Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Manav and Aarav together finish a job in 3 days. Manav alone takes 6 days. How many days would Aarav take alone?
- 2.Rohan can finish a job in 4 days and Meera in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 3.Isha and Kavya together finish a job in 4 days. Isha alone takes 5 days. How many days would Kavya take alone?
- 4.Pooja can finish a job in 20 days and Vivaan in 4 days. Pooja works alone for 10 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 5.Rahul works twice as fast as Ishaan. Together they finish a job in 7 days. How many days would Ishaan take alone?
- 6.Meera works three times as fast as Vivaan. Together they finish a job in 2 days. How many days would Vivaan take alone?
- 7.Zoya works three times as fast as Meera. Together they finish a job in 11 days. How many days would Meera take alone?
- 8.Vivaan can finish a job in 24 days and Meera in 8 days. Vivaan works alone for 12 days and then stops. Meera finishes the rest. How many days does Meera take?
- 9.Kabir can finish a job in 8 days and Tara in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Pooja and Isha together finish a job in 4 days. Pooja alone takes 6 days. How many days would Isha take alone?
- 11.Arjun works three times as fast as Priya. Together they finish a job in 3 days. How many days would Priya take alone?
- 12.Karan works three times as fast as Farhan. Together they finish a job in 7 days. How many days would Farhan take alone?
- 13.Diya and Isha together finish a job in 3 days. Diya alone takes 4 days. How many days would Isha take alone?
- 14.Sneha can finish a job in 19 days and Manav in 18 days. What fraction of the job do they finish if they work together for 1 day? =
- 15.Manav can finish a job in 15 days and Pooja in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Pooja can finish a job in 17 days and Dev in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 17.Tara can finish a job in 5 days and Rahul in 25 days. Tara works alone for 2 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 18.Arjun works three times as fast as Saanvi. Together they finish a job in 4 days. How many days would Saanvi take alone?
- 19.Nisha can finish a job in 4 days and Tara in 10 days. Nisha works alone for 2 days and then stops. Tara finishes the rest. How many days does Tara take?
- 20.Aarav can finish a job in 18 days and Diya in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Farhan and Ananya together finish a job in 3 days. Farhan alone takes 4 days. How many days would Ananya take alone?
- 22.Farhan and Diya together finish a job in 5 days. Farhan alone takes 6 days. How many days would Diya take alone?
- 23.Karan can finish a job in 11 days and Meera in 22 days. Karan works alone for 6 days and then stops. Meera finishes the rest. How many days does Meera take?
- 24.Manav can finish a job in 14 days and Nisha in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Saanvi can finish a job in 13 days and Aarav in 12 days. What fraction of the job do they finish if they work together for 2 days? =
- 26.Diya can finish a job in 20 days and Kavya in 5 days. What fraction of the job do they finish if they work together for 2 days? =
- 27.Aditya works twice as fast as Sneha. Together they finish a job in 11 days. How many days would Sneha take alone?
- 28.Kabir can finish a job in 22 days and Aditya in 11 days. Kabir works alone for 12 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 29.Diya can finish a job in 11 days and Kavya in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 30.Priya can finish a job in 7 days and Nisha in 9 days. What fraction of the job do they finish if they work together for 3 days? =
- 31.Ananya can finish a job in 10 days and Aarav in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 32.Arjun and Saanvi together finish a job in 4 days. Arjun alone takes 8 days. How many days would Saanvi take alone?
- 33.Sneha can finish a job in 6 days and Rahul in 17 days. What fraction of the job do they finish if they work together for 3 days? =
- 34.Dev works three times as fast as Nisha. Together they finish a job in 5 days. How many days would Nisha take alone?
- 35.Manav can finish a job in 18 days and Kavya in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Nisha and Rahul together finish a job in 16 days. Nisha alone takes 20 days. How many days would Rahul take alone?
- 37.Manav can finish a job in 7 days and Kabir in 4 days. What fraction of the job do they finish if they work together for 1 day? =
- 38.Farhan can finish a job in 17 days and Rohan in 4 days. What fraction of the job do they finish if they work together for 3 days? =
- 39.Rahul and Arjun together finish a job in 2 days. Rahul alone takes 4 days. How many days would Arjun take alone?
- 40.Rahul and Nisha together finish a job in 12 days. Rahul alone takes 18 days. How many days would Nisha take alone?
Answer key
- 6
- 12/7
- 20
- 2
- 21
- 8
- 44
- 4
- 56/11
- 12
- 12
- 28
- 12
- 37/342
- 15/4
- 35/153
- 15
- 16
- 5
- 36/5
- 12
- 30
- 10
- 112/15
- 25/78
- 1/2
- 33
- 5
- 143/24
- 16/21
- 4/5
- 8
- 23/34
- 20
- 90/23
- 80
- 11/28
- 63/68
- 4
- 36