Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Rohan can finish a job in 4 days and Priya in 8 days. Rohan works alone for 3 days and then stops. Priya finishes the rest. How many days does Priya take?
- 2.Priya and Karan together finish a job in 12 days. Priya alone takes 15 days. How many days would Karan take alone?
- 3.Aditya can finish a job in 18 days and Saanvi in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Kabir can finish a job in 6 days and Manav in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Karan can finish a job in 8 days and Dev in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Aditya can finish a job in 12 days and Tara in 30 days. Aditya works alone for 6 days and then stops. Tara finishes the rest. How many days does Tara take?
- 7.Saanvi can finish a job in 12 days and Manav in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Manav can finish a job in 13 days and Ananya in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 9.Priya can finish a job in 14 days and Diya in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Saanvi can finish a job in 5 days and Diya in 9 days. What fraction of the job do they finish if they work together for 3 days? =
- 11.Diya works twice as fast as Zoya. Together they finish a job in 9 days. How many days would Zoya take alone?
- 12.Zoya and Arjun together finish a job in 2 days. Zoya alone takes 4 days. How many days would Arjun take alone?
- 13.Aarav works three times as fast as Arjun. Together they finish a job in 5 days. How many days would Arjun take alone?
- 14.Isha works twice as fast as Arjun. Together they finish a job in 2 days. How many days would Arjun take alone?
- 15.Vivaan can finish a job in 6 days and Aditya in 24 days. Vivaan works alone for 5 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 16.Kabir can finish a job in 4 days and Karan in 24 days. Kabir works alone for 1 day and then stops. Karan finishes the rest. How many days does Karan take?
- 17.Ananya and Meera together finish a job in 6 days. Ananya alone takes 15 days. How many days would Meera take alone?
- 18.Aarav and Rohan together finish a job in 6 days. Aarav alone takes 7 days. How many days would Rohan take alone?
- 19.Aarav and Manav together finish a job in 2 days. Aarav alone takes 4 days. How many days would Manav take alone?
- 20.Rahul and Rohan together finish a job in 2 days. Rahul alone takes 6 days. How many days would Rohan take alone?
- 21.Rahul works three times as fast as Manav. Together they finish a job in 5 days. How many days would Manav take alone?
- 22.Priya works twice as fast as Nisha. Together they finish a job in 5 days. How many days would Nisha take alone?
- 23.Zoya and Nisha together finish a job in 2 days. Zoya alone takes 6 days. How many days would Nisha take alone?
- 24.Aditya works three times as fast as Meera. Together they finish a job in 12 days. How many days would Meera take alone?
- 25.Sneha can finish a job in 8 days and Kabir in 16 days. Sneha works alone for 6 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 26.Vivaan and Tara together finish a job in 2 days. Vivaan alone takes 3 days. How many days would Tara take alone?
- 27.Diya can finish a job in 14 days and Manav in 8 days. What fraction of the job do they finish if they work together for 3 days? =
- 28.Sneha works three times as fast as Isha. Together they finish a job in 9 days. How many days would Isha take alone?
- 29.Vivaan and Tara together finish a job in 15 days. Vivaan alone takes 18 days. How many days would Tara take alone?
- 30.Sneha can finish a job in 7 days and Saanvi in 21 days. Sneha works alone for 6 days and then stops. Saanvi finishes the rest. How many days does Saanvi take?
- 31.Pooja and Tara together finish a job in 3 days. Pooja alone takes 4 days. How many days would Tara take alone?
- 32.Aarav can finish a job in 24 days and Vivaan in 6 days. Aarav works alone for 8 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 33.Aditya and Ananya together finish a job in 3 days. Aditya alone takes 4 days. How many days would Ananya take alone?
- 34.Karan can finish a job in 13 days and Rohan in 26 days. Karan works alone for 7 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 35.Karan and Nisha together finish a job in 6 days. Karan alone takes 8 days. How many days would Nisha take alone?
- 36.Priya can finish a job in 13 days and Kabir in 19 days. What fraction of the job do they finish if they work together for 1 day? =
- 37.Meera works twice as fast as Tara. Together they finish a job in 12 days. How many days would Tara take alone?
- 38.Kabir and Arjun together finish a job in 4 days. Kabir alone takes 5 days. How many days would Arjun take alone?
- 39.Meera can finish a job in 5 days and Arjun in 17 days. What fraction of the job do they finish if they work together for 2 days? =
- 40.Manav and Ishaan together finish a job in 10 days. Manav alone takes 12 days. How many days would Ishaan take alone?
Answer key
- 2
- 60
- 90/11
- 12/5
- 136/25
- 15
- 24/5
- 31/117
- 238/31
- 14/15
- 27
- 4
- 20
- 6
- 4
- 18
- 10
- 42
- 4
- 3
- 20
- 15
- 3
- 48
- 4
- 6
- 33/56
- 36
- 90
- 3
- 12
- 4
- 12
- 12
- 24
- 32/247
- 36
- 20
- 44/85
- 60