Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Meera can finish a job in 2 days and Farhan in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Tara and Aarav together finish a job in 3 days. Tara alone takes 4 days. How many days would Aarav take alone?
- 3.Priya can finish a job in 20 days and Diya in 30 days. Priya works alone for 6 days and then stops. Diya finishes the rest. How many days does Diya take?
- 4.Vivaan works twice as fast as Diya. Together they finish a job in 10 days. How many days would Diya take alone?
- 5.Dev can finish a job in 6 days and Karan in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Priya can finish a job in 16 days and Saanvi in 6 days. What fraction of the job do they finish if they work together for 1 day? =
- 7.Rohan works three times as fast as Isha. Together they finish a job in 5 days. How many days would Isha take alone?
- 8.Meera can finish a job in 12 days and Diya in 7 days. What fraction of the job do they finish if they work together for 1 day? =
- 9.Farhan can finish a job in 12 days and Ananya in 9 days. Farhan works alone for 8 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 10.Vivaan works three times as fast as Karan. Together they finish a job in 3 days. How many days would Karan take alone?
- 11.Tara can finish a job in 17 days and Kabir in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Ananya and Nisha together finish a job in 15 days. Ananya alone takes 18 days. How many days would Nisha take alone?
- 13.Karan can finish a job in 8 days and Zoya in 16 days. What fraction of the job do they finish if they work together for 3 days? =
- 14.Arjun can finish a job in 3 days and Isha in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Nisha and Rahul together finish a job in 2 days. Nisha alone takes 3 days. How many days would Rahul take alone?
- 16.Sneha can finish a job in 16 days and Manav in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Nisha can finish a job in 12 days and Farhan in 27 days. Nisha works alone for 4 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 18.Ishaan and Meera together finish a job in 3 days. Ishaan alone takes 4 days. How many days would Meera take alone?
- 19.Sneha can finish a job in 16 days and Ananya in 24 days. Sneha works alone for 8 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 20.Nisha can finish a job in 7 days and Farhan in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Karan can finish a job in 9 days and Isha in 11 days. What fraction of the job do they finish if they work together for 2 days? =
- 22.Arjun can finish a job in 4 days and Ishaan in 8 days. Arjun works alone for 1 day and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 23.Kabir can finish a job in 16 days and Priya in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 24.Saanvi can finish a job in 11 days and Aarav in 4 days. What fraction of the job do they finish if they work together for 1 day? =
- 25.Karan and Diya together finish a job in 2 days. Karan alone takes 3 days. How many days would Diya take alone?
- 26.Diya can finish a job in 9 days and Kabir in 13 days. What fraction of the job do they finish if they work together for 2 days? =
- 27.Aarav can finish a job in 20 days and Kavya in 15 days. Aarav works alone for 4 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 28.Kabir can finish a job in 10 days and Rohan in 17 days. What fraction of the job do they finish if they work together for 3 days? =
- 29.Priya and Arjun together finish a job in 6 days. Priya alone takes 7 days. How many days would Arjun take alone?
- 30.Rohan and Kabir together finish a job in 7 days. Rohan alone takes 8 days. How many days would Kabir take alone?
- 31.Tara works three times as fast as Manav. Together they finish a job in 2 days. How many days would Manav take alone?
- 32.Tara can finish a job in 15 days and Dev in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Nisha can finish a job in 14 days and Pooja in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Rahul can finish a job in 11 days and Priya in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Dev and Nisha together finish a job in 8 days. Dev alone takes 10 days. How many days would Nisha take alone?
- 36.Ananya can finish a job in 30 days and Arjun in 18 days. Ananya works alone for 15 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 37.Vivaan can finish a job in 5 days and Rohan in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Diya works twice as fast as Farhan. Together they finish a job in 9 days. How many days would Farhan take alone?
- 39.Diya can finish a job in 20 days and Dev in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 40.Diya works three times as fast as Farhan. Together they finish a job in 11 days. How many days would Farhan take alone?
Answer key
- 30/17
- 12
- 21
- 30
- 24/7
- 11/48
- 20
- 19/84
- 3
- 12
- 119/24
- 90
- 9/16
- 30/13
- 6
- 80/21
- 18
- 12
- 12
- 91/20
- 40/99
- 6
- 16/5
- 15/44
- 6
- 44/117
- 12
- 81/170
- 42
- 56
- 8
- 30/17
- 182/27
- 44/15
- 40
- 9
- 95/24
- 27
- 13/30
- 44