Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Diya can finish a job in 10 days and Kabir in 25 days. Diya works alone for 4 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 2.Pooja can finish a job in 9 days and Ishaan in 16 days. What fraction of the job do they finish if they work together for 3 days? =
- 3.Tara can finish a job in 17 days and Ananya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Kabir can finish a job in 7 days and Aarav in 21 days. Kabir works alone for 1 day and then stops. Aarav finishes the rest. How many days does Aarav take?
- 5.Kavya can finish a job in 10 days and Vivaan in 25 days. Kavya works alone for 4 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 6.Farhan works twice as fast as Dev. Together they finish a job in 11 days. How many days would Dev take alone?
- 7.Karan can finish a job in 12 days and Tara in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Arjun works twice as fast as Manav. Together they finish a job in 3 days. How many days would Manav take alone?
- 9.Nisha works twice as fast as Aditya. Together they finish a job in 7 days. How many days would Aditya take alone?
- 10.Dev and Rahul together finish a job in 2 days. Dev alone takes 4 days. How many days would Rahul take alone?
- 11.Meera and Farhan together finish a job in 8 days. Meera alone takes 10 days. How many days would Farhan take alone?
- 12.Dev can finish a job in 9 days and Rahul in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 13.Ishaan and Aarav together finish a job in 2 days. Ishaan alone takes 4 days. How many days would Aarav take alone?
- 14.Zoya can finish a job in 4 days and Kavya in 6 days. Zoya works alone for 2 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 15.Diya can finish a job in 19 days and Manav in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Sneha and Rohan together finish a job in 2 days. Sneha alone takes 4 days. How many days would Rohan take alone?
- 17.Rohan can finish a job in 11 days and Kabir in 15 days. What fraction of the job do they finish if they work together for 3 days? =
- 18.Nisha can finish a job in 2 days and Priya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Kabir can finish a job in 6 days and Tara in 24 days. Kabir works alone for 2 days and then stops. Tara finishes the rest. How many days does Tara take?
- 20.Aarav and Kavya together finish a job in 3 days. Aarav alone takes 6 days. How many days would Kavya take alone?
- 21.Saanvi can finish a job in 18 days and Kavya in 4 days. What fraction of the job do they finish if they work together for 2 days? =
- 22.Aarav can finish a job in 11 days and Ishaan in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Pooja can finish a job in 9 days and Dev in 15 days. Pooja works alone for 6 days and then stops. Dev finishes the rest. How many days does Dev take?
- 24.Isha works three times as fast as Priya. Together they finish a job in 4 days. How many days would Priya take alone?
- 25.Dev and Kabir together finish a job in 6 days. Dev alone takes 8 days. How many days would Kabir take alone?
- 26.Aarav can finish a job in 20 days and Nisha in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Aditya can finish a job in 10 days and Pooja in 25 days. Aditya works alone for 4 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 28.Diya can finish a job in 19 days and Zoya in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Dev works twice as fast as Rohan. Together they finish a job in 5 days. How many days would Rohan take alone?
- 30.Ishaan can finish a job in 15 days and Diya in 30 days. Ishaan works alone for 3 days and then stops. Diya finishes the rest. How many days does Diya take?
- 31.Tara can finish a job in 7 days and Rohan in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Arjun can finish a job in 13 days and Sneha in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Vivaan can finish a job in 22 days and Zoya in 11 days. Vivaan works alone for 4 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 34.Kavya can finish a job in 2 days and Diya in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Priya and Zoya together finish a job in 8 days. Priya alone takes 12 days. How many days would Zoya take alone?
- 36.Vivaan and Ananya together finish a job in 5 days. Vivaan alone takes 10 days. How many days would Ananya take alone?
- 37.Rahul can finish a job in 7 days and Ishaan in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Aarav can finish a job in 6 days and Aditya in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 39.Karan can finish a job in 20 days and Meera in 7 days. What fraction of the job do they finish if they work together for 2 days? =
- 40.Rahul can finish a job in 20 days and Saanvi in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
Answer key
- 15
- 25/48
- 51/20
- 18
- 15
- 33
- 204/29
- 9
- 21
- 4
- 40
- 23/63
- 4
- 3
- 38/21
- 4
- 26/55
- 6/5
- 16
- 6
- 11/18
- 154/25
- 5
- 16
- 24
- 10/3
- 15
- 285/34
- 15
- 24
- 77/18
- 143/24
- 9
- 7/4
- 24
- 10
- 70/17
- 19/26
- 27/70
- 140/17