Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Kavya can finish a job in 10 days and Tara in 20 days. What fraction of the job do they finish if they work together for 2 days? =
- 2.Rahul can finish a job in 4 days and Rohan in 6 days. Rahul works alone for 2 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 3.Rahul can finish a job in 9 days and Vivaan in 7 days. What fraction of the job do they finish if they work together for 3 days? =
- 4.Arjun can finish a job in 10 days and Aarav in 25 days. Arjun works alone for 2 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 5.Sneha can finish a job in 19 days and Aditya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Farhan can finish a job in 20 days and Kabir in 8 days. What fraction of the job do they finish if they work together for 3 days? =
- 7.Ishaan can finish a job in 24 days and Arjun in 6 days. Ishaan works alone for 8 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 8.Saanvi and Zoya together finish a job in 2 days. Saanvi alone takes 6 days. How many days would Zoya take alone?
- 9.Ananya can finish a job in 18 days and Manav in 10 days. What fraction of the job do they finish if they work together for 2 days? =
- 10.Kavya can finish a job in 15 days and Aarav in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 11.Ananya can finish a job in 3 days and Dev in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Arjun can finish a job in 4 days and Karan in 24 days. Arjun works alone for 1 day and then stops. Karan finishes the rest. How many days does Karan take?
- 13.Aarav can finish a job in 8 days and Kabir in 18 days. Aarav works alone for 4 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 14.Nisha and Rahul together finish a job in 2 days. Nisha alone takes 3 days. How many days would Rahul take alone?
- 15.Manav can finish a job in 9 days and Isha in 18 days. Manav works alone for 2 days and then stops. Isha finishes the rest. How many days does Isha take?
- 16.Priya can finish a job in 8 days and Ishaan in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Aarav and Tara together finish a job in 8 days. Aarav alone takes 9 days. How many days would Tara take alone?
- 18.Saanvi can finish a job in 11 days and Aditya in 13 days. What fraction of the job do they finish if they work together for 1 day? =
- 19.Diya and Meera together finish a job in 12 days. Diya alone takes 16 days. How many days would Meera take alone?
- 20.Nisha can finish a job in 12 days and Kabir in 8 days. Nisha works alone for 9 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 21.Kabir and Saanvi together finish a job in 3 days. Kabir alone takes 4 days. How many days would Saanvi take alone?
- 22.Aarav and Kabir together finish a job in 2 days. Aarav alone takes 3 days. How many days would Kabir take alone?
- 23.Vivaan and Manav together finish a job in 3 days. Vivaan alone takes 6 days. How many days would Manav take alone?
- 24.Rohan and Meera together finish a job in 2 days. Rohan alone takes 3 days. How many days would Meera take alone?
- 25.Sneha can finish a job in 2 days and Priya in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 26.Arjun can finish a job in 30 days and Aditya in 18 days. Arjun works alone for 5 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 27.Karan can finish a job in 5 days and Farhan in 16 days. What fraction of the job do they finish if they work together for 1 day? =
- 28.Kavya works three times as fast as Pooja. Together they finish a job in 3 days. How many days would Pooja take alone?
- 29.Meera can finish a job in 8 days and Farhan in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 30.Zoya can finish a job in 10 days and Dev in 28 days. Zoya works alone for 5 days and then stops. Dev finishes the rest. How many days does Dev take?
- 31.Meera and Isha together finish a job in 4 days. Meera alone takes 5 days. How many days would Isha take alone?
- 32.Farhan can finish a job in 6 days and Pooja in 21 days. Farhan works alone for 4 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 33.Kabir can finish a job in 5 days and Sneha in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Aarav can finish a job in 4 days and Pooja in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Vivaan can finish a job in 18 days and Nisha in 12 days. What fraction of the job do they finish if they work together for 1 day? =
- 36.Pooja can finish a job in 3 days and Diya in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 37.Kabir can finish a job in 4 days and Dev in 16 days. Kabir works alone for 3 days and then stops. Dev finishes the rest. How many days does Dev take?
- 38.Vivaan works twice as fast as Manav. Together they finish a job in 7 days. How many days would Manav take alone?
- 39.Tara works twice as fast as Ananya. Together they finish a job in 9 days. How many days would Ananya take alone?
- 40.Farhan can finish a job in 6 days and Aditya in 11 days. What fraction of the job do they finish if they work together for 1 day? =
Answer key
- 3/10
- 3
- 16/21
- 20
- 342/37
- 21/40
- 4
- 3
- 14/45
- 31/120
- 12/7
- 18
- 9
- 6
- 14
- 24/11
- 72
- 24/143
- 48
- 2
- 12
- 6
- 6
- 6
- 12/7
- 15
- 21/80
- 12
- 152/27
- 14
- 20
- 7
- 80/21
- 10/3
- 5/36
- 57/22
- 4
- 21
- 27
- 17/66