Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Vivaan can finish a job in 3 days and Diya in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Priya can finish a job in 8 days and Aditya in 7 days. What fraction of the job do they finish if they work together for 2 days? =
- 3.Meera can finish a job in 8 days and Farhan in 6 days. What fraction of the job do they finish if they work together for 1 day? =
- 4.Zoya works twice as fast as Saanvi. Together they finish a job in 4 days. How many days would Saanvi take alone?
- 5.Nisha and Rohan together finish a job in 3 days. Nisha alone takes 4 days. How many days would Rohan take alone?
- 6.Manav can finish a job in 17 days and Dev in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Pooja and Zoya together finish a job in 8 days. Pooja alone takes 9 days. How many days would Zoya take alone?
- 8.Nisha and Sneha together finish a job in 3 days. Nisha alone takes 4 days. How many days would Sneha take alone?
- 9.Saanvi works three times as fast as Nisha. Together they finish a job in 3 days. How many days would Nisha take alone?
- 10.Saanvi and Priya together finish a job in 4 days. Saanvi alone takes 5 days. How many days would Priya take alone?
- 11.Rahul and Vivaan together finish a job in 3 days. Rahul alone takes 6 days. How many days would Vivaan take alone?
- 12.Manav can finish a job in 20 days and Isha in 12 days. What fraction of the job do they finish if they work together for 3 days? =
- 13.Zoya can finish a job in 16 days and Rohan in 9 days. What fraction of the job do they finish if they work together for 1 day? =
- 14.Meera can finish a job in 6 days and Farhan in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Saanvi can finish a job in 16 days and Arjun in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Pooja and Rohan together finish a job in 3 days. Pooja alone takes 6 days. How many days would Rohan take alone?
- 17.Tara can finish a job in 7 days and Nisha in 28 days. Tara works alone for 4 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 18.Arjun works twice as fast as Pooja. Together they finish a job in 8 days. How many days would Pooja take alone?
- 19.Nisha can finish a job in 10 days and Aarav in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 20.Isha and Ishaan together finish a job in 7 days. Isha alone takes 8 days. How many days would Ishaan take alone?
- 21.Priya can finish a job in 8 days and Kavya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Rohan can finish a job in 10 days and Manav in 30 days. Rohan works alone for 8 days and then stops. Manav finishes the rest. How many days does Manav take?
- 23.Nisha can finish a job in 8 days and Dev in 16 days. Nisha works alone for 2 days and then stops. Dev finishes the rest. How many days does Dev take?
- 24.Sneha can finish a job in 30 days and Vivaan in 20 days. Sneha works alone for 9 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 25.Kabir can finish a job in 18 days and Ishaan in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 26.Sneha can finish a job in 13 days and Nisha in 6 days. What fraction of the job do they finish if they work together for 1 day? =
- 27.Diya can finish a job in 3 days and Saanvi in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Farhan can finish a job in 6 days and Aarav in 12 days. Farhan works alone for 2 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 29.Farhan and Diya together finish a job in 8 days. Farhan alone takes 12 days. How many days would Diya take alone?
- 30.Rahul works twice as fast as Zoya. Together they finish a job in 8 days. How many days would Zoya take alone?
- 31.Ananya can finish a job in 14 days and Vivaan in 28 days. Ananya works alone for 3 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 32.Saanvi can finish a job in 16 days and Nisha in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Vivaan can finish a job in 6 days and Pooja in 8 days. Vivaan works alone for 3 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 34.Tara and Pooja together finish a job in 9 days. Tara alone takes 10 days. How many days would Pooja take alone?
- 35.Tara can finish a job in 18 days and Karan in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Dev can finish a job in 20 days and Meera in 7 days. What fraction of the job do they finish if they work together for 3 days? =
- 37.Isha can finish a job in 12 days and Diya in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 38.Zoya and Arjun together finish a job in 12 days. Zoya alone takes 24 days. How many days would Arjun take alone?
- 39.Karan can finish a job in 9 days and Nisha in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 40.Meera can finish a job in 18 days and Tara in 17 days. What fraction of the job do they finish if they work together for 3 days? =
Answer key
- 24/11
- 15/28
- 7/24
- 12
- 12
- 85/22
- 72
- 12
- 12
- 20
- 6
- 2/5
- 25/144
- 30/11
- 144/25
- 6
- 12
- 24
- 6
- 56
- 72/13
- 6
- 12
- 14
- 2/3
- 19/78
- 15/8
- 8
- 24
- 24
- 22
- 144/25
- 4
- 90
- 126/25
- 81/140
- 17/60
- 24
- 25/72
- 35/102