Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Ananya can finish a job in 11 days and Isha in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Manav works twice as fast as Meera. Together they finish a job in 8 days. How many days would Meera take alone?
- 3.Meera and Arjun together finish a job in 3 days. Meera alone takes 4 days. How many days would Arjun take alone?
- 4.Meera works twice as fast as Ananya. Together they finish a job in 4 days. How many days would Ananya take alone?
- 5.Farhan and Kavya together finish a job in 6 days. Farhan alone takes 15 days. How many days would Kavya take alone?
- 6.Meera can finish a job in 4 days and Dev in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Kavya can finish a job in 13 days and Vivaan in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Kavya can finish a job in 7 days and Diya in 28 days. Kavya works alone for 3 days and then stops. Diya finishes the rest. How many days does Diya take?
- 9.Farhan and Meera together finish a job in 6 days. Farhan alone takes 15 days. How many days would Meera take alone?
- 10.Meera works twice as fast as Priya. Together they finish a job in 11 days. How many days would Priya take alone?
- 11.Arjun and Sneha together finish a job in 5 days. Arjun alone takes 6 days. How many days would Sneha take alone?
- 12.Karan can finish a job in 17 days and Diya in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Diya can finish a job in 18 days and Pooja in 10 days. Diya works alone for 9 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 14.Sneha can finish a job in 14 days and Ananya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Ishaan and Aditya together finish a job in 12 days. Ishaan alone takes 18 days. How many days would Aditya take alone?
- 16.Dev can finish a job in 18 days and Isha in 13 days. What fraction of the job do they finish if they work together for 2 days? =
- 17.Rohan can finish a job in 18 days and Nisha in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 18.Priya can finish a job in 15 days and Ananya in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Priya works twice as fast as Isha. Together they finish a job in 4 days. How many days would Isha take alone?
- 20.Meera can finish a job in 10 days and Zoya in 30 days. Meera works alone for 2 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 21.Ananya works twice as fast as Manav. Together they finish a job in 5 days. How many days would Manav take alone?
- 22.Vivaan can finish a job in 18 days and Dev in 8 days. Vivaan works alone for 9 days and then stops. Dev finishes the rest. How many days does Dev take?
- 23.Ishaan works twice as fast as Meera. Together they finish a job in 2 days. How many days would Meera take alone?
- 24.Kabir and Isha together finish a job in 2 days. Kabir alone takes 4 days. How many days would Isha take alone?
- 25.Kavya can finish a job in 9 days and Arjun in 30 days. Kavya works alone for 3 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 26.Pooja can finish a job in 14 days and Farhan in 7 days. Pooja works alone for 12 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 27.Zoya works three times as fast as Arjun. Together they finish a job in 7 days. How many days would Arjun take alone?
- 28.Meera can finish a job in 4 days and Ananya in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 29.Sneha can finish a job in 3 days and Dev in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 30.Ishaan can finish a job in 9 days and Farhan in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Aditya works twice as fast as Rahul. Together they finish a job in 6 days. How many days would Rahul take alone?
- 32.Ishaan can finish a job in 18 days and Diya in 9 days. Ishaan works alone for 6 days and then stops. Diya finishes the rest. How many days does Diya take?
- 33.Sneha can finish a job in 9 days and Ananya in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 34.Saanvi can finish a job in 5 days and Aarav in 12 days. What fraction of the job do they finish if they work together for 3 days? =
- 35.Kabir can finish a job in 19 days and Aarav in 4 days. What fraction of the job do they finish if they work together for 3 days? =
- 36.Saanvi can finish a job in 17 days and Arjun in 10 days. What fraction of the job do they finish if they work together for 2 days? =
- 37.Saanvi can finish a job in 8 days and Manav in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Rahul and Kavya together finish a job in 9 days. Rahul alone takes 12 days. How many days would Kavya take alone?
- 39.Karan works three times as fast as Vivaan. Together they finish a job in 7 days. How many days would Vivaan take alone?
- 40.Pooja can finish a job in 13 days and Rohan in 26 days. Pooja works alone for 3 days and then stops. Rohan finishes the rest. How many days does Rohan take?
Answer key
- 88/19
- 24
- 12
- 12
- 10
- 52/17
- 130/23
- 16
- 10
- 33
- 30
- 102/23
- 5
- 42/17
- 36
- 31/117
- 17/72
- 30/7
- 12
- 24
- 15
- 4
- 6
- 4
- 20
- 1
- 28
- 5/8
- 6/5
- 45/14
- 18
- 6
- 25/72
- 17/20
- 69/76
- 27/85
- 72/17
- 36
- 28
- 20