Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Isha works three times as fast as Arjun. Together they finish a job in 3 days. How many days would Arjun take alone?
- 2.Rohan can finish a job in 8 days and Kavya in 24 days. Rohan works alone for 1 day and then stops. Kavya finishes the rest. How many days does Kavya take?
- 3.Diya can finish a job in 14 days and Saanvi in 20 days. What fraction of the job do they finish if they work together for 1 day? =
- 4.Aarav and Saanvi together finish a job in 5 days. Aarav alone takes 10 days. How many days would Saanvi take alone?
- 5.Dev and Pooja together finish a job in 5 days. Dev alone takes 10 days. How many days would Pooja take alone?
- 6.Tara can finish a job in 18 days and Priya in 5 days. What fraction of the job do they finish if they work together for 3 days? =
- 7.Pooja works three times as fast as Rahul. Together they finish a job in 10 days. How many days would Rahul take alone?
- 8.Diya can finish a job in 4 days and Nisha in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 9.Manav can finish a job in 7 days and Priya in 9 days. What fraction of the job do they finish if they work together for 1 day? =
- 10.Aarav can finish a job in 12 days and Isha in 28 days. Aarav works alone for 6 days and then stops. Isha finishes the rest. How many days does Isha take?
- 11.Sneha can finish a job in 2 days and Zoya in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Rohan can finish a job in 10 days and Ishaan in 9 days. What fraction of the job do they finish if they work together for 1 day? =
- 13.Sneha can finish a job in 15 days and Arjun in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Isha can finish a job in 5 days and Saanvi in 11 days. What fraction of the job do they finish if they work together for 3 days? =
- 15.Manav can finish a job in 14 days and Saanvi in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Aarav works twice as fast as Saanvi. Together they finish a job in 6 days. How many days would Saanvi take alone?
- 17.Vivaan and Ishaan together finish a job in 10 days. Vivaan alone takes 15 days. How many days would Ishaan take alone?
- 18.Ananya can finish a job in 16 days and Priya in 19 days. What fraction of the job do they finish if they work together for 1 day? =
- 19.Vivaan can finish a job in 6 days and Rahul in 27 days. Vivaan works alone for 2 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 20.Sneha can finish a job in 12 days and Zoya in 7 days. What fraction of the job do they finish if they work together for 1 day? =
- 21.Kabir can finish a job in 4 days and Diya in 24 days. Kabir works alone for 2 days and then stops. Diya finishes the rest. How many days does Diya take?
- 22.Isha can finish a job in 15 days and Aditya in 6 days. What fraction of the job do they finish if they work together for 1 day? =
- 23.Sneha and Tara together finish a job in 4 days. Sneha alone takes 6 days. How many days would Tara take alone?
- 24.Ishaan and Nisha together finish a job in 10 days. Ishaan alone takes 14 days. How many days would Nisha take alone?
- 25.Diya can finish a job in 7 days and Pooja in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 26.Dev can finish a job in 2 days and Manav in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Ananya can finish a job in 4 days and Kabir in 8 days. Ananya works alone for 2 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 28.Sneha can finish a job in 7 days and Aditya in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 29.Karan and Ananya together finish a job in 6 days. Karan alone takes 24 days. How many days would Ananya take alone?
- 30.Aarav and Kabir together finish a job in 2 days. Aarav alone takes 3 days. How many days would Kabir take alone?
- 31.Ananya can finish a job in 5 days and Karan in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Aarav can finish a job in 6 days and Isha in 22 days. Aarav works alone for 3 days and then stops. Isha finishes the rest. How many days does Isha take?
- 33.Diya and Saanvi together finish a job in 2 days. Diya alone takes 6 days. How many days would Saanvi take alone?
- 34.Kabir can finish a job in 7 days and Isha in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Aarav can finish a job in 18 days and Saanvi in 9 days. Aarav works alone for 16 days and then stops. Saanvi finishes the rest. How many days does Saanvi take?
- 36.Manav works three times as fast as Pooja. Together they finish a job in 9 days. How many days would Pooja take alone?
- 37.Vivaan and Rahul together finish a job in 2 days. Vivaan alone takes 6 days. How many days would Rahul take alone?
- 38.Manav can finish a job in 10 days and Aditya in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 39.Meera can finish a job in 20 days and Farhan in 15 days. What fraction of the job do they finish if they work together for 3 days? =
- 40.Tara works three times as fast as Ishaan. Together they finish a job in 3 days. How many days would Ishaan take alone?
Answer key
- 12
- 21
- 17/140
- 10
- 10
- 23/30
- 40
- 44/15
- 16/63
- 14
- 14/9
- 19/90
- 45/8
- 48/55
- 126/23
- 18
- 30
- 35/304
- 18
- 19/84
- 12
- 7/30
- 12
- 35
- 63/16
- 12/7
- 4
- 25/63
- 8
- 6
- 65/18
- 11
- 3
- 28/11
- 1
- 36
- 3
- 14/45
- 7/20
- 12