Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Vivaan and Kabir together finish a job in 2 days. Vivaan alone takes 3 days. How many days would Kabir take alone?
- 2.Ananya can finish a job in 8 days and Tara in 4 days. Ananya works alone for 4 days and then stops. Tara finishes the rest. How many days does Tara take?
- 3.Ananya can finish a job in 14 days and Kabir in 5 days. What fraction of the job do they finish if they work together for 3 days? =
- 4.Ishaan can finish a job in 18 days and Rahul in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Nisha can finish a job in 4 days and Priya in 15 days. What fraction of the job do they finish if they work together for 2 days? =
- 6.Aarav can finish a job in 8 days and Zoya in 15 days. What fraction of the job do they finish if they work together for 1 day? =
- 7.Farhan can finish a job in 8 days and Pooja in 16 days. Farhan works alone for 4 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 8.Manav can finish a job in 7 days and Saanvi in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 9.Vivaan works twice as fast as Kabir. Together they finish a job in 11 days. How many days would Kabir take alone?
- 10.Rahul can finish a job in 15 days and Pooja in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Zoya can finish a job in 20 days and Diya in 10 days. Zoya works alone for 2 days and then stops. Diya finishes the rest. How many days does Diya take?
- 12.Ishaan can finish a job in 10 days and Rahul in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Isha can finish a job in 17 days and Arjun in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Zoya can finish a job in 5 days and Rahul in 7 days. What fraction of the job do they finish if they work together for 1 day? =
- 15.Rohan can finish a job in 6 days and Manav in 10 days. What fraction of the job do they finish if they work together for 3 days? =
- 16.Aarav works twice as fast as Saanvi. Together they finish a job in 6 days. How many days would Saanvi take alone?
- 17.Ananya can finish a job in 8 days and Meera in 18 days. What fraction of the job do they finish if they work together for 1 day? =
- 18.Diya can finish a job in 5 days and Priya in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 19.Priya can finish a job in 6 days and Ishaan in 30 days. Priya works alone for 4 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 20.Meera works twice as fast as Vivaan. Together they finish a job in 6 days. How many days would Vivaan take alone?
- 21.Isha works three times as fast as Tara. Together they finish a job in 12 days. How many days would Tara take alone?
- 22.Rahul and Isha together finish a job in 9 days. Rahul alone takes 18 days. How many days would Isha take alone?
- 23.Isha can finish a job in 6 days and Nisha in 12 days. Isha works alone for 1 day and then stops. Nisha finishes the rest. How many days does Nisha take?
- 24.Pooja can finish a job in 20 days and Rahul in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Isha can finish a job in 19 days and Pooja in 8 days. What fraction of the job do they finish if they work together for 1 day? =
- 26.Diya and Sneha together finish a job in 2 days. Diya alone takes 4 days. How many days would Sneha take alone?
- 27.Diya can finish a job in 9 days and Zoya in 27 days. Diya works alone for 5 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 28.Arjun can finish a job in 9 days and Kavya in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 29.Priya and Saanvi together finish a job in 6 days. Priya alone takes 15 days. How many days would Saanvi take alone?
- 30.Priya can finish a job in 6 days and Aarav in 27 days. Priya works alone for 4 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 31.Saanvi can finish a job in 7 days and Aditya in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 32.Rahul and Zoya together finish a job in 6 days. Rahul alone takes 9 days. How many days would Zoya take alone?
- 33.Priya and Dev together finish a job in 16 days. Priya alone takes 24 days. How many days would Dev take alone?
- 34.Aarav can finish a job in 8 days and Priya in 13 days. What fraction of the job do they finish if they work together for 1 day? =
- 35.Kavya can finish a job in 15 days and Priya in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Rahul works twice as fast as Kabir. Together they finish a job in 4 days. How many days would Kabir take alone?
- 37.Diya can finish a job in 6 days and Meera in 26 days. Diya works alone for 3 days and then stops. Meera finishes the rest. How many days does Meera take?
- 38.Ananya can finish a job in 18 days and Ishaan in 4 days. Ananya works alone for 9 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 39.Sneha works twice as fast as Aditya. Together they finish a job in 8 days. How many days would Aditya take alone?
- 40.Rahul and Diya together finish a job in 2 days. Rahul alone takes 3 days. How many days would Diya take alone?
Answer key
- 6
- 2
- 57/70
- 342/37
- 19/30
- 23/120
- 8
- 63/16
- 33
- 120/23
- 9
- 90/19
- 255/32
- 12/35
- 4/5
- 18
- 13/72
- 21/40
- 10
- 18
- 48
- 18
- 10
- 20/11
- 27/152
- 4
- 12
- 5/9
- 10
- 9
- 12/35
- 18
- 48
- 21/104
- 240/31
- 12
- 13
- 2
- 24
- 6