Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Sneha works twice as fast as Aarav. Together they finish a job in 9 days. How many days would Aarav take alone?
- 2.Rohan can finish a job in 18 days and Isha in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 3.Priya can finish a job in 13 days and Zoya in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Rohan can finish a job in 6 days and Meera in 10 days. Rohan works alone for 3 days and then stops. Meera finishes the rest. How many days does Meera take?
- 5.Rahul can finish a job in 4 days and Zoya in 11 days. What fraction of the job do they finish if they work together for 1 day? =
- 6.Meera can finish a job in 5 days and Rohan in 20 days. Meera works alone for 2 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 7.Vivaan works three times as fast as Meera. Together they finish a job in 10 days. How many days would Meera take alone?
- 8.Rahul can finish a job in 9 days and Aarav in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 9.Farhan and Ananya together finish a job in 2 days. Farhan alone takes 3 days. How many days would Ananya take alone?
- 10.Priya can finish a job in 6 days and Rahul in 24 days. Priya works alone for 2 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 11.Arjun and Diya together finish a job in 4 days. Arjun alone takes 6 days. How many days would Diya take alone?
- 12.Karan and Dev together finish a job in 3 days. Karan alone takes 4 days. How many days would Dev take alone?
- 13.Isha and Diya together finish a job in 6 days. Isha alone takes 12 days. How many days would Diya take alone?
- 14.Farhan can finish a job in 10 days and Priya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Kabir and Tara together finish a job in 2 days. Kabir alone takes 4 days. How many days would Tara take alone?
- 16.Kabir can finish a job in 12 days and Arjun in 24 days. Kabir works alone for 5 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 17.Vivaan works twice as fast as Pooja. Together they finish a job in 5 days. How many days would Pooja take alone?
- 18.Arjun can finish a job in 10 days and Kabir in 5 days. Arjun works alone for 2 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 19.Aarav works three times as fast as Rohan. Together they finish a job in 9 days. How many days would Rohan take alone?
- 20.Rohan can finish a job in 2 days and Diya in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Ishaan can finish a job in 20 days and Meera in 15 days. Ishaan works alone for 8 days and then stops. Meera finishes the rest. How many days does Meera take?
- 22.Zoya works twice as fast as Priya. Together they finish a job in 3 days. How many days would Priya take alone?
- 23.Isha can finish a job in 13 days and Aarav in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 24.Kabir works twice as fast as Arjun. Together they finish a job in 12 days. How many days would Arjun take alone?
- 25.Nisha can finish a job in 14 days and Meera in 7 days. Nisha works alone for 10 days and then stops. Meera finishes the rest. How many days does Meera take?
- 26.Manav and Aarav together finish a job in 20 days. Manav alone takes 30 days. How many days would Aarav take alone?
- 27.Diya can finish a job in 4 days and Arjun in 20 days. What fraction of the job do they finish if they work together for 1 day? =
- 28.Nisha can finish a job in 10 days and Meera in 18 days. Nisha works alone for 5 days and then stops. Meera finishes the rest. How many days does Meera take?
- 29.Farhan and Isha together finish a job in 10 days. Farhan alone takes 14 days. How many days would Isha take alone?
- 30.Kabir can finish a job in 17 days and Rahul in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Dev works twice as fast as Rohan. Together they finish a job in 3 days. How many days would Rohan take alone?
- 32.Saanvi can finish a job in 7 days and Aditya in 19 days. What fraction of the job do they finish if they work together for 1 day? =
- 33.Meera can finish a job in 6 days and Vivaan in 21 days. Meera works alone for 2 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 34.Rahul can finish a job in 12 days and Aarav in 9 days. What fraction of the job do they finish if they work together for 1 day? =
- 35.Aditya works three times as fast as Arjun. Together they finish a job in 3 days. How many days would Arjun take alone?
- 36.Karan and Kabir together finish a job in 2 days. Karan alone takes 3 days. How many days would Kabir take alone?
- 37.Diya can finish a job in 16 days and Aarav in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Dev can finish a job in 2 days and Isha in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Meera can finish a job in 9 days and Isha in 6 days. Meera works alone for 6 days and then stops. Isha finishes the rest. How many days does Isha take?
- 40.Priya can finish a job in 6 days and Saanvi in 30 days. Priya works alone for 2 days and then stops. Saanvi finishes the rest. How many days does Saanvi take?
Answer key
- 27
- 4/9
- 52/17
- 5
- 15/44
- 12
- 40
- 63/16
- 6
- 16
- 12
- 12
- 12
- 45/7
- 4
- 14
- 15
- 4
- 36
- 16/9
- 9
- 9
- 78/19
- 36
- 2
- 60
- 3/10
- 9
- 35
- 323/36
- 9
- 26/133
- 14
- 7/36
- 12
- 6
- 240/31
- 14/9
- 2
- 20