Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Tara can finish a job in 17 days and Aarav in 19 days. What fraction of the job do they finish if they work together for 2 days? =
- 2.Nisha can finish a job in 4 days and Rahul in 10 days. Nisha works alone for 2 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 3.Pooja can finish a job in 12 days and Aditya in 16 days. Pooja works alone for 9 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 4.Rahul can finish a job in 14 days and Ananya in 7 days. Rahul works alone for 12 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 5.Arjun can finish a job in 19 days and Rohan in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Dev works three times as fast as Arjun. Together they finish a job in 6 days. How many days would Arjun take alone?
- 7.Aditya and Farhan together finish a job in 3 days. Aditya alone takes 4 days. How many days would Farhan take alone?
- 8.Dev works three times as fast as Diya. Together they finish a job in 5 days. How many days would Diya take alone?
- 9.Saanvi can finish a job in 6 days and Dev in 17 days. What fraction of the job do they finish if they work together for 2 days? =
- 10.Pooja can finish a job in 14 days and Ananya in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Isha and Ishaan together finish a job in 4 days. Isha alone takes 6 days. How many days would Ishaan take alone?
- 12.Isha can finish a job in 14 days and Zoya in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Priya and Farhan together finish a job in 15 days. Priya alone takes 20 days. How many days would Farhan take alone?
- 14.Rohan can finish a job in 12 days and Dev in 18 days. What fraction of the job do they finish if they work together for 3 days? =
- 15.Diya can finish a job in 10 days and Manav in 20 days. Diya works alone for 2 days and then stops. Manav finishes the rest. How many days does Manav take?
- 16.Arjun can finish a job in 10 days and Priya in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 17.Ishaan and Kabir together finish a job in 5 days. Ishaan alone takes 6 days. How many days would Kabir take alone?
- 18.Nisha can finish a job in 15 days and Saanvi in 13 days. What fraction of the job do they finish if they work together for 1 day? =
- 19.Sneha can finish a job in 15 days and Nisha in 12 days. Sneha works alone for 10 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 20.Zoya can finish a job in 4 days and Ishaan in 24 days. Zoya works alone for 2 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 21.Tara can finish a job in 13 days and Meera in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Aarav and Farhan together finish a job in 2 days. Aarav alone takes 3 days. How many days would Farhan take alone?
- 23.Rahul works three times as fast as Vivaan. Together they finish a job in 5 days. How many days would Vivaan take alone?
- 24.Diya can finish a job in 13 days and Rahul in 8 days. What fraction of the job do they finish if they work together for 3 days? =
- 25.Saanvi can finish a job in 4 days and Aditya in 14 days. Saanvi works alone for 2 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 26.Pooja can finish a job in 15 days and Dev in 24 days. Pooja works alone for 5 days and then stops. Dev finishes the rest. How many days does Dev take?
- 27.Nisha and Rahul together finish a job in 9 days. Nisha alone takes 10 days. How many days would Rahul take alone?
- 28.Aarav can finish a job in 9 days and Nisha in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Zoya can finish a job in 20 days and Karan in 30 days. Zoya works alone for 16 days and then stops. Karan finishes the rest. How many days does Karan take?
- 30.Ananya works three times as fast as Meera. Together they finish a job in 5 days. How many days would Meera take alone?
- 31.Ananya can finish a job in 20 days and Dev in 10 days. Ananya works alone for 10 days and then stops. Dev finishes the rest. How many days does Dev take?
- 32.Ananya works three times as fast as Tara. Together they finish a job in 2 days. How many days would Tara take alone?
- 33.Aarav works twice as fast as Aditya. Together they finish a job in 8 days. How many days would Aditya take alone?
- 34.Nisha can finish a job in 5 days and Kavya in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Aditya can finish a job in 17 days and Dev in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Aarav and Meera together finish a job in 2 days. Aarav alone takes 3 days. How many days would Meera take alone?
- 37.Kavya can finish a job in 2 days and Rohan in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Priya can finish a job in 11 days and Saanvi in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Arjun can finish a job in 6 days and Kabir in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Rohan works three times as fast as Arjun. Together they finish a job in 5 days. How many days would Arjun take alone?
Answer key
- 72/323
- 5
- 4
- 1
- 95/24
- 24
- 12
- 20
- 23/51
- 140/17
- 12
- 126/23
- 60
- 5/12
- 16
- 4/5
- 30
- 28/195
- 4
- 12
- 182/27
- 6
- 20
- 63/104
- 7
- 16
- 90
- 99/20
- 6
- 20
- 5
- 8
- 24
- 85/22
- 323/36
- 6
- 20/11
- 99/20
- 12/5
- 20