Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Vivaan can finish a job in 27 days and Ananya in 9 days. Vivaan works alone for 24 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 2.Nisha works twice as fast as Arjun. Together they finish a job in 5 days. How many days would Arjun take alone?
- 3.Farhan can finish a job in 14 days and Arjun in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Priya can finish a job in 17 days and Farhan in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 5.Arjun can finish a job in 5 days and Rohan in 20 days. Arjun works alone for 1 day and then stops. Rohan finishes the rest. How many days does Rohan take?
- 6.Rahul and Ishaan together finish a job in 18 days. Rahul alone takes 24 days. How many days would Ishaan take alone?
- 7.Pooja and Rohan together finish a job in 3 days. Pooja alone takes 4 days. How many days would Rohan take alone?
- 8.Rahul works twice as fast as Kavya. Together they finish a job in 8 days. How many days would Kavya take alone?
- 9.Aditya can finish a job in 19 days and Rahul in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Diya can finish a job in 10 days and Isha in 20 days. Diya works alone for 5 days and then stops. Isha finishes the rest. How many days does Isha take?
- 11.Saanvi works twice as fast as Dev. Together they finish a job in 8 days. How many days would Dev take alone?
- 12.Meera and Karan together finish a job in 6 days. Meera alone takes 10 days. How many days would Karan take alone?
- 13.Priya and Manav together finish a job in 8 days. Priya alone takes 16 days. How many days would Manav take alone?
- 14.Dev works three times as fast as Manav. Together they finish a job in 9 days. How many days would Manav take alone?
- 15.Karan can finish a job in 18 days and Farhan in 6 days. Karan works alone for 15 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 16.Sneha can finish a job in 7 days and Aditya in 21 days. Sneha works alone for 5 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 17.Kabir can finish a job in 10 days and Zoya in 18 days. What fraction of the job do they finish if they work together for 3 days? =
- 18.Saanvi can finish a job in 13 days and Diya in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Nisha can finish a job in 6 days and Isha in 10 days. Nisha works alone for 3 days and then stops. Isha finishes the rest. How many days does Isha take?
- 20.Diya works three times as fast as Vivaan. Together they finish a job in 9 days. How many days would Vivaan take alone?
- 21.Rohan and Rahul together finish a job in 8 days. Rohan alone takes 12 days. How many days would Rahul take alone?
- 22.Kabir can finish a job in 15 days and Ananya in 20 days. Kabir works alone for 6 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 23.Sneha works three times as fast as Meera. Together they finish a job in 11 days. How many days would Meera take alone?
- 24.Kabir can finish a job in 18 days and Aarav in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 25.Manav works three times as fast as Aarav. Together they finish a job in 6 days. How many days would Aarav take alone?
- 26.Zoya can finish a job in 26 days and Farhan in 10 days. Zoya works alone for 13 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 27.Aditya works three times as fast as Meera. Together they finish a job in 6 days. How many days would Meera take alone?
- 28.Rohan can finish a job in 13 days and Sneha in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Zoya and Farhan together finish a job in 8 days. Zoya alone takes 9 days. How many days would Farhan take alone?
- 30.Aarav and Karan together finish a job in 10 days. Aarav alone takes 30 days. How many days would Karan take alone?
- 31.Kabir works twice as fast as Manav. Together they finish a job in 6 days. How many days would Manav take alone?
- 32.Isha works three times as fast as Sneha. Together they finish a job in 3 days. How many days would Sneha take alone?
- 33.Kabir can finish a job in 4 days and Ishaan in 20 days. What fraction of the job do they finish if they work together for 1 day? =
- 34.Meera and Sneha together finish a job in 5 days. Meera alone takes 6 days. How many days would Sneha take alone?
- 35.Karan and Tara together finish a job in 2 days. Karan alone takes 3 days. How many days would Tara take alone?
- 36.Dev works twice as fast as Aarav. Together they finish a job in 3 days. How many days would Aarav take alone?
- 37.Tara can finish a job in 10 days and Priya in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Rahul and Meera together finish a job in 15 days. Rahul alone takes 18 days. How many days would Meera take alone?
- 39.Kabir works twice as fast as Nisha. Together they finish a job in 7 days. How many days would Nisha take alone?
- 40.Pooja can finish a job in 20 days and Saanvi in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
Answer key
- 1
- 15
- 63/8
- 33/136
- 16
- 72
- 12
- 24
- 38/21
- 10
- 24
- 15
- 16
- 36
- 1
- 6
- 7/15
- 260/33
- 5
- 36
- 24
- 12
- 44
- 7/45
- 24
- 5
- 24
- 78/19
- 72
- 15
- 18
- 12
- 3/10
- 30
- 6
- 9
- 5/3
- 90
- 21
- 40/7