Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Rohan can finish a job in 14 days and Pooja in 12 days. What fraction of the job do they finish if they work together for 1 day? =
- 2.Aarav and Pooja together finish a job in 4 days. Aarav alone takes 5 days. How many days would Pooja take alone?
- 3.Vivaan and Farhan together finish a job in 4 days. Vivaan alone takes 5 days. How many days would Farhan take alone?
- 4.Sneha works three times as fast as Rohan. Together they finish a job in 2 days. How many days would Rohan take alone?
- 5.Arjun and Kavya together finish a job in 6 days. Arjun alone takes 18 days. How many days would Kavya take alone?
- 6.Saanvi works three times as fast as Rahul. Together they finish a job in 6 days. How many days would Rahul take alone?
- 7.Rahul can finish a job in 15 days and Pooja in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 8.Farhan can finish a job in 10 days and Diya in 8 days. What fraction of the job do they finish if they work together for 1 day? =
- 9.Dev and Karan together finish a job in 3 days. Dev alone takes 12 days. How many days would Karan take alone?
- 10.Manav can finish a job in 5 days and Ananya in 15 days. Manav works alone for 2 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 11.Vivaan and Ishaan together finish a job in 2 days. Vivaan alone takes 4 days. How many days would Ishaan take alone?
- 12.Kavya and Aarav together finish a job in 6 days. Kavya alone takes 8 days. How many days would Aarav take alone?
- 13.Dev can finish a job in 18 days and Rahul in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Aarav can finish a job in 5 days and Rohan in 4 days. What fraction of the job do they finish if they work together for 1 day? =
- 15.Pooja can finish a job in 9 days and Meera in 15 days. What fraction of the job do they finish if they work together for 2 days? =
- 16.Nisha can finish a job in 12 days and Meera in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Aarav can finish a job in 18 days and Kabir in 6 days. What fraction of the job do they finish if they work together for 1 day? =
- 18.Kabir can finish a job in 2 days and Arjun in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Priya can finish a job in 20 days and Ishaan in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 20.Aarav can finish a job in 11 days and Nisha in 8 days. What fraction of the job do they finish if they work together for 2 days? =
- 21.Karan can finish a job in 20 days and Aarav in 13 days. What fraction of the job do they finish if they work together for 1 day? =
- 22.Farhan can finish a job in 4 days and Aditya in 24 days. Farhan works alone for 1 day and then stops. Aditya finishes the rest. How many days does Aditya take?
- 23.Karan and Arjun together finish a job in 2 days. Karan alone takes 4 days. How many days would Arjun take alone?
- 24.Saanvi can finish a job in 7 days and Aditya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Tara works three times as fast as Manav. Together they finish a job in 8 days. How many days would Manav take alone?
- 26.Isha can finish a job in 3 days and Nisha in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Vivaan can finish a job in 8 days and Rohan in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Vivaan can finish a job in 15 days and Rahul in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 29.Tara works twice as fast as Aarav. Together they finish a job in 12 days. How many days would Aarav take alone?
- 30.Vivaan can finish a job in 7 days and Arjun in 21 days. Vivaan works alone for 6 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 31.Farhan can finish a job in 16 days and Rahul in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Kavya works three times as fast as Meera. Together they finish a job in 8 days. How many days would Meera take alone?
- 33.Diya and Rohan together finish a job in 7 days. Diya alone takes 8 days. How many days would Rohan take alone?
- 34.Rahul can finish a job in 7 days and Rohan in 21 days. Rahul works alone for 3 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 35.Ananya can finish a job in 6 days and Priya in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Kabir can finish a job in 14 days and Nisha in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 37.Pooja works twice as fast as Arjun. Together they finish a job in 6 days. How many days would Arjun take alone?
- 38.Sneha works twice as fast as Aarav. Together they finish a job in 11 days. How many days would Aarav take alone?
- 39.Manav works three times as fast as Kavya. Together they finish a job in 2 days. How many days would Kavya take alone?
- 40.Kabir and Vivaan together finish a job in 7 days. Kabir alone takes 8 days. How many days would Vivaan take alone?
Answer key
- 13/84
- 20
- 20
- 8
- 9
- 24
- 11/45
- 9/40
- 4
- 9
- 4
- 24
- 9/2
- 9/20
- 16/45
- 15/2
- 2/9
- 20/11
- 260/33
- 19/44
- 33/260
- 18
- 4
- 21/10
- 32
- 2
- 152/27
- 7/10
- 36
- 3
- 16/3
- 32
- 56
- 12
- 30/7
- 42/17
- 18
- 33
- 8
- 56