Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Aarav and Ishaan together finish a job in 6 days. Aarav alone takes 7 days. How many days would Ishaan take alone?
- 2.Rohan can finish a job in 4 days and Priya in 28 days. Rohan works alone for 3 days and then stops. Priya finishes the rest. How many days does Priya take?
- 3.Pooja works twice as fast as Priya. Together they finish a job in 5 days. How many days would Priya take alone?
- 4.Sneha can finish a job in 10 days and Tara in 15 days. Sneha works alone for 4 days and then stops. Tara finishes the rest. How many days does Tara take?
- 5.Sneha can finish a job in 21 days and Farhan in 14 days. Sneha works alone for 18 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 6.Zoya can finish a job in 7 days and Rohan in 14 days. Zoya works alone for 5 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 7.Aditya and Zoya together finish a job in 7 days. Aditya alone takes 14 days. How many days would Zoya take alone?
- 8.Arjun can finish a job in 7 days and Tara in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 9.Zoya can finish a job in 30 days and Kabir in 12 days. Zoya works alone for 25 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 10.Kavya can finish a job in 11 days and Ishaan in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 11.Manav works three times as fast as Dev. Together they finish a job in 12 days. How many days would Dev take alone?
- 12.Dev and Arjun together finish a job in 6 days. Dev alone takes 12 days. How many days would Arjun take alone?
- 13.Aarav and Isha together finish a job in 2 days. Aarav alone takes 3 days. How many days would Isha take alone?
- 14.Rohan and Ananya together finish a job in 11 days. Rohan alone takes 22 days. How many days would Ananya take alone?
- 15.Tara works twice as fast as Priya. Together they finish a job in 2 days. How many days would Priya take alone?
- 16.Karan can finish a job in 13 days and Kavya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Ishaan and Zoya together finish a job in 4 days. Ishaan alone takes 5 days. How many days would Zoya take alone?
- 18.Meera works twice as fast as Kavya. Together they finish a job in 10 days. How many days would Kavya take alone?
- 19.Ananya can finish a job in 9 days and Rahul in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 20.Meera works three times as fast as Diya. Together they finish a job in 12 days. How many days would Diya take alone?
- 21.Farhan and Vivaan together finish a job in 12 days. Farhan alone takes 18 days. How many days would Vivaan take alone?
- 22.Dev and Rohan together finish a job in 2 days. Dev alone takes 4 days. How many days would Rohan take alone?
- 23.Manav works twice as fast as Meera. Together they finish a job in 6 days. How many days would Meera take alone?
- 24.Zoya and Diya together finish a job in 10 days. Zoya alone takes 12 days. How many days would Diya take alone?
- 25.Kabir works twice as fast as Arjun. Together they finish a job in 10 days. How many days would Arjun take alone?
- 26.Zoya works twice as fast as Sneha. Together they finish a job in 3 days. How many days would Sneha take alone?
- 27.Manav can finish a job in 24 days and Vivaan in 12 days. Manav works alone for 20 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 28.Sneha can finish a job in 6 days and Ananya in 16 days. What fraction of the job do they finish if they work together for 1 day? =
- 29.Pooja and Rohan together finish a job in 8 days. Pooja alone takes 10 days. How many days would Rohan take alone?
- 30.Dev can finish a job in 6 days and Ananya in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Ishaan can finish a job in 17 days and Isha in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Rohan can finish a job in 13 days and Ananya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Rohan can finish a job in 2 days and Meera in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Tara works twice as fast as Ananya. Together they finish a job in 3 days. How many days would Ananya take alone?
- 35.Tara can finish a job in 5 days and Ananya in 10 days. Tara works alone for 4 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 36.Nisha and Ananya together finish a job in 2 days. Nisha alone takes 6 days. How many days would Ananya take alone?
- 37.Saanvi and Tara together finish a job in 9 days. Saanvi alone takes 10 days. How many days would Tara take alone?
- 38.Priya can finish a job in 5 days and Zoya in 30 days. Priya works alone for 4 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 39.Aarav works twice as fast as Manav. Together they finish a job in 4 days. How many days would Manav take alone?
- 40.Ananya can finish a job in 4 days and Manav in 30 days. Ananya works alone for 2 days and then stops. Manav finishes the rest. How many days does Manav take?
Answer key
- 42
- 7
- 15
- 9
- 2
- 4
- 14
- 84/19
- 2
- 72/143
- 48
- 12
- 6
- 22
- 6
- 39/16
- 20
- 30
- 14/45
- 48
- 36
- 4
- 18
- 60
- 30
- 9
- 2
- 11/48
- 40
- 15/4
- 272/33
- 234/31
- 3/2
- 9
- 2
- 3
- 90
- 6
- 12
- 15
Free quantitative aptitude lessons, practice and worksheets at talentjr.in/quantitative-aptitude