Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Priya and Kabir together finish a job in 2 days. Priya alone takes 3 days. How many days would Kabir take alone?
- 2.Kavya can finish a job in 3 days and Nisha in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 3.Vivaan works twice as fast as Kabir. Together they finish a job in 11 days. How many days would Kabir take alone?
- 4.Pooja can finish a job in 17 days and Sneha in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Ananya can finish a job in 6 days and Meera in 19 days. What fraction of the job do they finish if they work together for 2 days? =
- 6.Rohan and Saanvi together finish a job in 2 days. Rohan alone takes 3 days. How many days would Saanvi take alone?
- 7.Meera and Nisha together finish a job in 8 days. Meera alone takes 12 days. How many days would Nisha take alone?
- 8.Rahul and Kavya together finish a job in 4 days. Rahul alone takes 6 days. How many days would Kavya take alone?
- 9.Saanvi can finish a job in 10 days and Kabir in 30 days. Saanvi works alone for 5 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 10.Farhan and Manav together finish a job in 2 days. Farhan alone takes 3 days. How many days would Manav take alone?
- 11.Kavya can finish a job in 6 days and Diya in 17 days. What fraction of the job do they finish if they work together for 2 days? =
- 12.Diya can finish a job in 19 days and Priya in 15 days. What fraction of the job do they finish if they work together for 1 day? =
- 13.Zoya works twice as fast as Arjun. Together they finish a job in 9 days. How many days would Arjun take alone?
- 14.Vivaan and Nisha together finish a job in 2 days. Vivaan alone takes 3 days. How many days would Nisha take alone?
- 15.Arjun works twice as fast as Pooja. Together they finish a job in 9 days. How many days would Pooja take alone?
- 16.Vivaan and Priya together finish a job in 6 days. Vivaan alone takes 9 days. How many days would Priya take alone?
- 17.Farhan can finish a job in 14 days and Rahul in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Priya can finish a job in 5 days and Pooja in 30 days. Priya works alone for 4 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 19.Rahul can finish a job in 5 days and Meera in 30 days. Rahul works alone for 3 days and then stops. Meera finishes the rest. How many days does Meera take?
- 20.Rahul can finish a job in 7 days and Manav in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Diya can finish a job in 8 days and Nisha in 4 days. Diya works alone for 2 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 22.Meera and Zoya together finish a job in 8 days. Meera alone takes 12 days. How many days would Zoya take alone?
- 23.Sneha can finish a job in 13 days and Meera in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 24.Isha can finish a job in 28 days and Karan in 21 days. Isha works alone for 16 days and then stops. Karan finishes the rest. How many days does Karan take?
- 25.Nisha and Sneha together finish a job in 2 days. Nisha alone takes 4 days. How many days would Sneha take alone?
- 26.Sneha can finish a job in 10 days and Ishaan in 18 days. What fraction of the job do they finish if they work together for 1 day? =
- 27.Arjun and Farhan together finish a job in 4 days. Arjun alone takes 6 days. How many days would Farhan take alone?
- 28.Manav can finish a job in 15 days and Sneha in 5 days. Manav works alone for 9 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 29.Isha can finish a job in 4 days and Farhan in 12 days. Isha works alone for 1 day and then stops. Farhan finishes the rest. How many days does Farhan take?
- 30.Dev can finish a job in 30 days and Sneha in 5 days. Dev works alone for 12 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 31.Nisha can finish a job in 8 days and Isha in 16 days. Nisha works alone for 7 days and then stops. Isha finishes the rest. How many days does Isha take?
- 32.Karan can finish a job in 8 days and Dev in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Ananya can finish a job in 5 days and Farhan in 10 days. Ananya works alone for 3 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 34.Nisha can finish a job in 18 days and Karan in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Manav can finish a job in 5 days and Karan in 30 days. Manav works alone for 2 days and then stops. Karan finishes the rest. How many days does Karan take?
- 36.Ananya can finish a job in 17 days and Farhan in 14 days. What fraction of the job do they finish if they work together for 1 day? =
- 37.Nisha works twice as fast as Pooja. Together they finish a job in 2 days. How many days would Pooja take alone?
- 38.Aarav can finish a job in 18 days and Arjun in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 39.Dev can finish a job in 10 days and Rohan in 30 days. Dev works alone for 1 day and then stops. Rohan finishes the rest. How many days does Rohan take?
- 40.Karan and Diya together finish a job in 3 days. Karan alone takes 4 days. How many days would Diya take alone?
Answer key
- 6
- 6/5
- 33
- 340/37
- 25/57
- 6
- 24
- 12
- 15
- 6
- 23/51
- 34/285
- 27
- 6
- 27
- 18
- 28/9
- 6
- 12
- 56/15
- 3
- 24
- 39/16
- 9
- 4
- 7/45
- 12
- 2
- 9
- 3
- 2
- 40/7
- 4
- 90/11
- 18
- 31/238
- 6
- 7/45
- 27
- 12