Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Kavya and Rohan together finish a job in 2 days. Kavya alone takes 6 days. How many days would Rohan take alone?
- 2.Dev and Pooja together finish a job in 2 days. Dev alone takes 6 days. How many days would Pooja take alone?
- 3.Priya can finish a job in 21 days and Aarav in 18 days. Priya works alone for 14 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 4.Saanvi can finish a job in 8 days and Karan in 20 days. Saanvi works alone for 4 days and then stops. Karan finishes the rest. How many days does Karan take?
- 5.Rahul can finish a job in 6 days and Aarav in 18 days. Rahul works alone for 5 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 6.Aarav can finish a job in 3 days and Sneha in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Arjun works twice as fast as Zoya. Together they finish a job in 2 days. How many days would Zoya take alone?
- 8.Ishaan works three times as fast as Farhan. Together they finish a job in 10 days. How many days would Farhan take alone?
- 9.Aarav can finish a job in 6 days and Kavya in 30 days. Aarav works alone for 4 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 10.Aarav works three times as fast as Priya. Together they finish a job in 3 days. How many days would Priya take alone?
- 11.Kavya can finish a job in 14 days and Rahul in 28 days. Kavya works alone for 6 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 12.Aarav can finish a job in 16 days and Aditya in 4 days. Aarav works alone for 12 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 13.Aditya and Meera together finish a job in 4 days. Aditya alone takes 20 days. How many days would Meera take alone?
- 14.Ishaan can finish a job in 10 days and Rahul in 5 days. Ishaan works alone for 4 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 15.Saanvi can finish a job in 6 days and Meera in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Kavya and Meera together finish a job in 14 days. Kavya alone takes 21 days. How many days would Meera take alone?
- 17.Farhan can finish a job in 16 days and Saanvi in 20 days. What fraction of the job do they finish if they work together for 1 day? =
- 18.Tara can finish a job in 12 days and Sneha in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Farhan can finish a job in 15 days and Sneha in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 20.Arjun can finish a job in 22 days and Zoya in 11 days. Arjun works alone for 8 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 21.Dev can finish a job in 18 days and Zoya in 4 days. What fraction of the job do they finish if they work together for 1 day? =
- 22.Rahul can finish a job in 5 days and Priya in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Ishaan works three times as fast as Tara. Together they finish a job in 5 days. How many days would Tara take alone?
- 24.Karan can finish a job in 30 days and Priya in 12 days. Karan works alone for 5 days and then stops. Priya finishes the rest. How many days does Priya take?
- 25.Pooja can finish a job in 6 days and Meera in 26 days. Pooja works alone for 3 days and then stops. Meera finishes the rest. How many days does Meera take?
- 26.Priya can finish a job in 12 days and Isha in 8 days. Priya works alone for 3 days and then stops. Isha finishes the rest. How many days does Isha take?
- 27.Diya works twice as fast as Meera. Together they finish a job in 2 days. How many days would Meera take alone?
- 28.Pooja can finish a job in 24 days and Arjun in 20 days. Pooja works alone for 18 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 29.Farhan and Meera together finish a job in 3 days. Farhan alone takes 4 days. How many days would Meera take alone?
- 30.Tara can finish a job in 8 days and Diya in 16 days. Tara works alone for 7 days and then stops. Diya finishes the rest. How many days does Diya take?
- 31.Aditya can finish a job in 6 days and Tara in 30 days. Aditya works alone for 5 days and then stops. Tara finishes the rest. How many days does Tara take?
- 32.Diya works three times as fast as Isha. Together they finish a job in 4 days. How many days would Isha take alone?
- 33.Isha works twice as fast as Ananya. Together they finish a job in 11 days. How many days would Ananya take alone?
- 34.Tara works three times as fast as Karan. Together they finish a job in 12 days. How many days would Karan take alone?
- 35.Arjun can finish a job in 4 days and Nisha in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Farhan can finish a job in 2 days and Pooja in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 37.Kabir can finish a job in 7 days and Rohan in 17 days. What fraction of the job do they finish if they work together for 2 days? =
- 38.Arjun can finish a job in 4 days and Pooja in 6 days. Arjun works alone for 2 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 39.Nisha can finish a job in 11 days and Farhan in 6 days. What fraction of the job do they finish if they work together for 1 day? =
- 40.Aarav works three times as fast as Ishaan. Together they finish a job in 7 days. How many days would Ishaan take alone?
Answer key
- 3
- 3
- 6
- 10
- 3
- 18/7
- 6
- 40
- 10
- 12
- 16
- 1
- 5
- 3
- 114/25
- 42
- 9/80
- 4
- 210/29
- 7
- 11/36
- 30/11
- 20
- 10
- 13
- 6
- 6
- 5
- 12
- 2
- 5
- 16
- 33
- 48
- 36/11
- 4/3
- 48/119
- 3
- 17/66
- 28