Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Arjun works twice as fast as Tara. Together they finish a job in 6 days. How many days would Tara take alone?
- 2.Zoya works three times as fast as Kabir. Together they finish a job in 10 days. How many days would Kabir take alone?
- 3.Farhan can finish a job in 13 days and Aditya in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Vivaan works twice as fast as Priya. Together they finish a job in 11 days. How many days would Priya take alone?
- 5.Dev can finish a job in 10 days and Saanvi in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Manav and Rohan together finish a job in 3 days. Manav alone takes 6 days. How many days would Rohan take alone?
- 7.Dev works twice as fast as Ananya. Together they finish a job in 6 days. How many days would Ananya take alone?
- 8.Meera can finish a job in 16 days and Nisha in 15 days. What fraction of the job do they finish if they work together for 1 day? =
- 9.Tara can finish a job in 5 days and Diya in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Karan works twice as fast as Nisha. Together they finish a job in 10 days. How many days would Nisha take alone?
- 11.Ananya and Nisha together finish a job in 4 days. Ananya alone takes 5 days. How many days would Nisha take alone?
- 12.Priya can finish a job in 15 days and Vivaan in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Zoya can finish a job in 27 days and Rahul in 9 days. Zoya works alone for 21 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 14.Nisha works twice as fast as Zoya. Together they finish a job in 12 days. How many days would Zoya take alone?
- 15.Aarav and Sneha together finish a job in 2 days. Aarav alone takes 4 days. How many days would Sneha take alone?
- 16.Ishaan can finish a job in 7 days and Aditya in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Zoya and Karan together finish a job in 2 days. Zoya alone takes 3 days. How many days would Karan take alone?
- 18.Aditya can finish a job in 18 days and Priya in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Rohan can finish a job in 12 days and Saanvi in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 20.Isha can finish a job in 14 days and Vivaan in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 21.Meera works three times as fast as Vivaan. Together they finish a job in 8 days. How many days would Vivaan take alone?
- 22.Rohan can finish a job in 16 days and Arjun in 8 days. Rohan works alone for 4 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 23.Nisha can finish a job in 14 days and Manav in 9 days. What fraction of the job do they finish if they work together for 2 days? =
- 24.Ishaan can finish a job in 4 days and Rahul in 14 days. Ishaan works alone for 2 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 25.Saanvi can finish a job in 13 days and Kavya in 19 days. What fraction of the job do they finish if they work together for 1 day? =
- 26.Pooja can finish a job in 6 days and Dev in 9 days. Pooja works alone for 4 days and then stops. Dev finishes the rest. How many days does Dev take?
- 27.Rohan can finish a job in 4 days and Diya in 10 days. Rohan works alone for 2 days and then stops. Diya finishes the rest. How many days does Diya take?
- 28.Karan can finish a job in 6 days and Aditya in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Ishaan works twice as fast as Saanvi. Together they finish a job in 3 days. How many days would Saanvi take alone?
- 30.Rohan can finish a job in 15 days and Rahul in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Isha can finish a job in 12 days and Kabir in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Isha can finish a job in 5 days and Meera in 30 days. Isha works alone for 3 days and then stops. Meera finishes the rest. How many days does Meera take?
- 33.Diya can finish a job in 13 days and Aarav in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Kabir can finish a job in 13 days and Farhan in 8 days. What fraction of the job do they finish if they work together for 3 days? =
- 35.Isha can finish a job in 15 days and Diya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Kavya and Dev together finish a job in 2 days. Kavya alone takes 3 days. How many days would Dev take alone?
- 37.Rohan can finish a job in 19 days and Kabir in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Isha can finish a job in 10 days and Pooja in 20 days. Isha works alone for 7 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 39.Kavya can finish a job in 6 days and Arjun in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Diya can finish a job in 12 days and Farhan in 4 days. What fraction of the job do they finish if they work together for 1 day? =
Answer key
- 18
- 40
- 208/29
- 33
- 6
- 6
- 18
- 31/240
- 4
- 30
- 20
- 285/34
- 2
- 36
- 4
- 14/9
- 6
- 198/29
- 60/11
- 81/182
- 32
- 6
- 23/63
- 7
- 32/247
- 3
- 5
- 30/7
- 9
- 90/11
- 60/17
- 12
- 182/27
- 63/104
- 5/2
- 6
- 323/36
- 6
- 4
- 1/3
Free quantitative aptitude lessons, practice and worksheets at talentjr.in/quantitative-aptitude