Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Tara can finish a job in 20 days and Aditya in 4 days. What fraction of the job do they finish if they work together for 3 days? =
- 2.Ishaan can finish a job in 4 days and Aarav in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 3.Aditya can finish a job in 19 days and Kabir in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Aarav can finish a job in 10 days and Ananya in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Arjun can finish a job in 9 days and Vivaan in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Sneha works three times as fast as Kabir. Together they finish a job in 2 days. How many days would Kabir take alone?
- 7.Sneha can finish a job in 16 days and Ananya in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Pooja and Karan together finish a job in 3 days. Pooja alone takes 6 days. How many days would Karan take alone?
- 9.Priya can finish a job in 5 days and Nisha in 20 days. Priya works alone for 3 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 10.Pooja can finish a job in 27 days and Dev in 30 days. Pooja works alone for 9 days and then stops. Dev finishes the rest. How many days does Dev take?
- 11.Kavya and Kabir together finish a job in 6 days. Kavya alone takes 10 days. How many days would Kabir take alone?
- 12.Karan can finish a job in 16 days and Tara in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Karan can finish a job in 6 days and Zoya in 9 days. Karan works alone for 2 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 14.Rohan and Farhan together finish a job in 8 days. Rohan alone takes 10 days. How many days would Farhan take alone?
- 15.Saanvi and Tara together finish a job in 5 days. Saanvi alone takes 10 days. How many days would Tara take alone?
- 16.Aarav and Meera together finish a job in 10 days. Aarav alone takes 15 days. How many days would Meera take alone?
- 17.Diya works three times as fast as Pooja. Together they finish a job in 8 days. How many days would Pooja take alone?
- 18.Nisha can finish a job in 10 days and Manav in 30 days. Nisha works alone for 4 days and then stops. Manav finishes the rest. How many days does Manav take?
- 19.Karan can finish a job in 8 days and Saanvi in 19 days. What fraction of the job do they finish if they work together for 3 days? =
- 20.Pooja can finish a job in 20 days and Zoya in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 21.Aditya can finish a job in 6 days and Zoya in 8 days. What fraction of the job do they finish if they work together for 1 day? =
- 22.Vivaan can finish a job in 19 days and Farhan in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Saanvi can finish a job in 19 days and Zoya in 14 days. What fraction of the job do they finish if they work together for 3 days? =
- 24.Arjun works three times as fast as Zoya. Together they finish a job in 6 days. How many days would Zoya take alone?
- 25.Arjun can finish a job in 28 days and Ishaan in 12 days. Arjun works alone for 7 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 26.Vivaan can finish a job in 6 days and Rohan in 14 days. Vivaan works alone for 3 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 27.Nisha can finish a job in 13 days and Ishaan in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Rahul can finish a job in 10 days and Kavya in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Pooja can finish a job in 6 days and Farhan in 24 days. Pooja works alone for 1 day and then stops. Farhan finishes the rest. How many days does Farhan take?
- 30.Rohan can finish a job in 16 days and Kavya in 4 days. What fraction of the job do they finish if they work together for 3 days? =
- 31.Ananya works three times as fast as Nisha. Together they finish a job in 9 days. How many days would Nisha take alone?
- 32.Karan works twice as fast as Diya. Together they finish a job in 3 days. How many days would Diya take alone?
- 33.Meera can finish a job in 15 days and Aarav in 11 days. What fraction of the job do they finish if they work together for 2 days? =
- 34.Manav can finish a job in 15 days and Meera in 4 days. What fraction of the job do they finish if they work together for 3 days? =
- 35.Manav and Sneha together finish a job in 4 days. Manav alone takes 5 days. How many days would Sneha take alone?
- 36.Saanvi can finish a job in 6 days and Karan in 18 days. Saanvi works alone for 3 days and then stops. Karan finishes the rest. How many days does Karan take?
- 37.Rohan and Karan together finish a job in 10 days. Rohan alone takes 30 days. How many days would Karan take alone?
- 38.Nisha works three times as fast as Saanvi. Together they finish a job in 12 days. How many days would Saanvi take alone?
- 39.Rohan can finish a job in 21 days and Diya in 6 days. Rohan works alone for 7 days and then stops. Diya finishes the rest. How many days does Diya take?
- 40.Ananya works three times as fast as Zoya. Together they finish a job in 4 days. How many days would Zoya take alone?
Answer key
- 9/10
- 9/14
- 285/34
- 40/9
- 45/14
- 8
- 48/7
- 6
- 8
- 20
- 15
- 240/31
- 6
- 40
- 10
- 30
- 32
- 18
- 81/152
- 99/260
- 7/24
- 228/31
- 99/266
- 24
- 9
- 7
- 182/27
- 10/3
- 20
- 15/16
- 36
- 9
- 52/165
- 19/20
- 20
- 9
- 15
- 48
- 4
- 16
Free quantitative aptitude lessons, practice and worksheets at talentjr.in/quantitative-aptitude