Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Ishaan can finish a job in 10 days and Karan in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Dev can finish a job in 4 days and Vivaan in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 3.Meera can finish a job in 6 days and Diya in 30 days. Meera works alone for 4 days and then stops. Diya finishes the rest. How many days does Diya take?
- 4.Ishaan can finish a job in 26 days and Pooja in 13 days. Ishaan works alone for 24 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 5.Aditya can finish a job in 19 days and Sneha in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Meera and Karan together finish a job in 5 days. Meera alone takes 10 days. How many days would Karan take alone?
- 7.Kavya can finish a job in 9 days and Dev in 16 days. What fraction of the job do they finish if they work together for 3 days? =
- 8.Tara works twice as fast as Sneha. Together they finish a job in 7 days. How many days would Sneha take alone?
- 9.Ishaan works three times as fast as Kavya. Together they finish a job in 9 days. How many days would Kavya take alone?
- 10.Manav can finish a job in 12 days and Zoya in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Karan can finish a job in 21 days and Diya in 7 days. Karan works alone for 6 days and then stops. Diya finishes the rest. How many days does Diya take?
- 12.Kavya and Pooja together finish a job in 3 days. Kavya alone takes 12 days. How many days would Pooja take alone?
- 13.Farhan and Kavya together finish a job in 3 days. Farhan alone takes 4 days. How many days would Kavya take alone?
- 14.Kabir and Aarav together finish a job in 4 days. Kabir alone takes 5 days. How many days would Aarav take alone?
- 15.Rahul can finish a job in 20 days and Rohan in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Ishaan works three times as fast as Kabir. Together they finish a job in 2 days. How many days would Kabir take alone?
- 17.Saanvi and Kabir together finish a job in 2 days. Saanvi alone takes 3 days. How many days would Kabir take alone?
- 18.Kavya can finish a job in 4 days and Diya in 20 days. Kavya works alone for 3 days and then stops. Diya finishes the rest. How many days does Diya take?
- 19.Pooja and Zoya together finish a job in 4 days. Pooja alone takes 5 days. How many days would Zoya take alone?
- 20.Aditya and Arjun together finish a job in 4 days. Aditya alone takes 5 days. How many days would Arjun take alone?
- 21.Arjun can finish a job in 6 days and Saanvi in 12 days. What fraction of the job do they finish if they work together for 3 days? =
- 22.Isha works three times as fast as Rohan. Together they finish a job in 6 days. How many days would Rohan take alone?
- 23.Zoya and Isha together finish a job in 7 days. Zoya alone takes 8 days. How many days would Isha take alone?
- 24.Isha and Karan together finish a job in 7 days. Isha alone takes 14 days. How many days would Karan take alone?
- 25.Dev works three times as fast as Aarav. Together they finish a job in 7 days. How many days would Aarav take alone?
- 26.Pooja can finish a job in 8 days and Kavya in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Arjun can finish a job in 9 days and Nisha in 7 days. What fraction of the job do they finish if they work together for 1 day? =
- 28.Sneha and Manav together finish a job in 16 days. Sneha alone takes 24 days. How many days would Manav take alone?
- 29.Saanvi can finish a job in 8 days and Aarav in 24 days. Saanvi works alone for 6 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 30.Sneha can finish a job in 5 days and Diya in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Meera works three times as fast as Saanvi. Together they finish a job in 5 days. How many days would Saanvi take alone?
- 32.Meera works twice as fast as Saanvi. Together they finish a job in 4 days. How many days would Saanvi take alone?
- 33.Kabir can finish a job in 15 days and Arjun in 4 days. What fraction of the job do they finish if they work together for 2 days? =
- 34.Pooja and Rohan together finish a job in 6 days. Pooja alone takes 18 days. How many days would Rohan take alone?
- 35.Rohan can finish a job in 12 days and Saanvi in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Farhan can finish a job in 8 days and Aditya in 7 days. What fraction of the job do they finish if they work together for 3 days? =
- 37.Kabir and Pooja together finish a job in 2 days. Kabir alone takes 3 days. How many days would Pooja take alone?
- 38.Dev can finish a job in 13 days and Aditya in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Karan works three times as fast as Aarav. Together they finish a job in 9 days. How many days would Aarav take alone?
- 40.Arjun can finish a job in 12 days and Vivaan in 4 days. What fraction of the job do they finish if they work together for 2 days? =
Answer key
- 10/3
- 7/20
- 10
- 1
- 247/32
- 10
- 25/48
- 21
- 36
- 15/2
- 5
- 4
- 12
- 20
- 60/13
- 8
- 6
- 5
- 20
- 20
- 3/4
- 24
- 56
- 14
- 28
- 40/7
- 16/63
- 48
- 6
- 30/11
- 20
- 12
- 19/30
- 9
- 12/7
- 45/56
- 6
- 156/25
- 36
- 2/3