Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Arjun can finish a job in 14 days and Karan in 7 days. Arjun works alone for 6 days and then stops. Karan finishes the rest. How many days does Karan take?
- 2.Tara can finish a job in 12 days and Dev in 8 days. What fraction of the job do they finish if they work together for 3 days? =
- 3.Pooja and Aarav together finish a job in 2 days. Pooja alone takes 4 days. How many days would Aarav take alone?
- 4.Farhan can finish a job in 7 days and Meera in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 5.Zoya can finish a job in 4 days and Kavya in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Nisha can finish a job in 2 days and Arjun in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Sneha can finish a job in 26 days and Arjun in 13 days. Sneha works alone for 22 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 8.Rahul can finish a job in 2 days and Zoya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 9.Kabir and Tara together finish a job in 2 days. Kabir alone takes 6 days. How many days would Tara take alone?
- 10.Tara works three times as fast as Aditya. Together they finish a job in 4 days. How many days would Aditya take alone?
- 11.Ishaan can finish a job in 17 days and Rahul in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Farhan works twice as fast as Meera. Together they finish a job in 3 days. How many days would Meera take alone?
- 13.Nisha works three times as fast as Priya. Together they finish a job in 3 days. How many days would Priya take alone?
- 14.Arjun and Manav together finish a job in 2 days. Arjun alone takes 6 days. How many days would Manav take alone?
- 15.Tara can finish a job in 15 days and Ananya in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Zoya and Kabir together finish a job in 5 days. Zoya alone takes 6 days. How many days would Kabir take alone?
- 17.Nisha can finish a job in 10 days and Diya in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 18.Vivaan can finish a job in 16 days and Isha in 18 days. What fraction of the job do they finish if they work together for 1 day? =
- 19.Aarav can finish a job in 11 days and Kabir in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 20.Rahul can finish a job in 17 days and Karan in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Saanvi can finish a job in 3 days and Arjun in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Aditya works twice as fast as Tara. Together they finish a job in 12 days. How many days would Tara take alone?
- 23.Sneha can finish a job in 7 days and Saanvi in 21 days. Sneha works alone for 2 days and then stops. Saanvi finishes the rest. How many days does Saanvi take?
- 24.Aarav and Ananya together finish a job in 2 days. Aarav alone takes 4 days. How many days would Ananya take alone?
- 25.Tara can finish a job in 15 days and Zoya in 19 days. What fraction of the job do they finish if they work together for 1 day? =
- 26.Aditya can finish a job in 6 days and Kabir in 12 days. Aditya works alone for 2 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 27.Farhan works three times as fast as Priya. Together they finish a job in 8 days. How many days would Priya take alone?
- 28.Priya and Isha together finish a job in 16 days. Priya alone takes 20 days. How many days would Isha take alone?
- 29.Dev can finish a job in 14 days and Aarav in 6 days. What fraction of the job do they finish if they work together for 1 day? =
- 30.Ananya can finish a job in 15 days and Nisha in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Ananya works three times as fast as Saanvi. Together they finish a job in 10 days. How many days would Saanvi take alone?
- 32.Aditya can finish a job in 4 days and Dev in 16 days. Aditya works alone for 1 day and then stops. Dev finishes the rest. How many days does Dev take?
- 33.Karan can finish a job in 15 days and Pooja in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Aarav can finish a job in 16 days and Manav in 8 days. What fraction of the job do they finish if they work together for 3 days? =
- 35.Sneha can finish a job in 18 days and Kabir in 9 days. What fraction of the job do they finish if they work together for 3 days? =
- 36.Manav can finish a job in 12 days and Sneha in 24 days. Manav works alone for 6 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 37.Nisha can finish a job in 12 days and Farhan in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Ananya can finish a job in 8 days and Vivaan in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Aarav can finish a job in 9 days and Ishaan in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 40.Saanvi can finish a job in 28 days and Ishaan in 12 days. Saanvi works alone for 21 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
Answer key
- 4
- 5/8
- 4
- 60/91
- 12/5
- 26/15
- 2
- 6/5
- 3
- 16
- 204/29
- 9
- 12
- 3
- 105/22
- 30
- 12/35
- 17/144
- 209/30
- 51/20
- 51/20
- 36
- 15
- 4
- 34/285
- 8
- 32
- 80
- 5/21
- 30/17
- 40
- 12
- 285/34
- 9/16
- 1/2
- 12
- 36/5
- 24/7
- 22/39
- 3