Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Pooja works three times as fast as Aditya. Together they finish a job in 12 days. How many days would Aditya take alone?
- 2.Manav can finish a job in 8 days and Saanvi in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 3.Manav can finish a job in 15 days and Meera in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Aarav and Tara together finish a job in 2 days. Aarav alone takes 6 days. How many days would Tara take alone?
- 5.Aarav works twice as fast as Farhan. Together they finish a job in 4 days. How many days would Farhan take alone?
- 6.Meera works three times as fast as Ananya. Together they finish a job in 6 days. How many days would Ananya take alone?
- 7.Arjun works twice as fast as Karan. Together they finish a job in 2 days. How many days would Karan take alone?
- 8.Meera works twice as fast as Isha. Together they finish a job in 5 days. How many days would Isha take alone?
- 9.Kabir works twice as fast as Zoya. Together they finish a job in 7 days. How many days would Zoya take alone?
- 10.Ananya and Ishaan together finish a job in 2 days. Ananya alone takes 3 days. How many days would Ishaan take alone?
- 11.Kavya works three times as fast as Manav. Together they finish a job in 10 days. How many days would Manav take alone?
- 12.Kabir can finish a job in 19 days and Vivaan in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Zoya can finish a job in 19 days and Dev in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Priya can finish a job in 17 days and Pooja in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Karan works three times as fast as Arjun. Together they finish a job in 5 days. How many days would Arjun take alone?
- 16.Diya can finish a job in 6 days and Sneha in 30 days. Diya works alone for 3 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 17.Sneha and Dev together finish a job in 4 days. Sneha alone takes 8 days. How many days would Dev take alone?
- 18.Arjun can finish a job in 14 days and Aarav in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Sneha can finish a job in 15 days and Ishaan in 16 days. What fraction of the job do they finish if they work together for 1 day? =
- 20.Vivaan and Priya together finish a job in 9 days. Vivaan alone takes 18 days. How many days would Priya take alone?
- 21.Isha and Manav together finish a job in 10 days. Isha alone takes 14 days. How many days would Manav take alone?
- 22.Isha can finish a job in 6 days and Manav in 7 days. What fraction of the job do they finish if they work together for 1 day? =
- 23.Pooja and Aarav together finish a job in 3 days. Pooja alone takes 4 days. How many days would Aarav take alone?
- 24.Diya can finish a job in 12 days and Rohan in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Ishaan can finish a job in 8 days and Vivaan in 28 days. Ishaan works alone for 6 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 26.Zoya can finish a job in 18 days and Vivaan in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Meera and Ananya together finish a job in 10 days. Meera alone takes 15 days. How many days would Ananya take alone?
- 28.Aarav can finish a job in 19 days and Zoya in 4 days. What fraction of the job do they finish if they work together for 2 days? =
- 29.Nisha and Arjun together finish a job in 2 days. Nisha alone takes 3 days. How many days would Arjun take alone?
- 30.Rahul can finish a job in 20 days and Diya in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Manav can finish a job in 9 days and Nisha in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Meera can finish a job in 21 days and Rohan in 15 days. Meera works alone for 14 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 33.Isha can finish a job in 6 days and Kabir in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Karan works three times as fast as Kavya. Together they finish a job in 10 days. How many days would Kavya take alone?
- 35.Dev can finish a job in 12 days and Vivaan in 5 days. What fraction of the job do they finish if they work together for 2 days? =
- 36.Pooja can finish a job in 4 days and Diya in 14 days. Pooja works alone for 2 days and then stops. Diya finishes the rest. How many days does Diya take?
- 37.Arjun can finish a job in 4 days and Dev in 5 days. What fraction of the job do they finish if they work together for 2 days? =
- 38.Rohan and Aarav together finish a job in 4 days. Rohan alone takes 5 days. How many days would Aarav take alone?
- 39.Aditya can finish a job in 7 days and Nisha in 18 days. What fraction of the job do they finish if they work together for 1 day? =
- 40.Aarav can finish a job in 16 days and Priya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
Answer key
- 48
- 9/40
- 120/23
- 3
- 12
- 24
- 6
- 15
- 21
- 6
- 40
- 342/37
- 228/31
- 119/24
- 20
- 15
- 8
- 35/6
- 31/240
- 18
- 35
- 13/42
- 12
- 36/7
- 7
- 45/7
- 30
- 23/38
- 6
- 140/27
- 36/13
- 5
- 15/4
- 40
- 17/30
- 7
- 9/10
- 20
- 25/126
- 48/19