Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Aarav and Saanvi together finish a job in 9 days. Aarav alone takes 12 days. How many days would Saanvi take alone?
- 2.Farhan can finish a job in 16 days and Arjun in 5 days. What fraction of the job do they finish if they work together for 3 days? =
- 3.Farhan can finish a job in 15 days and Nisha in 8 days. What fraction of the job do they finish if they work together for 2 days? =
- 4.Pooja works twice as fast as Arjun. Together they finish a job in 12 days. How many days would Arjun take alone?
- 5.Isha works three times as fast as Kabir. Together they finish a job in 9 days. How many days would Kabir take alone?
- 6.Priya can finish a job in 4 days and Aarav in 8 days. Priya works alone for 2 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 7.Isha can finish a job in 16 days and Zoya in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Meera works three times as fast as Dev. Together they finish a job in 9 days. How many days would Dev take alone?
- 9.Nisha can finish a job in 13 days and Farhan in 10 days. What fraction of the job do they finish if they work together for 3 days? =
- 10.Nisha works twice as fast as Karan. Together they finish a job in 11 days. How many days would Karan take alone?
- 11.Manav works twice as fast as Arjun. Together they finish a job in 9 days. How many days would Arjun take alone?
- 12.Diya can finish a job in 4 days and Arjun in 26 days. Diya works alone for 2 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 13.Kavya can finish a job in 15 days and Karan in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Nisha works three times as fast as Kavya. Together they finish a job in 4 days. How many days would Kavya take alone?
- 15.Pooja and Kabir together finish a job in 3 days. Pooja alone takes 4 days. How many days would Kabir take alone?
- 16.Pooja can finish a job in 13 days and Vivaan in 11 days. What fraction of the job do they finish if they work together for 1 day? =
- 17.Nisha can finish a job in 6 days and Meera in 9 days. What fraction of the job do they finish if they work together for 1 day? =
- 18.Rahul and Vivaan together finish a job in 3 days. Rahul alone takes 4 days. How many days would Vivaan take alone?
- 19.Ishaan works twice as fast as Pooja. Together they finish a job in 5 days. How many days would Pooja take alone?
- 20.Aarav can finish a job in 8 days and Aditya in 10 days. Aarav works alone for 4 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 21.Meera can finish a job in 10 days and Aditya in 6 days. Meera works alone for 5 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 22.Nisha can finish a job in 16 days and Diya in 14 days. Nisha works alone for 8 days and then stops. Diya finishes the rest. How many days does Diya take?
- 23.Ananya can finish a job in 5 days and Zoya in 20 days. Ananya works alone for 4 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 24.Aditya can finish a job in 5 days and Isha in 10 days. Aditya works alone for 2 days and then stops. Isha finishes the rest. How many days does Isha take?
- 25.Arjun can finish a job in 12 days and Nisha in 4 days. Arjun works alone for 3 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 26.Kabir works twice as fast as Rohan. Together they finish a job in 5 days. How many days would Rohan take alone?
- 27.Ishaan and Arjun together finish a job in 2 days. Ishaan alone takes 3 days. How many days would Arjun take alone?
- 28.Aditya can finish a job in 19 days and Pooja in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Ananya works twice as fast as Kavya. Together they finish a job in 7 days. How many days would Kavya take alone?
- 30.Ishaan and Aarav together finish a job in 10 days. Ishaan alone takes 14 days. How many days would Aarav take alone?
- 31.Rahul works three times as fast as Kavya. Together they finish a job in 3 days. How many days would Kavya take alone?
- 32.Vivaan can finish a job in 6 days and Dev in 20 days. What fraction of the job do they finish if they work together for 2 days? =
- 33.Aarav can finish a job in 12 days and Kavya in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Aditya can finish a job in 4 days and Tara in 12 days. Aditya works alone for 2 days and then stops. Tara finishes the rest. How many days does Tara take?
- 35.Priya can finish a job in 16 days and Zoya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Rohan and Rahul together finish a job in 8 days. Rohan alone takes 9 days. How many days would Rahul take alone?
- 37.Diya and Zoya together finish a job in 4 days. Diya alone takes 8 days. How many days would Zoya take alone?
- 38.Isha works three times as fast as Nisha. Together they finish a job in 7 days. How many days would Nisha take alone?
- 39.Dev can finish a job in 13 days and Pooja in 11 days. What fraction of the job do they finish if they work together for 3 days? =
- 40.Kavya works twice as fast as Aarav. Together they finish a job in 7 days. How many days would Aarav take alone?
Answer key
- 36
- 63/80
- 23/60
- 36
- 36
- 4
- 16/9
- 36
- 69/130
- 33
- 27
- 13
- 20/3
- 16
- 12
- 24/143
- 5/18
- 12
- 15
- 5
- 3
- 7
- 4
- 6
- 3
- 15
- 6
- 266/33
- 21
- 35
- 12
- 13/30
- 36/7
- 6
- 144/17
- 72
- 8
- 28
- 72/143
- 21