Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Kabir and Zoya together finish a job in 3 days. Kabir alone takes 4 days. How many days would Zoya take alone?
- 2.Vivaan and Priya together finish a job in 3 days. Vivaan alone takes 6 days. How many days would Priya take alone?
- 3.Rahul can finish a job in 7 days and Isha in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Aarav can finish a job in 20 days and Diya in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Isha works twice as fast as Ananya. Together they finish a job in 12 days. How many days would Ananya take alone?
- 6.Manav can finish a job in 6 days and Isha in 21 days. Manav works alone for 2 days and then stops. Isha finishes the rest. How many days does Isha take?
- 7.Sneha can finish a job in 8 days and Rahul in 14 days. What fraction of the job do they finish if they work together for 1 day? =
- 8.Isha can finish a job in 8 days and Arjun in 4 days. Isha works alone for 4 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 9.Vivaan works three times as fast as Isha. Together they finish a job in 3 days. How many days would Isha take alone?
- 10.Aarav can finish a job in 7 days and Manav in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 11.Dev can finish a job in 12 days and Rohan in 10 days. Dev works alone for 6 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 12.Pooja and Karan together finish a job in 12 days. Pooja alone takes 20 days. How many days would Karan take alone?
- 13.Rahul can finish a job in 19 days and Tara in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 14.Aditya can finish a job in 15 days and Aarav in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 15.Rahul and Zoya together finish a job in 5 days. Rahul alone takes 10 days. How many days would Zoya take alone?
- 16.Meera works twice as fast as Vivaan. Together they finish a job in 4 days. How many days would Vivaan take alone?
- 17.Rahul works twice as fast as Karan. Together they finish a job in 10 days. How many days would Karan take alone?
- 18.Meera works three times as fast as Ananya. Together they finish a job in 9 days. How many days would Ananya take alone?
- 19.Arjun can finish a job in 24 days and Priya in 20 days. Arjun works alone for 18 days and then stops. Priya finishes the rest. How many days does Priya take?
- 20.Ananya and Zoya together finish a job in 3 days. Ananya alone takes 4 days. How many days would Zoya take alone?
- 21.Kabir and Manav together finish a job in 2 days. Kabir alone takes 3 days. How many days would Manav take alone?
- 22.Pooja can finish a job in 9 days and Nisha in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Rohan can finish a job in 18 days and Tara in 19 days. What fraction of the job do they finish if they work together for 1 day? =
- 24.Arjun can finish a job in 16 days and Zoya in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 25.Isha can finish a job in 4 days and Diya in 28 days. Isha works alone for 3 days and then stops. Diya finishes the rest. How many days does Diya take?
- 26.Zoya can finish a job in 8 days and Tara in 4 days. Zoya works alone for 6 days and then stops. Tara finishes the rest. How many days does Tara take?
- 27.Farhan can finish a job in 7 days and Vivaan in 14 days. What fraction of the job do they finish if they work together for 3 days? =
- 28.Diya can finish a job in 13 days and Karan in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Saanvi and Kavya together finish a job in 7 days. Saanvi alone takes 8 days. How many days would Kavya take alone?
- 30.Rahul can finish a job in 11 days and Saanvi in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Aarav and Kavya together finish a job in 2 days. Aarav alone takes 3 days. How many days would Kavya take alone?
- 32.Ananya can finish a job in 8 days and Saanvi in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 33.Diya works three times as fast as Karan. Together they finish a job in 9 days. How many days would Karan take alone?
- 34.Dev works twice as fast as Aarav. Together they finish a job in 5 days. How many days would Aarav take alone?
- 35.Ishaan can finish a job in 5 days and Ananya in 15 days. Ishaan works alone for 3 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 36.Ishaan can finish a job in 6 days and Aditya in 30 days. Ishaan works alone for 2 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 37.Diya can finish a job in 8 days and Kabir in 4 days. Diya works alone for 2 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 38.Saanvi and Farhan together finish a job in 15 days. Saanvi alone takes 30 days. How many days would Farhan take alone?
- 39.Dev and Karan together finish a job in 5 days. Dev alone takes 10 days. How many days would Karan take alone?
- 40.Sneha can finish a job in 5 days and Priya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
Answer key
- 12
- 6
- 56/15
- 20/3
- 36
- 14
- 11/56
- 2
- 12
- 13/14
- 5
- 30
- 25/57
- 1/6
- 10
- 12
- 30
- 36
- 5
- 12
- 6
- 153/26
- 37/342
- 17/72
- 7
- 1
- 9/14
- 39/16
- 56
- 187/28
- 6
- 13/36
- 36
- 15
- 6
- 20
- 3
- 30
- 10
- 15/8