Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Manav works three times as fast as Tara. Together they finish a job in 8 days. How many days would Tara take alone?
- 2.Farhan works twice as fast as Diya. Together they finish a job in 11 days. How many days would Diya take alone?
- 3.Manav works three times as fast as Sneha. Together they finish a job in 9 days. How many days would Sneha take alone?
- 4.Sneha can finish a job in 6 days and Diya in 18 days. Sneha works alone for 1 day and then stops. Diya finishes the rest. How many days does Diya take?
- 5.Sneha works twice as fast as Nisha. Together they finish a job in 7 days. How many days would Nisha take alone?
- 6.Pooja can finish a job in 19 days and Aditya in 8 days. What fraction of the job do they finish if they work together for 1 day? =
- 7.Zoya and Kabir together finish a job in 4 days. Zoya alone takes 12 days. How many days would Kabir take alone?
- 8.Farhan and Aditya together finish a job in 8 days. Farhan alone takes 16 days. How many days would Aditya take alone?
- 9.Nisha can finish a job in 12 days and Karan in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Kavya can finish a job in 13 days and Aditya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Meera works twice as fast as Dev. Together they finish a job in 7 days. How many days would Dev take alone?
- 12.Rohan can finish a job in 18 days and Isha in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Sneha can finish a job in 3 days and Tara in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Manav can finish a job in 3 days and Ishaan in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Isha and Ananya together finish a job in 15 days. Isha alone takes 18 days. How many days would Ananya take alone?
- 16.Sneha can finish a job in 10 days and Rohan in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Kabir and Tara together finish a job in 6 days. Kabir alone takes 7 days. How many days would Tara take alone?
- 18.Manav can finish a job in 25 days and Isha in 30 days. Manav works alone for 20 days and then stops. Isha finishes the rest. How many days does Isha take?
- 19.Vivaan works twice as fast as Ishaan. Together they finish a job in 8 days. How many days would Ishaan take alone?
- 20.Zoya works twice as fast as Vivaan. Together they finish a job in 10 days. How many days would Vivaan take alone?
- 21.Aditya can finish a job in 19 days and Vivaan in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Tara and Manav together finish a job in 2 days. Tara alone takes 3 days. How many days would Manav take alone?
- 23.Kabir can finish a job in 8 days and Ishaan in 24 days. Kabir works alone for 5 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 24.Pooja can finish a job in 6 days and Sneha in 20 days. Pooja works alone for 3 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 25.Aarav can finish a job in 8 days and Kabir in 16 days. Aarav works alone for 5 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 26.Saanvi can finish a job in 8 days and Vivaan in 5 days. What fraction of the job do they finish if they work together for 3 days? =
- 27.Diya can finish a job in 8 days and Vivaan in 24 days. Diya works alone for 2 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 28.Priya and Kavya together finish a job in 6 days. Priya alone takes 9 days. How many days would Kavya take alone?
- 29.Priya can finish a job in 12 days and Isha in 24 days. Priya works alone for 10 days and then stops. Isha finishes the rest. How many days does Isha take?
- 30.Zoya can finish a job in 19 days and Vivaan in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Zoya can finish a job in 15 days and Kabir in 25 days. Zoya works alone for 9 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 32.Diya can finish a job in 12 days and Sneha in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 33.Rahul can finish a job in 4 days and Meera in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Manav works three times as fast as Aditya. Together they finish a job in 12 days. How many days would Aditya take alone?
- 35.Karan and Saanvi together finish a job in 7 days. Karan alone takes 8 days. How many days would Saanvi take alone?
- 36.Manav and Diya together finish a job in 3 days. Manav alone takes 6 days. How many days would Diya take alone?
- 37.Rahul can finish a job in 12 days and Diya in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Rahul can finish a job in 6 days and Tara in 12 days. Rahul works alone for 1 day and then stops. Tara finishes the rest. How many days does Tara take?
- 39.Kavya can finish a job in 2 days and Tara in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Ananya and Aarav together finish a job in 2 days. Ananya alone takes 6 days. How many days would Aarav take alone?
Answer key
- 32
- 33
- 36
- 15
- 21
- 27/152
- 6
- 16
- 36/7
- 39/16
- 21
- 36/5
- 51/20
- 51/20
- 90
- 80/13
- 42
- 6
- 24
- 30
- 228/31
- 6
- 9
- 10
- 6
- 39/40
- 18
- 18
- 4
- 266/33
- 10
- 1/2
- 12/7
- 48
- 56
- 6
- 60/11
- 10
- 8/5
- 3