Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Sneha can finish a job in 6 days and Tara in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Karan works twice as fast as Rohan. Together they finish a job in 10 days. How many days would Rohan take alone?
- 3.Meera and Diya together finish a job in 2 days. Meera alone takes 4 days. How many days would Diya take alone?
- 4.Pooja and Rohan together finish a job in 8 days. Pooja alone takes 9 days. How many days would Rohan take alone?
- 5.Arjun can finish a job in 9 days and Ananya in 10 days. What fraction of the job do they finish if they work together for 2 days? =
- 6.Kabir can finish a job in 13 days and Zoya in 26 days. Kabir works alone for 11 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 7.Isha can finish a job in 20 days and Rohan in 5 days. Isha works alone for 4 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 8.Rohan and Sneha together finish a job in 4 days. Rohan alone takes 6 days. How many days would Sneha take alone?
- 9.Kabir can finish a job in 4 days and Nisha in 15 days. What fraction of the job do they finish if they work together for 1 day? =
- 10.Vivaan works twice as fast as Ishaan. Together they finish a job in 7 days. How many days would Ishaan take alone?
- 11.Ananya can finish a job in 15 days and Zoya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Karan and Zoya together finish a job in 2 days. Karan alone takes 4 days. How many days would Zoya take alone?
- 13.Aditya and Sneha together finish a job in 6 days. Aditya alone takes 9 days. How many days would Sneha take alone?
- 14.Manav can finish a job in 9 days and Ananya in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Arjun works three times as fast as Manav. Together they finish a job in 7 days. How many days would Manav take alone?
- 16.Rahul works three times as fast as Rohan. Together they finish a job in 3 days. How many days would Rohan take alone?
- 17.Rohan can finish a job in 22 days and Karan in 11 days. Rohan works alone for 14 days and then stops. Karan finishes the rest. How many days does Karan take?
- 18.Kabir can finish a job in 14 days and Arjun in 6 days. Kabir works alone for 7 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 19.Kabir and Karan together finish a job in 2 days. Kabir alone takes 3 days. How many days would Karan take alone?
- 20.Farhan and Sneha together finish a job in 4 days. Farhan alone takes 12 days. How many days would Sneha take alone?
- 21.Ishaan can finish a job in 16 days and Dev in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Zoya can finish a job in 10 days and Rohan in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Isha can finish a job in 20 days and Farhan in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 24.Rohan can finish a job in 9 days and Tara in 27 days. Rohan works alone for 4 days and then stops. Tara finishes the rest. How many days does Tara take?
- 25.Tara can finish a job in 4 days and Kabir in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 26.Ananya can finish a job in 4 days and Aarav in 30 days. Ananya works alone for 2 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 27.Diya works twice as fast as Kavya. Together they finish a job in 4 days. How many days would Kavya take alone?
- 28.Arjun can finish a job in 5 days and Rahul in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Aditya can finish a job in 4 days and Karan in 24 days. Aditya works alone for 1 day and then stops. Karan finishes the rest. How many days does Karan take?
- 30.Rahul works twice as fast as Manav. Together they finish a job in 8 days. How many days would Manav take alone?
- 31.Saanvi works three times as fast as Kabir. Together they finish a job in 12 days. How many days would Kabir take alone?
- 32.Zoya can finish a job in 5 days and Meera in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Dev can finish a job in 7 days and Isha in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Zoya can finish a job in 8 days and Manav in 16 days. Zoya works alone for 6 days and then stops. Manav finishes the rest. How many days does Manav take?
- 35.Sneha works twice as fast as Saanvi. Together they finish a job in 5 days. How many days would Saanvi take alone?
- 36.Diya can finish a job in 20 days and Pooja in 9 days. What fraction of the job do they finish if they work together for 1 day? =
- 37.Arjun can finish a job in 9 days and Dev in 18 days. Arjun works alone for 2 days and then stops. Dev finishes the rest. How many days does Dev take?
- 38.Diya works three times as fast as Rohan. Together they finish a job in 9 days. How many days would Rohan take alone?
- 39.Priya can finish a job in 9 days and Zoya in 5 days. What fraction of the job do they finish if they work together for 2 days? =
- 40.Dev can finish a job in 18 days and Farhan in 20 days. What fraction of the job do they finish if they work together for 1 day? =
Answer key
- 66/17
- 30
- 4
- 72
- 19/45
- 4
- 4
- 12
- 19/60
- 21
- 5/2
- 4
- 18
- 36/13
- 28
- 12
- 4
- 3
- 6
- 6
- 80/9
- 20/3
- 140/27
- 15
- 9/20
- 15
- 12
- 90/23
- 18
- 24
- 48
- 80/21
- 63/16
- 4
- 15
- 29/180
- 14
- 36
- 28/45
- 19/180