Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Priya can finish a job in 5 days and Tara in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Pooja can finish a job in 27 days and Dev in 18 days. Pooja works alone for 9 days and then stops. Dev finishes the rest. How many days does Dev take?
- 3.Ananya can finish a job in 13 days and Aarav in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Ishaan can finish a job in 8 days and Meera in 24 days. Ishaan works alone for 1 day and then stops. Meera finishes the rest. How many days does Meera take?
- 5.Aditya works three times as fast as Vivaan. Together they finish a job in 8 days. How many days would Vivaan take alone?
- 6.Kabir works twice as fast as Tara. Together they finish a job in 11 days. How many days would Tara take alone?
- 7.Sneha can finish a job in 13 days and Nisha in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Diya can finish a job in 13 days and Tara in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 9.Ishaan works three times as fast as Rahul. Together they finish a job in 7 days. How many days would Rahul take alone?
- 10.Tara can finish a job in 3 days and Sneha in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Meera can finish a job in 6 days and Isha in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Meera can finish a job in 18 days and Tara in 19 days. What fraction of the job do they finish if they work together for 2 days? =
- 13.Arjun can finish a job in 7 days and Rahul in 14 days. Arjun works alone for 3 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 14.Arjun can finish a job in 9 days and Pooja in 6 days. Arjun works alone for 3 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 15.Arjun and Rahul together finish a job in 8 days. Arjun alone takes 12 days. How many days would Rahul take alone?
- 16.Isha can finish a job in 5 days and Arjun in 10 days. Isha works alone for 3 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 17.Pooja can finish a job in 9 days and Sneha in 19 days. What fraction of the job do they finish if they work together for 2 days? =
- 18.Vivaan can finish a job in 13 days and Zoya in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Ishaan can finish a job in 14 days and Rohan in 15 days. What fraction of the job do they finish if they work together for 3 days? =
- 20.Farhan can finish a job in 15 days and Nisha in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Priya can finish a job in 14 days and Kabir in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Meera can finish a job in 8 days and Isha in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Zoya can finish a job in 4 days and Aditya in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 24.Dev can finish a job in 17 days and Arjun in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Ananya and Diya together finish a job in 5 days. Ananya alone takes 6 days. How many days would Diya take alone?
- 26.Nisha can finish a job in 6 days and Kabir in 12 days. Nisha works alone for 2 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 27.Farhan works three times as fast as Saanvi. Together they finish a job in 7 days. How many days would Saanvi take alone?
- 28.Karan can finish a job in 7 days and Aarav in 28 days. Karan works alone for 2 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 29.Priya can finish a job in 6 days and Isha in 9 days. Priya works alone for 4 days and then stops. Isha finishes the rest. How many days does Isha take?
- 30.Aarav can finish a job in 14 days and Isha in 7 days. Aarav works alone for 12 days and then stops. Isha finishes the rest. How many days does Isha take?
- 31.Sneha and Diya together finish a job in 2 days. Sneha alone takes 6 days. How many days would Diya take alone?
- 32.Diya can finish a job in 5 days and Kabir in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Diya can finish a job in 11 days and Aarav in 15 days. What fraction of the job do they finish if they work together for 3 days? =
- 34.Kabir can finish a job in 9 days and Kavya in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Saanvi works twice as fast as Arjun. Together they finish a job in 12 days. How many days would Arjun take alone?
- 36.Vivaan and Rahul together finish a job in 2 days. Vivaan alone takes 4 days. How many days would Rahul take alone?
- 37.Rahul can finish a job in 7 days and Diya in 9 days. What fraction of the job do they finish if they work together for 3 days? =
- 38.Diya can finish a job in 6 days and Meera in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Aarav works twice as fast as Saanvi. Together they finish a job in 4 days. How many days would Saanvi take alone?
- 40.Kabir can finish a job in 10 days and Rahul in 20 days. What fraction of the job do they finish if they work together for 1 day? =
Answer key
- 30/11
- 12
- 52/17
- 21
- 32
- 33
- 143/24
- 19/26
- 28
- 48/19
- 18/5
- 37/171
- 8
- 4
- 24
- 4
- 56/171
- 156/25
- 29/70
- 240/31
- 126/23
- 40/13
- 28/9
- 136/25
- 30
- 8
- 28
- 20
- 3
- 1
- 3
- 30/11
- 26/55
- 117/22
- 36
- 4
- 16/21
- 102/23
- 12
- 3/20