Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Aditya works three times as fast as Isha. Together they finish a job in 2 days. How many days would Isha take alone?
- 2.Arjun can finish a job in 6 days and Ananya in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 3.Kabir can finish a job in 8 days and Nisha in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Rohan can finish a job in 16 days and Nisha in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 5.Manav works twice as fast as Zoya. Together they finish a job in 8 days. How many days would Zoya take alone?
- 6.Arjun can finish a job in 8 days and Tara in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Ananya works twice as fast as Aditya. Together they finish a job in 11 days. How many days would Aditya take alone?
- 8.Farhan can finish a job in 11 days and Rahul in 19 days. What fraction of the job do they finish if they work together for 2 days? =
- 9.Nisha can finish a job in 10 days and Dev in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Kabir works three times as fast as Saanvi. Together they finish a job in 7 days. How many days would Saanvi take alone?
- 11.Dev can finish a job in 6 days and Rohan in 30 days. Dev works alone for 5 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 12.Rahul and Ananya together finish a job in 14 days. Rahul alone takes 18 days. How many days would Ananya take alone?
- 13.Pooja can finish a job in 17 days and Manav in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Arjun and Ananya together finish a job in 15 days. Arjun alone takes 24 days. How many days would Ananya take alone?
- 15.Vivaan can finish a job in 12 days and Diya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Karan can finish a job in 4 days and Priya in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 17.Nisha can finish a job in 13 days and Ananya in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 18.Rahul and Zoya together finish a job in 6 days. Rahul alone takes 7 days. How many days would Zoya take alone?
- 19.Ananya and Vivaan together finish a job in 8 days. Ananya alone takes 9 days. How many days would Vivaan take alone?
- 20.Vivaan can finish a job in 4 days and Rahul in 16 days. Vivaan works alone for 1 day and then stops. Rahul finishes the rest. How many days does Rahul take?
- 21.Sneha can finish a job in 9 days and Farhan in 24 days. Sneha works alone for 3 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 22.Kabir can finish a job in 14 days and Sneha in 11 days. What fraction of the job do they finish if they work together for 2 days? =
- 23.Rohan works twice as fast as Kabir. Together they finish a job in 12 days. How many days would Kabir take alone?
- 24.Aarav can finish a job in 14 days and Tara in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Rohan works twice as fast as Rahul. Together they finish a job in 3 days. How many days would Rahul take alone?
- 26.Sneha can finish a job in 10 days and Saanvi in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Priya can finish a job in 14 days and Rohan in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Ishaan can finish a job in 6 days and Rahul in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Aarav and Dev together finish a job in 2 days. Aarav alone takes 3 days. How many days would Dev take alone?
- 30.Karan can finish a job in 15 days and Dev in 10 days. Karan works alone for 3 days and then stops. Dev finishes the rest. How many days does Dev take?
- 31.Zoya can finish a job in 6 days and Sneha in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Tara can finish a job in 19 days and Isha in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Rahul works twice as fast as Karan. Together they finish a job in 10 days. How many days would Karan take alone?
- 34.Karan and Manav together finish a job in 10 days. Karan alone takes 20 days. How many days would Manav take alone?
- 35.Meera can finish a job in 4 days and Tara in 9 days. What fraction of the job do they finish if they work together for 1 day? =
- 36.Pooja and Rohan together finish a job in 5 days. Pooja alone takes 6 days. How many days would Rohan take alone?
- 37.Saanvi can finish a job in 16 days and Diya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Rahul can finish a job in 7 days and Aarav in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Kabir can finish a job in 22 days and Pooja in 28 days. Kabir works alone for 11 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 40.Ananya and Priya together finish a job in 2 days. Ananya alone takes 3 days. How many days would Priya take alone?
Answer key
- 8
- 102/23
- 40/13
- 21/80
- 24
- 136/25
- 33
- 60/209
- 6
- 28
- 5
- 63
- 272/33
- 40
- 36/5
- 5/6
- 18/65
- 42
- 72
- 12
- 16
- 25/77
- 36
- 7/4
- 9
- 6
- 7/4
- 18/5
- 6
- 8
- 12/5
- 190/29
- 30
- 20
- 13/36
- 30
- 144/17
- 126/25
- 14
- 6
Free quantitative aptitude lessons, practice and worksheets at talentjr.in/quantitative-aptitude