Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Priya works three times as fast as Ananya. Together they finish a job in 9 days. How many days would Ananya take alone?
- 2.Aarav and Diya together finish a job in 4 days. Aarav alone takes 6 days. How many days would Diya take alone?
- 3.Dev can finish a job in 10 days and Saanvi in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Manav can finish a job in 13 days and Arjun in 26 days. Manav works alone for 7 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 5.Meera can finish a job in 5 days and Karan in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Dev can finish a job in 14 days and Isha in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Farhan can finish a job in 4 days and Vivaan in 28 days. Farhan works alone for 3 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 8.Ishaan and Zoya together finish a job in 12 days. Ishaan alone takes 18 days. How many days would Zoya take alone?
- 9.Rohan can finish a job in 15 days and Meera in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Zoya can finish a job in 3 days and Arjun in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Vivaan and Pooja together finish a job in 6 days. Vivaan alone takes 9 days. How many days would Pooja take alone?
- 12.Isha can finish a job in 9 days and Saanvi in 4 days. What fraction of the job do they finish if they work together for 2 days? =
- 13.Arjun and Aditya together finish a job in 2 days. Arjun alone takes 6 days. How many days would Aditya take alone?
- 14.Kabir works three times as fast as Diya. Together they finish a job in 2 days. How many days would Diya take alone?
- 15.Aarav can finish a job in 3 days and Nisha in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Isha works three times as fast as Pooja. Together they finish a job in 12 days. How many days would Pooja take alone?
- 17.Rahul and Kavya together finish a job in 3 days. Rahul alone takes 6 days. How many days would Kavya take alone?
- 18.Rahul and Saanvi together finish a job in 9 days. Rahul alone takes 12 days. How many days would Saanvi take alone?
- 19.Pooja and Nisha together finish a job in 14 days. Pooja alone takes 28 days. How many days would Nisha take alone?
- 20.Vivaan can finish a job in 20 days and Rohan in 12 days. What fraction of the job do they finish if they work together for 2 days? =
- 21.Meera can finish a job in 7 days and Ananya in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Pooja can finish a job in 6 days and Kabir in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Manav and Saanvi together finish a job in 9 days. Manav alone takes 10 days. How many days would Saanvi take alone?
- 24.Rohan works three times as fast as Ishaan. Together they finish a job in 9 days. How many days would Ishaan take alone?
- 25.Saanvi and Diya together finish a job in 16 days. Saanvi alone takes 24 days. How many days would Diya take alone?
- 26.Karan and Kavya together finish a job in 3 days. Karan alone takes 4 days. How many days would Kavya take alone?
- 27.Farhan and Aarav together finish a job in 3 days. Farhan alone takes 4 days. How many days would Aarav take alone?
- 28.Aditya can finish a job in 14 days and Isha in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Kabir can finish a job in 25 days and Isha in 20 days. Kabir works alone for 20 days and then stops. Isha finishes the rest. How many days does Isha take?
- 30.Meera works twice as fast as Nisha. Together they finish a job in 7 days. How many days would Nisha take alone?
- 31.Dev and Isha together finish a job in 5 days. Dev alone takes 6 days. How many days would Isha take alone?
- 32.Karan works three times as fast as Vivaan. Together they finish a job in 11 days. How many days would Vivaan take alone?
- 33.Vivaan can finish a job in 6 days and Dev in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Zoya can finish a job in 8 days and Diya in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 35.Dev can finish a job in 18 days and Rohan in 19 days. What fraction of the job do they finish if they work together for 2 days? =
- 36.Manav works three times as fast as Ishaan. Together they finish a job in 8 days. How many days would Ishaan take alone?
- 37.Vivaan can finish a job in 7 days and Zoya in 28 days. Vivaan works alone for 6 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 38.Kabir can finish a job in 14 days and Zoya in 28 days. Kabir works alone for 1 day and then stops. Zoya finishes the rest. How many days does Zoya take?
- 39.Manav and Meera together finish a job in 12 days. Manav alone takes 30 days. How many days would Meera take alone?
- 40.Nisha can finish a job in 4 days and Meera in 22 days. Nisha works alone for 2 days and then stops. Meera finishes the rest. How many days does Meera take?
Answer key
- 36
- 12
- 170/27
- 12
- 95/24
- 63/8
- 7
- 36
- 60/19
- 12/5
- 18
- 13/18
- 3
- 8
- 5/2
- 48
- 6
- 36
- 28
- 4/15
- 14/9
- 9/2
- 90
- 36
- 48
- 12
- 12
- 140/17
- 4
- 21
- 30
- 44
- 30/11
- 9/40
- 37/171
- 32
- 4
- 26
- 20
- 11