Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Isha can finish a job in 18 days and Kavya in 6 days. Isha works alone for 15 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 2.Vivaan can finish a job in 2 days and Zoya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 3.Kabir can finish a job in 9 days and Dev in 6 days. Kabir works alone for 3 days and then stops. Dev finishes the rest. How many days does Dev take?
- 4.Isha and Zoya together finish a job in 2 days. Isha alone takes 4 days. How many days would Zoya take alone?
- 5.Farhan can finish a job in 14 days and Ishaan in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Ananya can finish a job in 2 days and Sneha in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Kavya can finish a job in 9 days and Sneha in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Priya can finish a job in 5 days and Zoya in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 9.Tara can finish a job in 3 days and Kabir in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Karan can finish a job in 15 days and Farhan in 6 days. Karan works alone for 5 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 11.Aarav can finish a job in 10 days and Kavya in 5 days. Aarav works alone for 8 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 12.Sneha can finish a job in 26 days and Farhan in 20 days. Sneha works alone for 13 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 13.Saanvi works twice as fast as Arjun. Together they finish a job in 2 days. How many days would Arjun take alone?
- 14.Ananya can finish a job in 2 days and Rahul in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Nisha can finish a job in 4 days and Kabir in 24 days. Nisha works alone for 3 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 16.Kavya works twice as fast as Saanvi. Together they finish a job in 5 days. How many days would Saanvi take alone?
- 17.Ananya can finish a job in 11 days and Meera in 15 days. What fraction of the job do they finish if they work together for 1 day? =
- 18.Nisha works twice as fast as Saanvi. Together they finish a job in 5 days. How many days would Saanvi take alone?
- 19.Isha works twice as fast as Manav. Together they finish a job in 11 days. How many days would Manav take alone?
- 20.Rahul can finish a job in 13 days and Zoya in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Rohan can finish a job in 14 days and Nisha in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Meera can finish a job in 18 days and Vivaan in 8 days. What fraction of the job do they finish if they work together for 3 days? =
- 23.Diya can finish a job in 6 days and Dev in 4 days. What fraction of the job do they finish if they work together for 2 days? =
- 24.Meera can finish a job in 7 days and Farhan in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Vivaan and Arjun together finish a job in 8 days. Vivaan alone takes 9 days. How many days would Arjun take alone?
- 26.Kabir and Vivaan together finish a job in 8 days. Kabir alone takes 16 days. How many days would Vivaan take alone?
- 27.Diya can finish a job in 10 days and Aarav in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Priya can finish a job in 20 days and Karan in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 29.Kabir and Meera together finish a job in 8 days. Kabir alone takes 16 days. How many days would Meera take alone?
- 30.Vivaan and Ananya together finish a job in 5 days. Vivaan alone takes 6 days. How many days would Ananya take alone?
- 31.Meera and Aarav together finish a job in 8 days. Meera alone takes 16 days. How many days would Aarav take alone?
- 32.Tara can finish a job in 3 days and Meera in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Rohan and Manav together finish a job in 2 days. Rohan alone takes 6 days. How many days would Manav take alone?
- 34.Vivaan can finish a job in 10 days and Tara in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 35.Pooja works three times as fast as Kabir. Together they finish a job in 9 days. How many days would Kabir take alone?
- 36.Arjun can finish a job in 12 days and Tara in 18 days. What fraction of the job do they finish if they work together for 1 day? =
- 37.Rahul can finish a job in 20 days and Priya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Sneha can finish a job in 12 days and Dev in 6 days. Sneha works alone for 8 days and then stops. Dev finishes the rest. How many days does Dev take?
- 39.Diya works twice as fast as Meera. Together they finish a job in 8 days. How many days would Meera take alone?
- 40.Vivaan can finish a job in 9 days and Ananya in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
Answer key
- 1
- 6/5
- 4
- 4
- 182/27
- 8/5
- 36/7
- 23/45
- 6/5
- 4
- 1
- 10
- 6
- 22/13
- 6
- 15
- 26/165
- 15
- 33
- 156/25
- 70/19
- 13/24
- 5/6
- 35/12
- 72
- 16
- 130/23
- 9/40
- 16
- 30
- 16
- 48/19
- 3
- 13/40
- 36
- 5/36
- 180/19
- 2
- 24
- 18/11