun works twice as fast as Kabir. Together they finish a job in 7 days. How many days would Kabir take alone?
- 8.Rahul can finish a job in 15 days and Arjun in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 9.Priya can finish a job in 21 days and Kabir in 14 days. Priya works alone for 12 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 10.Manav can finish a job in 4 days and Kabir in 8 days. Manav works alone for 3 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 11.Farhan can finish a job in 17 days and Tara in 4 days. What fraction of the job do they finish if they work together for 2 days? =
- 12.Aarav can finish a job in 7 days and Diya in 14 days. Aarav works alone for 4 days and then stops. Diya finishes the rest. How many days does Diya take?
- 13.Zoya and Rahul together finish a job in 3 days. Zoya alone takes 4 days. How many days would Rahul take alone?
- 14.Meera can finish a job in 15 days and Karan in 14 days. What fraction of the job do they finish if they work together for 3 days? =
- 15.Kavya and Zoya together finish a job in 5 days. Kavya alone takes 6 days. How many days would Zoya take alone?
- 16.Farhan works three times as fast as Arjun. Together they finish a job in 11 days. How many days would Arjun take alone?
- 17.Karan can finish a job in 14 days and Nisha in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Ananya works three times as fast as Dev. Together they finish a job in 4 days. How many days would Dev take alone?
- 19.Ishaan can finish a job in 12 days and Pooja in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 20.Zoya can finish a job in 18 days and Arjun in 27 days. Zoya works alone for 4 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 21.Isha can finish a job in 4 days and Priya in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Tara and Pooja together finish a job in 2 days. Tara alone takes 3 days. How many days would Pooja take alone?
- 23.Sneha can finish a job in 5 days and Meera in 15 days. Sneha works alone for 4 days and then stops. Meera finishes the rest. How many days does Meera take?
- 24.Tara can finish a job in 13 days and Isha in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 25.Karan can finish a job in 21 days and Kabir in 24 days. Karan works alone for 14 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 26.Pooja can finish a job in 5 days and Dev in 25 days. Pooja works alone for 3 days and then stops. Dev finishes the rest. How many days does Dev take?
- 27.Rohan works twice as fast as Arjun. Together they finish a job in 12 days. How many days would Arjun take alone?
- 28.Rahul can finish a job in 2 days and Zoya in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Kavya can finish a job in 8 days and Ishaan in 5 days. What fraction of the job do they finish if they work together for 3 days? =
- 30.Nisha can finish a job in 19 days and Rohan in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Pooja and Karan together finish a job in 6 days. Pooja alone takes 12 days. How many days would Karan take alone?
- 32.Zoya and Farhan together finish a job in 4 days. Zoya alone takes 5 days. How many days would Farhan take alone?
- 33.Aditya can finish a job in 12 days and Karan in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Meera can finish a job in 5 days and Pooja in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Diya can finish a job in 19 days and Saanvi in 7 days. What fraction of the job do they finish if they work together for 1 day? =
- 36.Dev can finish a job in 14 days and Nisha in 20 days. What fraction of the job do they finish if they work together for 3 days? =
- 37.Tara and Karan together finish a job in 8 days. Tara alone takes 24 days. How many days would Karan take alone?
- 38.Saanvi can finish a job in 8 days and Isha in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Meera can finish a job in 11 days and Zoya in 5 days. What fraction of the job do they finish if they work together for 3 days? =
- 40.Tara and Sneha together finish a job in 3 days. Tara alone takes 4 days. How many days would Sneha take alone?
Answer key
- 4
- 30
- 20
- 5
- 6
- 16
- 21
- 105/22
- 6
- 2
- 21/34
- 6
- 12
- 29/70
- 30
- 44
- 42/17
- 16
- 204/29
- 21
- 3
- 6
- 3
- 23/130
- 8
- 10
- 36
- 26/15
- 39/40
- 171/28
- 12
- 20
- 48/7
- 20/9
- 26/133
- 51/140
- 12
- 136/25
- 48/55
- 12