Time and Work Worksheet

Quantitative aptitude lesson 19: Time and work · Set 283 · 40 questions
TalentJR

The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.

NameDateTime takenScore ___ / 40
  1. 1.Karan can finish a job in 10 days and Zoya in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  2. 2.Manav and Rahul together finish a job in 2 days. Manav alone takes 4 days. How many days would Rahul take alone?
  3. 3.Sneha works twice as fast as Manav. Together they finish a job in 10 days. How many days would Manav take alone?
  4. 4.Farhan works twice as fast as Vivaan. Together they finish a job in 2 days. How many days would Vivaan take alone?
  5. 5.Meera can finish a job in 14 days and Kabir in 10 days. Meera works alone for 7 days and then stops. Kabir finishes the rest. How many days does Kabir take?
  6. 6.Aditya can finish a job in 9 days and Vivaan in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  7. 7.Ishaan works three times as fast as Kabir. Together they finish a job in 5 days. How many days would Kabir take alone?
  8. 8.Isha can finish a job in 6 days and Zoya in 30 days. Isha works alone for 1 day and then stops. Zoya finishes the rest. How many days does Zoya take?
  9. 9.Aarav can finish a job in 27 days and Saanvi in 9 days. Aarav works alone for 21 days and then stops. Saanvi finishes the rest. How many days does Saanvi take?
  10. 10.Nisha works twice as fast as Kabir. Together they finish a job in 9 days. How many days would Kabir take alone?
  11. 11.Tara can finish a job in 14 days and Kabir in 7 days. What fraction of the job do they finish if they work together for 2 days? =
  12. 12.Ishaan can finish a job in 2 days and Tara in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  13. 13.Zoya works three times as fast as Arjun. Together they finish a job in 7 days. How many days would Arjun take alone?
  14. 14.Meera can finish a job in 8 days and Aarav in 4 days. What fraction of the job do they finish if they work together for 2 days? =
  15. 15.Tara works twice as fast as Ananya. Together they finish a job in 3 days. How many days would Ananya take alone?
  16. 16.Vivaan and Sneha together finish a job in 8 days. Vivaan alone takes 24 days. How many days would Sneha take alone?
  17. 17.Kabir and Nisha together finish a job in 6 days. Kabir alone takes 18 days. How many days would Nisha take alone?
  18. 18.Priya works twice as fast as Aditya. Together they finish a job in 8 days. How many days would Aditya take alone?
  19. 19.Aarav and Isha together finish a job in 8 days. Aarav alone takes 12 days. How many days would Isha take alone?
  20. 20.Saanvi can finish a job in 14 days and Sneha in 28 days. Saanvi works alone for 2 days and then stops. Sneha finishes the rest. How many days does Sneha take?
  21. 21.Kabir can finish a job in 2 days and Kavya in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  22. 22.Sneha can finish a job in 11 days and Saanvi in 17 days. What fraction of the job do they finish if they work together for 1 day? =
  23. 23.Rohan works three times as fast as Rahul. Together they finish a job in 9 days. How many days would Rahul take alone?
  24. 24.Aditya and Ishaan together finish a job in 2 days. Aditya alone takes 6 days. How many days would Ishaan take alone?
  25. 25.Diya works three times as fast as Pooja. Together they finish a job in 12 days. How many days would Pooja take alone?
  26. 26.Zoya can finish a job in 8 days and Kavya in 6 days. What fraction of the job do they finish if they work together for 3 days? =
  27. 27.Vivaan can finish a job in 10 days and Kabir in 14 days. Vivaan works alone for 5 days and then stops. Kabir finishes the rest. How many days does Kabir take?
  28. 28.Zoya can finish a job in 4 days and Karan in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  29. 29.Karan can finish a job in 9 days and Aarav in 18 days. Karan works alone for 6 days and then stops. Aarav finishes the rest. How many days does Aarav take?
  30. 30.Nisha works three times as fast as Vivaan. Together they finish a job in 10 days. How many days would Vivaan take alone?
  31. 31.Rohan and Aditya together finish a job in 2 days. Rohan alone takes 3 days. How many days would Aditya take alone?
  32. 32.Manav works twice as fast as Karan. Together they finish a job in 4 days. How many days would Karan take alone?
  33. 33.Aarav can finish a job in 2 days and Diya in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  34. 34.Nisha and Ishaan together finish a job in 3 days. Nisha alone takes 4 days. How many days would Ishaan take alone?
  35. 35.Diya works twice as fast as Tara. Together they finish a job in 9 days. How many days would Tara take alone?
  36. 36.Zoya can finish a job in 8 days and Kabir in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  37. 37.Rahul works twice as fast as Isha. Together they finish a job in 6 days. How many days would Isha take alone?
  38. 38.Farhan works twice as fast as Diya. Together they finish a job in 2 days. How many days would Diya take alone?
  39. 39.Karan can finish a job in 13 days and Dev in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  40. 40.Farhan can finish a job in 10 days and Aarav in 25 days. Farhan works alone for 2 days and then stops. Aarav finishes the rest. How many days does Aarav take?

Answer key

  1. 6
  2. 4
  3. 30
  4. 6
  5. 5
  6. 9/4
  7. 20
  8. 25
  9. 2
  10. 27
  11. 3/7
  12. 16/9
  13. 28
  14. 3/4
  15. 9
  16. 12
  17. 9
  18. 24
  19. 24
  20. 24
  21. 16/9
  22. 28/187
  23. 36
  24. 3
  25. 48
  26. 7/8
  27. 7
  28. 36/13
  29. 6
  30. 40
  31. 6
  32. 12
  33. 22/13
  34. 12
  35. 27
  36. 8/5
  37. 18
  38. 6
  39. 260/33
  40. 20

Free quantitative aptitude lessons, practice and worksheets at talentjr.in/quantitative-aptitude