Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Meera and Zoya together finish a job in 4 days. Meera alone takes 8 days. How many days would Zoya take alone?
- 2.Vivaan and Meera together finish a job in 3 days. Vivaan alone takes 4 days. How many days would Meera take alone?
- 3.Nisha can finish a job in 8 days and Ishaan in 24 days. Nisha works alone for 4 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 4.Ishaan and Isha together finish a job in 12 days. Ishaan alone takes 30 days. How many days would Isha take alone?
- 5.Kabir can finish a job in 30 days and Isha in 10 days. Kabir works alone for 18 days and then stops. Isha finishes the rest. How many days does Isha take?
- 6.Diya can finish a job in 10 days and Arjun in 24 days. Diya works alone for 5 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 7.Kavya can finish a job in 19 days and Dev in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Diya works three times as fast as Manav. Together they finish a job in 5 days. How many days would Manav take alone?
- 9.Rohan can finish a job in 4 days and Arjun in 24 days. Rohan works alone for 1 day and then stops. Arjun finishes the rest. How many days does Arjun take?
- 10.Diya can finish a job in 13 days and Kabir in 26 days. Diya works alone for 7 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 11.Ananya can finish a job in 13 days and Priya in 10 days. What fraction of the job do they finish if they work together for 2 days? =
- 12.Zoya can finish a job in 7 days and Meera in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 13.Aarav can finish a job in 5 days and Zoya in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Kabir works twice as fast as Rahul. Together they finish a job in 8 days. How many days would Rahul take alone?
- 15.Arjun and Zoya together finish a job in 2 days. Arjun alone takes 4 days. How many days would Zoya take alone?
- 16.Farhan works three times as fast as Ishaan. Together they finish a job in 5 days. How many days would Ishaan take alone?
- 17.Diya can finish a job in 2 days and Kabir in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Meera can finish a job in 9 days and Dev in 11 days. What fraction of the job do they finish if they work together for 3 days? =
- 19.Tara and Kabir together finish a job in 21 days. Tara alone takes 30 days. How many days would Kabir take alone?
- 20.Kabir and Ishaan together finish a job in 3 days. Kabir alone takes 4 days. How many days would Ishaan take alone?
- 21.Arjun can finish a job in 8 days and Ananya in 10 days. What fraction of the job do they finish if they work together for 3 days? =
- 22.Aarav works twice as fast as Priya. Together they finish a job in 7 days. How many days would Priya take alone?
- 23.Karan can finish a job in 5 days and Aditya in 11 days. What fraction of the job do they finish if they work together for 3 days? =
- 24.Aditya works three times as fast as Aarav. Together they finish a job in 11 days. How many days would Aarav take alone?
- 25.Ishaan can finish a job in 9 days and Aarav in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 26.Dev can finish a job in 20 days and Ananya in 15 days. What fraction of the job do they finish if they work together for 1 day? =
- 27.Zoya works twice as fast as Manav. Together they finish a job in 2 days. How many days would Manav take alone?
- 28.Sneha works twice as fast as Meera. Together they finish a job in 2 days. How many days would Meera take alone?
- 29.Ishaan can finish a job in 8 days and Rohan in 20 days. Ishaan works alone for 4 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 30.Aarav works three times as fast as Saanvi. Together they finish a job in 10 days. How many days would Saanvi take alone?
- 31.Karan can finish a job in 11 days and Arjun in 9 days. What fraction of the job do they finish if they work together for 2 days? =
- 32.Karan works twice as fast as Ananya. Together they finish a job in 2 days. How many days would Ananya take alone?
- 33.Ananya can finish a job in 8 days and Priya in 12 days. What fraction of the job do they finish if they work together for 3 days? =
- 34.Dev and Zoya together finish a job in 2 days. Dev alone takes 6 days. How many days would Zoya take alone?
- 35.Rahul can finish a job in 6 days and Ananya in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 36.Isha can finish a job in 9 days and Karan in 12 days. Isha works alone for 3 days and then stops. Karan finishes the rest. How many days does Karan take?
- 37.Arjun works three times as fast as Nisha. Together they finish a job in 3 days. How many days would Nisha take alone?
- 38.Dev and Vivaan together finish a job in 6 days. Dev alone takes 7 days. How many days would Vivaan take alone?
- 39.Arjun can finish a job in 12 days and Rahul in 19 days. What fraction of the job do they finish if they work together for 1 day? =
- 40.Vivaan and Arjun together finish a job in 14 days. Vivaan alone takes 21 days. How many days would Arjun take alone?
Answer key
- 8
- 12
- 12
- 20
- 4
- 12
- 304/35
- 20
- 18
- 12
- 23/65
- 60/91
- 45/14
- 24
- 4
- 20
- 14/9
- 20/33
- 70
- 12
- 27/40
- 21
- 48/55
- 44
- 25/72
- 7/60
- 6
- 6
- 10
- 40
- 40/99
- 6
- 5/8
- 3
- 11/30
- 8
- 12
- 42
- 31/228
- 42