Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Karan can finish a job in 4 days and Farhan in 24 days. Karan works alone for 1 day and then stops. Farhan finishes the rest. How many days does Farhan take?
- 2.Ananya can finish a job in 19 days and Manav in 7 days. What fraction of the job do they finish if they work together for 1 day? =
- 3.Arjun can finish a job in 12 days and Karan in 16 days. What fraction of the job do they finish if they work together for 1 day? =
- 4.Vivaan can finish a job in 14 days and Tara in 28 days. Vivaan works alone for 1 day and then stops. Tara finishes the rest. How many days does Tara take?
- 5.Ananya can finish a job in 16 days and Manav in 18 days. Ananya works alone for 8 days and then stops. Manav finishes the rest. How many days does Manav take?
- 6.Sneha can finish a job in 15 days and Manav in 8 days. What fraction of the job do they finish if they work together for 2 days? =
- 7.Nisha can finish a job in 11 days and Farhan in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Vivaan and Pooja together finish a job in 4 days. Vivaan alone takes 6 days. How many days would Pooja take alone?
- 9.Tara can finish a job in 15 days and Sneha in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Meera can finish a job in 6 days and Rahul in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Vivaan works twice as fast as Meera. Together they finish a job in 6 days. How many days would Meera take alone?
- 12.Pooja and Isha together finish a job in 3 days. Pooja alone takes 4 days. How many days would Isha take alone?
- 13.Aarav can finish a job in 4 days and Zoya in 20 days. Aarav works alone for 1 day and then stops. Zoya finishes the rest. How many days does Zoya take?
- 14.Aarav can finish a job in 15 days and Ananya in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 15.Zoya can finish a job in 9 days and Rohan in 18 days. Zoya works alone for 5 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 16.Ananya can finish a job in 20 days and Nisha in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Farhan can finish a job in 6 days and Arjun in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Aditya can finish a job in 15 days and Zoya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Ananya can finish a job in 16 days and Sneha in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 20.Rahul and Farhan together finish a job in 11 days. Rahul alone takes 22 days. How many days would Farhan take alone?
- 21.Meera and Priya together finish a job in 15 days. Meera alone takes 18 days. How many days would Priya take alone?
- 22.Meera can finish a job in 16 days and Kavya in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Farhan and Rahul together finish a job in 4 days. Farhan alone takes 5 days. How many days would Rahul take alone?
- 24.Diya can finish a job in 17 days and Nisha in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Aditya works twice as fast as Priya. Together they finish a job in 4 days. How many days would Priya take alone?
- 26.Kabir works three times as fast as Saanvi. Together they finish a job in 11 days. How many days would Saanvi take alone?
- 27.Dev works twice as fast as Meera. Together they finish a job in 10 days. How many days would Meera take alone?
- 28.Rohan can finish a job in 8 days and Sneha in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Rohan can finish a job in 7 days and Aditya in 14 days. Rohan works alone for 5 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 30.Isha can finish a job in 14 days and Saanvi in 20 days. What fraction of the job do they finish if they work together for 2 days? =
- 31.Rohan can finish a job in 7 days and Sneha in 28 days. Rohan works alone for 5 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 32.Zoya works twice as fast as Arjun. Together they finish a job in 9 days. How many days would Arjun take alone?
- 33.Diya and Isha together finish a job in 2 days. Diya alone takes 4 days. How many days would Isha take alone?
- 34.Isha and Aditya together finish a job in 6 days. Isha alone takes 9 days. How many days would Aditya take alone?
- 35.Ananya can finish a job in 7 days and Dev in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Ananya works three times as fast as Kabir. Together they finish a job in 12 days. How many days would Kabir take alone?
- 37.Kabir works twice as fast as Saanvi. Together they finish a job in 10 days. How many days would Saanvi take alone?
- 38.Ishaan can finish a job in 2 days and Meera in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Saanvi and Rohan together finish a job in 4 days. Saanvi alone takes 8 days. How many days would Rohan take alone?
- 40.Arjun works three times as fast as Meera. Together they finish a job in 4 days. How many days would Meera take alone?
Answer key
- 18
- 26/133
- 7/48
- 26
- 9
- 23/60
- 44/15
- 12
- 5/2
- 66/17
- 18
- 12
- 15
- 31/120
- 8
- 20/3
- 12/5
- 90/11
- 144/25
- 22
- 90
- 80/9
- 20
- 221/30
- 12
- 44
- 30
- 24/7
- 4
- 17/70
- 8
- 27
- 4
- 18
- 140/27
- 48
- 30
- 18/11
- 8
- 16
Free quantitative aptitude lessons, practice and worksheets at talentjr.in/quantitative-aptitude