Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Aditya and Ananya together finish a job in 3 days. Aditya alone takes 4 days. How many days would Ananya take alone?
- 2.Aditya and Ananya together finish a job in 15 days. Aditya alone takes 30 days. How many days would Ananya take alone?
- 3.Rahul and Pooja together finish a job in 2 days. Rahul alone takes 6 days. How many days would Pooja take alone?
- 4.Diya and Dev together finish a job in 18 days. Diya alone takes 24 days. How many days would Dev take alone?
- 5.Isha can finish a job in 6 days and Sneha in 28 days. Isha works alone for 3 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 6.Kabir can finish a job in 13 days and Zoya in 19 days. What fraction of the job do they finish if they work together for 1 day? =
- 7.Tara can finish a job in 13 days and Arjun in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Tara can finish a job in 14 days and Pooja in 15 days. What fraction of the job do they finish if they work together for 3 days? =
- 9.Ishaan and Zoya together finish a job in 4 days. Ishaan alone takes 6 days. How many days would Zoya take alone?
- 10.Dev can finish a job in 20 days and Kabir in 8 days. What fraction of the job do they finish if they work together for 2 days? =
- 11.Pooja can finish a job in 11 days and Diya in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Arjun can finish a job in 12 days and Nisha in 18 days. What fraction of the job do they finish if they work together for 3 days? =
- 13.Diya can finish a job in 13 days and Karan in 6 days. What fraction of the job do they finish if they work together for 1 day? =
- 14.Sneha can finish a job in 8 days and Diya in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Isha can finish a job in 5 days and Meera in 25 days. Isha works alone for 3 days and then stops. Meera finishes the rest. How many days does Meera take?
- 16.Zoya can finish a job in 5 days and Nisha in 20 days. Zoya works alone for 1 day and then stops. Nisha finishes the rest. How many days does Nisha take?
- 17.Manav can finish a job in 12 days and Vivaan in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Aditya works twice as fast as Saanvi. Together they finish a job in 11 days. How many days would Saanvi take alone?
- 19.Ishaan can finish a job in 5 days and Manav in 12 days. What fraction of the job do they finish if they work together for 3 days? =
- 20.Manav and Priya together finish a job in 16 days. Manav alone takes 20 days. How many days would Priya take alone?
- 21.Isha can finish a job in 5 days and Kabir in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Zoya and Karan together finish a job in 2 days. Zoya alone takes 3 days. How many days would Karan take alone?
- 23.Manav can finish a job in 17 days and Saanvi in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 24.Karan and Pooja together finish a job in 10 days. Karan alone takes 12 days. How many days would Pooja take alone?
- 25.Ananya works twice as fast as Diya. Together they finish a job in 4 days. How many days would Diya take alone?
- 26.Arjun and Vivaan together finish a job in 7 days. Arjun alone takes 8 days. How many days would Vivaan take alone?
- 27.Isha works three times as fast as Nisha. Together they finish a job in 10 days. How many days would Nisha take alone?
- 28.Arjun can finish a job in 11 days and Manav in 5 days. What fraction of the job do they finish if they work together for 3 days? =
- 29.Priya can finish a job in 5 days and Meera in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 30.Diya can finish a job in 5 days and Aarav in 30 days. Diya works alone for 1 day and then stops. Aarav finishes the rest. How many days does Aarav take?
- 31.Manav can finish a job in 5 days and Rahul in 10 days. Manav works alone for 2 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 32.Nisha can finish a job in 3 days and Rohan in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Farhan can finish a job in 6 days and Sneha in 18 days. Farhan works alone for 5 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 34.Rahul and Ananya together finish a job in 21 days. Rahul alone takes 28 days. How many days would Ananya take alone?
- 35.Meera and Arjun together finish a job in 3 days. Meera alone takes 4 days. How many days would Arjun take alone?
- 36.Aditya can finish a job in 28 days and Vivaan in 14 days. Aditya works alone for 22 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 37.Tara can finish a job in 17 days and Meera in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 38.Priya can finish a job in 12 days and Pooja in 8 days. Priya works alone for 9 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 39.Kavya can finish a job in 6 days and Arjun in 20 days. Kavya works alone for 3 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 40.Farhan can finish a job in 4 days and Sneha in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
Answer key
- 12
- 30
- 3
- 72
- 14
- 32/247
- 143/24
- 29/70
- 12
- 7/20
- 88/19
- 5/12
- 19/78
- 8/3
- 10
- 16
- 36/7
- 33
- 17/20
- 80
- 60/17
- 6
- 31/119
- 60
- 12
- 56
- 40
- 48/55
- 15/4
- 24
- 6
- 5/2
- 3
- 84
- 12
- 3
- 23/34
- 2
- 10
- 68/21