Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Manav can finish a job in 13 days and Kabir in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Kabir can finish a job in 8 days and Rahul in 9 days. What fraction of the job do they finish if they work together for 2 days? =
- 3.Rahul can finish a job in 17 days and Aditya in 18 days. What fraction of the job do they finish if they work together for 3 days? =
- 4.Rohan can finish a job in 16 days and Aditya in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Vivaan can finish a job in 15 days and Kavya in 20 days. Vivaan works alone for 3 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 6.Manav and Ananya together finish a job in 14 days. Manav alone takes 28 days. How many days would Ananya take alone?
- 7.Kabir and Priya together finish a job in 2 days. Kabir alone takes 3 days. How many days would Priya take alone?
- 8.Aditya works twice as fast as Meera. Together they finish a job in 11 days. How many days would Meera take alone?
- 9.Isha works three times as fast as Zoya. Together they finish a job in 11 days. How many days would Zoya take alone?
- 10.Sneha works twice as fast as Isha. Together they finish a job in 4 days. How many days would Isha take alone?
- 11.Karan works twice as fast as Priya. Together they finish a job in 10 days. How many days would Priya take alone?
- 12.Kabir can finish a job in 9 days and Ananya in 6 days. Kabir works alone for 3 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 13.Rohan can finish a job in 19 days and Farhan in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 14.Kabir can finish a job in 15 days and Kavya in 25 days. Kabir works alone for 6 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 15.Nisha works twice as fast as Sneha. Together they finish a job in 5 days. How many days would Sneha take alone?
- 16.Dev can finish a job in 7 days and Diya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Dev and Diya together finish a job in 4 days. Dev alone takes 8 days. How many days would Diya take alone?
- 18.Vivaan can finish a job in 9 days and Ishaan in 27 days. Vivaan works alone for 6 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 19.Aditya works twice as fast as Saanvi. Together they finish a job in 4 days. How many days would Saanvi take alone?
- 20.Pooja works three times as fast as Nisha. Together they finish a job in 3 days. How many days would Nisha take alone?
- 21.Rohan works twice as fast as Pooja. Together they finish a job in 10 days. How many days would Pooja take alone?
- 22.Farhan can finish a job in 17 days and Kavya in 7 days. What fraction of the job do they finish if they work together for 1 day? =
- 23.Rohan can finish a job in 10 days and Tara in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 24.Arjun can finish a job in 18 days and Aditya in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Farhan can finish a job in 20 days and Pooja in 7 days. What fraction of the job do they finish if they work together for 2 days? =
- 26.Karan works twice as fast as Arjun. Together they finish a job in 3 days. How many days would Arjun take alone?
- 27.Isha can finish a job in 12 days and Zoya in 21 days. Isha works alone for 4 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 28.Isha can finish a job in 14 days and Priya in 22 days. Isha works alone for 7 days and then stops. Priya finishes the rest. How many days does Priya take?
- 29.Nisha can finish a job in 16 days and Kabir in 11 days. What fraction of the job do they finish if they work together for 1 day? =
- 30.Arjun and Dev together finish a job in 5 days. Arjun alone takes 6 days. How many days would Dev take alone?
- 31.Aarav can finish a job in 8 days and Aditya in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 32.Priya works three times as fast as Nisha. Together they finish a job in 4 days. How many days would Nisha take alone?
- 33.Dev can finish a job in 8 days and Tara in 28 days. Dev works alone for 4 days and then stops. Tara finishes the rest. How many days does Tara take?
- 34.Arjun can finish a job in 6 days and Tara in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Isha and Manav together finish a job in 3 days. Isha alone takes 12 days. How many days would Manav take alone?
- 36.Arjun can finish a job in 14 days and Ishaan in 21 days. Arjun works alone for 10 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 37.Vivaan and Meera together finish a job in 10 days. Vivaan alone takes 15 days. How many days would Meera take alone?
- 38.Arjun works three times as fast as Sneha. Together they finish a job in 3 days. How many days would Sneha take alone?
- 39.Meera can finish a job in 16 days and Isha in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Dev works three times as fast as Karan. Together they finish a job in 12 days. How many days would Karan take alone?
Answer key
- 208/29
- 17/36
- 35/102
- 272/33
- 16
- 28
- 6
- 33
- 44
- 12
- 30
- 4
- 96/247
- 15
- 15
- 21/10
- 8
- 9
- 12
- 12
- 30
- 24/119
- 70/17
- 198/29
- 27/70
- 9
- 14
- 11
- 27/176
- 30
- 13/36
- 16
- 14
- 12/5
- 4
- 6
- 30
- 12
- 304/35
- 48