Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Aditya can finish a job in 18 days and Farhan in 4 days. What fraction of the job do they finish if they work together for 1 day? =
- 2.Farhan can finish a job in 7 days and Vivaan in 9 days. What fraction of the job do they finish if they work together for 1 day? =
- 3.Sneha can finish a job in 6 days and Saanvi in 12 days. Sneha works alone for 3 days and then stops. Saanvi finishes the rest. How many days does Saanvi take?
- 4.Diya can finish a job in 15 days and Ananya in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Tara can finish a job in 18 days and Aarav in 12 days. What fraction of the job do they finish if they work together for 1 day? =
- 6.Sneha works three times as fast as Nisha. Together they finish a job in 9 days. How many days would Nisha take alone?
- 7.Sneha and Rahul together finish a job in 4 days. Sneha alone takes 6 days. How many days would Rahul take alone?
- 8.Saanvi works twice as fast as Isha. Together they finish a job in 10 days. How many days would Isha take alone?
- 9.Dev can finish a job in 7 days and Aarav in 28 days. Dev works alone for 2 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 10.Saanvi works twice as fast as Diya. Together they finish a job in 6 days. How many days would Diya take alone?
- 11.Ananya works three times as fast as Isha. Together they finish a job in 4 days. How many days would Isha take alone?
- 12.Vivaan and Sneha together finish a job in 15 days. Vivaan alone takes 24 days. How many days would Sneha take alone?
- 13.Isha and Arjun together finish a job in 6 days. Isha alone takes 7 days. How many days would Arjun take alone?
- 14.Meera and Aditya together finish a job in 2 days. Meera alone takes 4 days. How many days would Aditya take alone?
- 15.Meera can finish a job in 18 days and Aarav in 21 days. Meera works alone for 12 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 16.Karan can finish a job in 12 days and Ananya in 16 days. What fraction of the job do they finish if they work together for 3 days? =
- 17.Rohan can finish a job in 5 days and Nisha in 10 days. Rohan works alone for 1 day and then stops. Nisha finishes the rest. How many days does Nisha take?
- 18.Manav can finish a job in 4 days and Isha in 7 days. What fraction of the job do they finish if they work together for 2 days? =
- 19.Kavya can finish a job in 5 days and Meera in 30 days. Kavya works alone for 1 day and then stops. Meera finishes the rest. How many days does Meera take?
- 20.Aditya can finish a job in 19 days and Rohan in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Manav can finish a job in 4 days and Rohan in 6 days. Manav works alone for 2 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 22.Rahul works three times as fast as Aarav. Together they finish a job in 8 days. How many days would Aarav take alone?
- 23.Aarav can finish a job in 11 days and Farhan in 19 days. What fraction of the job do they finish if they work together for 3 days? =
- 24.Dev can finish a job in 7 days and Nisha in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Kabir and Tara together finish a job in 4 days. Kabir alone takes 8 days. How many days would Tara take alone?
- 26.Zoya can finish a job in 12 days and Karan in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Sneha works three times as fast as Kabir. Together they finish a job in 12 days. How many days would Kabir take alone?
- 28.Aarav works twice as fast as Zoya. Together they finish a job in 7 days. How many days would Zoya take alone?
- 29.Diya can finish a job in 4 days and Kabir in 16 days. Diya works alone for 3 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 30.Farhan and Ananya together finish a job in 10 days. Farhan alone takes 15 days. How many days would Ananya take alone?
- 31.Kabir can finish a job in 10 days and Rohan in 15 days. What fraction of the job do they finish if they work together for 1 day? =
- 32.Kabir and Saanvi together finish a job in 3 days. Kabir alone takes 4 days. How many days would Saanvi take alone?
- 33.Zoya and Farhan together finish a job in 2 days. Zoya alone takes 3 days. How many days would Farhan take alone?
- 34.Kavya and Karan together finish a job in 9 days. Kavya alone takes 10 days. How many days would Karan take alone?
- 35.Rohan works twice as fast as Kavya. Together they finish a job in 5 days. How many days would Kavya take alone?
- 36.Farhan works twice as fast as Saanvi. Together they finish a job in 7 days. How many days would Saanvi take alone?
- 37.Arjun can finish a job in 7 days and Sneha in 14 days. Arjun works alone for 2 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 38.Zoya can finish a job in 4 days and Aarav in 19 days. What fraction of the job do they finish if they work together for 2 days? =
- 39.Farhan can finish a job in 6 days and Dev in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Rahul can finish a job in 19 days and Farhan in 6 days. What fraction of the job do they finish if they work together for 2 days? =
Answer key
- 11/36
- 16/63
- 6
- 255/32
- 5/36
- 36
- 12
- 30
- 20
- 18
- 16
- 40
- 42
- 4
- 7
- 7/16
- 8
- 11/14
- 24
- 304/35
- 3
- 32
- 90/209
- 28/11
- 8
- 20/3
- 48
- 21
- 4
- 30
- 1/6
- 12
- 6
- 90
- 15
- 21
- 10
- 23/38
- 30/11
- 25/57