Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Zoya and Farhan together finish a job in 4 days. Zoya alone takes 5 days. How many days would Farhan take alone?
- 2.Farhan can finish a job in 4 days and Rahul in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 3.Tara and Aditya together finish a job in 6 days. Tara alone takes 9 days. How many days would Aditya take alone?
- 4.Karan works three times as fast as Priya. Together they finish a job in 5 days. How many days would Priya take alone?
- 5.Kabir works twice as fast as Pooja. Together they finish a job in 6 days. How many days would Pooja take alone?
- 6.Zoya can finish a job in 10 days and Priya in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Aarav can finish a job in 18 days and Saanvi in 14 days. What fraction of the job do they finish if they work together for 1 day? =
- 8.Nisha and Vivaan together finish a job in 2 days. Nisha alone takes 3 days. How many days would Vivaan take alone?
- 9.Arjun can finish a job in 18 days and Aarav in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Meera can finish a job in 18 days and Rohan in 17 days. What fraction of the job do they finish if they work together for 2 days? =
- 11.Kavya can finish a job in 4 days and Arjun in 20 days. Kavya works alone for 2 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 12.Kabir can finish a job in 17 days and Ananya in 4 days. What fraction of the job do they finish if they work together for 3 days? =
- 13.Aditya can finish a job in 9 days and Saanvi in 16 days. What fraction of the job do they finish if they work together for 1 day? =
- 14.Arjun can finish a job in 13 days and Rohan in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Arjun works three times as fast as Priya. Together they finish a job in 7 days. How many days would Priya take alone?
- 16.Rohan can finish a job in 12 days and Farhan in 4 days. Rohan works alone for 3 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 17.Arjun can finish a job in 7 days and Ishaan in 14 days. Arjun works alone for 6 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 18.Arjun can finish a job in 5 days and Isha in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Karan and Nisha together finish a job in 4 days. Karan alone takes 8 days. How many days would Nisha take alone?
- 20.Aditya can finish a job in 6 days and Arjun in 8 days. What fraction of the job do they finish if they work together for 3 days? =
- 21.Ananya can finish a job in 8 days and Zoya in 24 days. Ananya works alone for 7 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 22.Vivaan works three times as fast as Manav. Together they finish a job in 6 days. How many days would Manav take alone?
- 23.Dev works three times as fast as Diya. Together they finish a job in 3 days. How many days would Diya take alone?
- 24.Saanvi can finish a job in 9 days and Karan in 27 days. Saanvi works alone for 1 day and then stops. Karan finishes the rest. How many days does Karan take?
- 25.Karan can finish a job in 13 days and Rohan in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 26.Kabir and Aarav together finish a job in 6 days. Kabir alone takes 18 days. How many days would Aarav take alone?
- 27.Arjun works twice as fast as Zoya. Together they finish a job in 12 days. How many days would Zoya take alone?
- 28.Rahul can finish a job in 2 days and Aditya in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Farhan and Rohan together finish a job in 16 days. Farhan alone takes 20 days. How many days would Rohan take alone?
- 30.Aarav can finish a job in 5 days and Arjun in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 31.Rahul works twice as fast as Sneha. Together they finish a job in 3 days. How many days would Sneha take alone?
- 32.Rohan can finish a job in 28 days and Farhan in 14 days. Rohan works alone for 12 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 33.Meera can finish a job in 21 days and Vivaan in 14 days. Meera works alone for 12 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 34.Arjun can finish a job in 20 days and Kabir in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Nisha can finish a job in 4 days and Manav in 15 days. What fraction of the job do they finish if they work together for 1 day? =
- 36.Meera works twice as fast as Diya. Together they finish a job in 5 days. How many days would Diya take alone?
- 37.Sneha works three times as fast as Isha. Together they finish a job in 4 days. How many days would Isha take alone?
- 38.Arjun can finish a job in 21 days and Kavya in 6 days. Arjun works alone for 14 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 39.Nisha and Karan together finish a job in 3 days. Nisha alone takes 6 days. How many days would Karan take alone?
- 40.Zoya can finish a job in 12 days and Manav in 6 days. What fraction of the job do they finish if they work together for 1 day? =
Answer key
- 20
- 5/6
- 18
- 20
- 18
- 15/4
- 8/63
- 6
- 36/11
- 35/153
- 10
- 63/68
- 25/144
- 104/21
- 28
- 3
- 2
- 10/3
- 8
- 7/8
- 3
- 24
- 12
- 24
- 39/16
- 9
- 36
- 34/19
- 80
- 23/45
- 9
- 8
- 6
- 140/17
- 19/60
- 15
- 16
- 2
- 6
- 1/4