Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Isha works twice as fast as Pooja. Together they finish a job in 12 days. How many days would Pooja take alone?
- 2.Saanvi works three times as fast as Rahul. Together they finish a job in 12 days. How many days would Rahul take alone?
- 3.Farhan can finish a job in 8 days and Aarav in 20 days. What fraction of the job do they finish if they work together for 2 days? =
- 4.Nisha works twice as fast as Kabir. Together they finish a job in 6 days. How many days would Kabir take alone?
- 5.Tara works three times as fast as Ananya. Together they finish a job in 12 days. How many days would Ananya take alone?
- 6.Meera can finish a job in 15 days and Aarav in 12 days. Meera works alone for 10 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 7.Dev and Zoya together finish a job in 6 days. Dev alone takes 8 days. How many days would Zoya take alone?
- 8.Farhan works three times as fast as Meera. Together they finish a job in 10 days. How many days would Meera take alone?
- 9.Nisha can finish a job in 15 days and Vivaan in 18 days. Nisha works alone for 10 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 10.Arjun can finish a job in 16 days and Karan in 19 days. What fraction of the job do they finish if they work together for 2 days? =
- 11.Ishaan and Meera together finish a job in 6 days. Ishaan alone takes 9 days. How many days would Meera take alone?
- 12.Aarav works twice as fast as Zoya. Together they finish a job in 5 days. How many days would Zoya take alone?
- 13.Isha can finish a job in 4 days and Rahul in 12 days. Isha works alone for 2 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 14.Pooja and Farhan together finish a job in 4 days. Pooja alone takes 12 days. How many days would Farhan take alone?
- 15.Kavya can finish a job in 15 days and Vivaan in 11 days. What fraction of the job do they finish if they work together for 1 day? =
- 16.Karan can finish a job in 18 days and Diya in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Meera can finish a job in 25 days and Arjun in 10 days. Meera works alone for 10 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 18.Meera and Priya together finish a job in 4 days. Meera alone takes 6 days. How many days would Priya take alone?
- 19.Tara works three times as fast as Ananya. Together they finish a job in 5 days. How many days would Ananya take alone?
- 20.Diya can finish a job in 12 days and Kabir in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Saanvi and Kabir together finish a job in 4 days. Saanvi alone takes 6 days. How many days would Kabir take alone?
- 22.Arjun can finish a job in 8 days and Aarav in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Meera can finish a job in 7 days and Rohan in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 24.Rahul and Ishaan together finish a job in 5 days. Rahul alone takes 10 days. How many days would Ishaan take alone?
- 25.Manav and Zoya together finish a job in 2 days. Manav alone takes 3 days. How many days would Zoya take alone?
- 26.Farhan can finish a job in 8 days and Pooja in 28 days. Farhan works alone for 6 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 27.Manav can finish a job in 12 days and Meera in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Priya can finish a job in 4 days and Meera in 30 days. Priya works alone for 2 days and then stops. Meera finishes the rest. How many days does Meera take?
- 29.Meera can finish a job in 15 days and Manav in 12 days. Meera works alone for 10 days and then stops. Manav finishes the rest. How many days does Manav take?
- 30.Aarav and Farhan together finish a job in 12 days. Aarav alone takes 15 days. How many days would Farhan take alone?
- 31.Zoya can finish a job in 4 days and Dev in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Aarav and Karan together finish a job in 12 days. Aarav alone takes 20 days. How many days would Karan take alone?
- 33.Tara can finish a job in 8 days and Rahul in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Kabir and Rohan together finish a job in 10 days. Kabir alone takes 12 days. How many days would Rohan take alone?
- 35.Tara can finish a job in 4 days and Rohan in 12 days. Tara works alone for 3 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 36.Meera and Sneha together finish a job in 2 days. Meera alone takes 4 days. How many days would Sneha take alone?
- 37.Diya can finish a job in 9 days and Ishaan in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 38.Aarav can finish a job in 10 days and Rahul in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Dev and Karan together finish a job in 4 days. Dev alone takes 6 days. How many days would Karan take alone?
- 40.Karan and Vivaan together finish a job in 4 days. Karan alone takes 8 days. How many days would Vivaan take alone?
Answer key
- 36
- 48
- 7/20
- 18
- 48
- 4
- 24
- 40
- 6
- 35/152
- 18
- 15
- 6
- 6
- 26/165
- 234/31
- 6
- 12
- 20
- 60/17
- 12
- 56/15
- 63/16
- 10
- 6
- 7
- 84/19
- 15
- 4
- 60
- 4/3
- 30
- 8/5
- 60
- 3
- 4
- 23/63
- 170/27
- 12
- 8