Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Vivaan can finish a job in 5 days and Farhan in 15 days. Vivaan works alone for 4 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 2.Karan can finish a job in 25 days and Nisha in 5 days. Karan works alone for 5 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 3.Kabir can finish a job in 16 days and Isha in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Arjun can finish a job in 8 days and Meera in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Aditya can finish a job in 14 days and Priya in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Pooja can finish a job in 18 days and Meera in 7 days. What fraction of the job do they finish if they work together for 3 days? =
- 7.Karan can finish a job in 24 days and Manav in 15 days. Karan works alone for 8 days and then stops. Manav finishes the rest. How many days does Manav take?
- 8.Pooja can finish a job in 5 days and Rahul in 18 days. What fraction of the job do they finish if they work together for 1 day? =
- 9.Aarav can finish a job in 5 days and Kavya in 12 days. What fraction of the job do they finish if they work together for 3 days? =
- 10.Kabir can finish a job in 6 days and Sneha in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 11.Aditya can finish a job in 18 days and Priya in 9 days. Aditya works alone for 4 days and then stops. Priya finishes the rest. How many days does Priya take?
- 12.Zoya can finish a job in 20 days and Karan in 12 days. Zoya works alone for 5 days and then stops. Karan finishes the rest. How many days does Karan take?
- 13.Ishaan and Nisha together finish a job in 6 days. Ishaan alone takes 8 days. How many days would Nisha take alone?
- 14.Nisha can finish a job in 26 days and Sneha in 20 days. Nisha works alone for 13 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 15.Meera works twice as fast as Nisha. Together they finish a job in 7 days. How many days would Nisha take alone?
- 16.Isha can finish a job in 28 days and Karan in 4 days. Isha works alone for 21 days and then stops. Karan finishes the rest. How many days does Karan take?
- 17.Karan and Pooja together finish a job in 8 days. Karan alone takes 10 days. How many days would Pooja take alone?
- 18.Karan works twice as fast as Pooja. Together they finish a job in 3 days. How many days would Pooja take alone?
- 19.Tara and Dev together finish a job in 2 days. Tara alone takes 3 days. How many days would Dev take alone?
- 20.Rohan can finish a job in 9 days and Nisha in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Diya can finish a job in 13 days and Farhan in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Kavya can finish a job in 8 days and Zoya in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Saanvi and Diya together finish a job in 2 days. Saanvi alone takes 3 days. How many days would Diya take alone?
- 24.Nisha and Ananya together finish a job in 4 days. Nisha alone takes 8 days. How many days would Ananya take alone?
- 25.Meera can finish a job in 10 days and Manav in 8 days. Meera works alone for 5 days and then stops. Manav finishes the rest. How many days does Manav take?
- 26.Isha can finish a job in 19 days and Diya in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Rohan can finish a job in 6 days and Ananya in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Rahul and Nisha together finish a job in 18 days. Rahul alone takes 24 days. How many days would Nisha take alone?
- 29.Pooja can finish a job in 17 days and Vivaan in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 30.Karan can finish a job in 14 days and Rohan in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 31.Rahul can finish a job in 7 days and Kavya in 28 days. Rahul works alone for 1 day and then stops. Kavya finishes the rest. How many days does Kavya take?
- 32.Saanvi works twice as fast as Vivaan. Together they finish a job in 3 days. How many days would Vivaan take alone?
- 33.Dev and Sneha together finish a job in 2 days. Dev alone takes 3 days. How many days would Sneha take alone?
- 34.Nisha can finish a job in 9 days and Manav in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Vivaan can finish a job in 30 days and Kavya in 25 days. Vivaan works alone for 24 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 36.Nisha works twice as fast as Pooja. Together they finish a job in 12 days. How many days would Pooja take alone?
- 37.Farhan can finish a job in 19 days and Aarav in 11 days. What fraction of the job do they finish if they work together for 1 day? =
- 38.Ananya and Rahul together finish a job in 2 days. Ananya alone takes 3 days. How many days would Rahul take alone?
- 39.Farhan can finish a job in 12 days and Saanvi in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Sneha can finish a job in 4 days and Manav in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
Answer key
- 3
- 4
- 48/11
- 24/5
- 140/17
- 25/42
- 10
- 23/90
- 17/20
- 19/26
- 7
- 9
- 24
- 10
- 21
- 1
- 40
- 9
- 6
- 63/16
- 221/30
- 16/3
- 6
- 8
- 4
- 285/34
- 15/4
- 72
- 187/28
- 19/70
- 24
- 9
- 6
- 90/19
- 5
- 36
- 30/209
- 6
- 60/11
- 20/9
Free quantitative aptitude lessons, practice and worksheets at talentjr.in/quantitative-aptitude