Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Arjun can finish a job in 4 days and Meera in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Meera works twice as fast as Rohan. Together they finish a job in 10 days. How many days would Rohan take alone?
- 3.Saanvi can finish a job in 19 days and Kavya in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Manav can finish a job in 4 days and Dev in 16 days. Manav works alone for 1 day and then stops. Dev finishes the rest. How many days does Dev take?
- 5.Diya can finish a job in 6 days and Tara in 21 days. Diya works alone for 2 days and then stops. Tara finishes the rest. How many days does Tara take?
- 6.Zoya can finish a job in 19 days and Diya in 20 days. What fraction of the job do they finish if they work together for 1 day? =
- 7.Sneha can finish a job in 17 days and Kavya in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 8.Sneha and Dev together finish a job in 3 days. Sneha alone takes 6 days. How many days would Dev take alone?
- 9.Kavya works three times as fast as Ishaan. Together they finish a job in 11 days. How many days would Ishaan take alone?
- 10.Zoya can finish a job in 5 days and Arjun in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Farhan and Zoya together finish a job in 2 days. Farhan alone takes 3 days. How many days would Zoya take alone?
- 12.Arjun can finish a job in 4 days and Dev in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Saanvi works three times as fast as Vivaan. Together they finish a job in 7 days. How many days would Vivaan take alone?
- 14.Zoya can finish a job in 20 days and Rohan in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Ananya can finish a job in 18 days and Rohan in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Farhan and Pooja together finish a job in 21 days. Farhan alone takes 30 days. How many days would Pooja take alone?
- 17.Zoya can finish a job in 16 days and Rohan in 24 days. Zoya works alone for 10 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 18.Kabir can finish a job in 15 days and Meera in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Kabir works twice as fast as Vivaan. Together they finish a job in 10 days. How many days would Vivaan take alone?
- 20.Vivaan and Isha together finish a job in 2 days. Vivaan alone takes 6 days. How many days would Isha take alone?
- 21.Meera and Kavya together finish a job in 4 days. Meera alone takes 20 days. How many days would Kavya take alone?
- 22.Pooja can finish a job in 30 days and Manav in 4 days. Pooja works alone for 15 days and then stops. Manav finishes the rest. How many days does Manav take?
- 23.Rahul works twice as fast as Pooja. Together they finish a job in 12 days. How many days would Pooja take alone?
- 24.Priya can finish a job in 19 days and Manav in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Rohan can finish a job in 7 days and Vivaan in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 26.Nisha can finish a job in 30 days and Karan in 15 days. Nisha works alone for 28 days and then stops. Karan finishes the rest. How many days does Karan take?
- 27.Dev and Aarav together finish a job in 2 days. Dev alone takes 3 days. How many days would Aarav take alone?
- 28.Pooja can finish a job in 7 days and Nisha in 14 days. What fraction of the job do they finish if they work together for 1 day? =
- 29.Rahul can finish a job in 8 days and Vivaan in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 30.Farhan works three times as fast as Aditya. Together they finish a job in 11 days. How many days would Aditya take alone?
- 31.Pooja and Arjun together finish a job in 4 days. Pooja alone takes 5 days. How many days would Arjun take alone?
- 32.Diya can finish a job in 15 days and Ishaan in 12 days. What fraction of the job do they finish if they work together for 1 day? =
- 33.Kabir and Arjun together finish a job in 7 days. Kabir alone takes 8 days. How many days would Arjun take alone?
- 34.Kavya can finish a job in 7 days and Isha in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Aarav can finish a job in 6 days and Nisha in 24 days. Aarav works alone for 4 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 36.Zoya can finish a job in 14 days and Diya in 7 days. What fraction of the job do they finish if they work together for 1 day? =
- 37.Kavya can finish a job in 12 days and Ananya in 24 days. Kavya works alone for 9 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 38.Tara can finish a job in 5 days and Priya in 4 days. What fraction of the job do they finish if they work together for 1 day? =
- 39.Karan can finish a job in 6 days and Sneha in 30 days. Karan works alone for 1 day and then stops. Sneha finishes the rest. How many days does Sneha take?
- 40.Isha can finish a job in 12 days and Pooja in 14 days. Isha works alone for 6 days and then stops. Pooja finishes the rest. How many days does Pooja take?
Answer key
- 36/11
- 30
- 95/24
- 12
- 14
- 39/380
- 204/29
- 6
- 44
- 90/23
- 6
- 52/17
- 28
- 140/27
- 9/5
- 70
- 9
- 255/32
- 30
- 3
- 5
- 2
- 36
- 247/32
- 91/20
- 1
- 6
- 3/14
- 136/25
- 44
- 20
- 3/20
- 56
- 35/12
- 8
- 3/14
- 6
- 9/20
- 25
- 7