Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Arjun can finish a job in 16 days and Rahul in 7 days. What fraction of the job do they finish if they work together for 2 days? =
- 2.Diya can finish a job in 10 days and Karan in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 3.Tara and Meera together finish a job in 8 days. Tara alone takes 9 days. How many days would Meera take alone?
- 4.Ananya can finish a job in 6 days and Isha in 18 days. Ananya works alone for 5 days and then stops. Isha finishes the rest. How many days does Isha take?
- 5.Priya can finish a job in 3 days and Farhan in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Kabir can finish a job in 6 days and Isha in 21 days. Kabir works alone for 2 days and then stops. Isha finishes the rest. How many days does Isha take?
- 7.Nisha can finish a job in 24 days and Kavya in 30 days. Nisha works alone for 8 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 8.Rohan can finish a job in 11 days and Arjun in 22 days. Rohan works alone for 3 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 9.Ishaan can finish a job in 28 days and Ananya in 14 days. Ishaan works alone for 10 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 10.Nisha can finish a job in 18 days and Karan in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Manav can finish a job in 4 days and Kabir in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Kavya and Sneha together finish a job in 6 days. Kavya alone takes 24 days. How many days would Sneha take alone?
- 13.Tara can finish a job in 6 days and Ishaan in 18 days. Tara works alone for 2 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 14.Rahul works three times as fast as Diya. Together they finish a job in 5 days. How many days would Diya take alone?
- 15.Rohan can finish a job in 13 days and Ananya in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 16.Ishaan works twice as fast as Ananya. Together they finish a job in 7 days. How many days would Ananya take alone?
- 17.Meera can finish a job in 16 days and Ananya in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Rahul can finish a job in 4 days and Rohan in 6 days. Rahul works alone for 2 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 19.Rohan works twice as fast as Aarav. Together they finish a job in 6 days. How many days would Aarav take alone?
- 20.Isha and Kavya together finish a job in 3 days. Isha alone takes 12 days. How many days would Kavya take alone?
- 21.Vivaan can finish a job in 30 days and Ananya in 12 days. Vivaan works alone for 10 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 22.Meera can finish a job in 7 days and Sneha in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Ishaan and Kabir together finish a job in 2 days. Ishaan alone takes 3 days. How many days would Kabir take alone?
- 24.Aditya can finish a job in 9 days and Karan in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Ananya can finish a job in 17 days and Rahul in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 26.Diya can finish a job in 30 days and Vivaan in 18 days. Diya works alone for 5 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 27.Vivaan can finish a job in 18 days and Nisha in 19 days. What fraction of the job do they finish if they work together for 2 days? =
- 28.Saanvi can finish a job in 13 days and Aditya in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Priya can finish a job in 12 days and Dev in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 30.Diya and Priya together finish a job in 3 days. Diya alone takes 12 days. How many days would Priya take alone?
- 31.Meera and Karan together finish a job in 3 days. Meera alone takes 4 days. How many days would Karan take alone?
- 32.Ishaan and Diya together finish a job in 3 days. Ishaan alone takes 4 days. How many days would Diya take alone?
- 33.Arjun and Tara together finish a job in 3 days. Arjun alone takes 4 days. How many days would Tara take alone?
- 34.Sneha and Pooja together finish a job in 8 days. Sneha alone takes 9 days. How many days would Pooja take alone?
- 35.Nisha works twice as fast as Saanvi. Together they finish a job in 8 days. How many days would Saanvi take alone?
- 36.Zoya can finish a job in 18 days and Ananya in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 37.Rahul can finish a job in 10 days and Arjun in 20 days. Rahul works alone for 5 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 38.Ananya can finish a job in 4 days and Farhan in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Arjun can finish a job in 20 days and Rahul in 13 days. What fraction of the job do they finish if they work together for 2 days? =
- 40.Kavya and Aditya together finish a job in 2 days. Kavya alone takes 4 days. How many days would Aditya take alone?
Answer key
- 23/56
- 40/9
- 72
- 3
- 18/7
- 14
- 20
- 16
- 9
- 90/23
- 3
- 8
- 12
- 20
- 23/130
- 21
- 208/29
- 3
- 18
- 4
- 8
- 14/9
- 6
- 144/25
- 323/36
- 15
- 37/171
- 208/29
- 3/4
- 4
- 12
- 12
- 12
- 72
- 24
- 2/3
- 10
- 52/17
- 33/130
- 4