Time and Work Worksheet

Quantitative aptitude lesson 19: Time and work · Set 70 · 40 questions
TalentJR

The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.

NameDateTime takenScore ___ / 40
  1. 1.Dev and Pooja together finish a job in 11 days. Dev alone takes 22 days. How many days would Pooja take alone?
  2. 2.Karan can finish a job in 16 days and Tara in 6 days. What fraction of the job do they finish if they work together for 1 day? =
  3. 3.Rahul works three times as fast as Karan. Together they finish a job in 6 days. How many days would Karan take alone?
  4. 4.Nisha can finish a job in 5 days and Tara in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  5. 5.Tara can finish a job in 12 days and Arjun in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  6. 6.Isha can finish a job in 12 days and Rohan in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  7. 7.Meera and Kabir together finish a job in 5 days. Meera alone takes 10 days. How many days would Kabir take alone?
  8. 8.Rohan works twice as fast as Ishaan. Together they finish a job in 2 days. How many days would Ishaan take alone?
  9. 9.Tara can finish a job in 20 days and Ishaan in 7 days. What fraction of the job do they finish if they work together for 2 days? =
  10. 10.Saanvi can finish a job in 12 days and Karan in 24 days. Saanvi works alone for 5 days and then stops. Karan finishes the rest. How many days does Karan take?
  11. 11.Nisha can finish a job in 19 days and Ishaan in 15 days. What fraction of the job do they finish if they work together for 3 days? =
  12. 12.Meera and Priya together finish a job in 4 days. Meera alone takes 20 days. How many days would Priya take alone?
  13. 13.Rohan works twice as fast as Kavya. Together they finish a job in 9 days. How many days would Kavya take alone?
  14. 14.Sneha works three times as fast as Tara. Together they finish a job in 10 days. How many days would Tara take alone?
  15. 15.Aditya can finish a job in 9 days and Ananya in 17 days. What fraction of the job do they finish if they work together for 1 day? =
  16. 16.Arjun and Saanvi together finish a job in 2 days. Arjun alone takes 4 days. How many days would Saanvi take alone?
  17. 17.Karan can finish a job in 12 days and Dev in 10 days. Karan works alone for 6 days and then stops. Dev finishes the rest. How many days does Dev take?
  18. 18.Ishaan can finish a job in 4 days and Karan in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  19. 19.Vivaan works twice as fast as Rahul. Together they finish a job in 8 days. How many days would Rahul take alone?
  20. 20.Manav can finish a job in 12 days and Sneha in 7 days. What fraction of the job do they finish if they work together for 1 day? =
  21. 21.Aditya can finish a job in 19 days and Dev in 12 days. What fraction of the job do they finish if they work together for 3 days? =
  22. 22.Pooja can finish a job in 9 days and Arjun in 5 days. What fraction of the job do they finish if they work together for 1 day? =
  23. 23.Arjun and Kabir together finish a job in 2 days. Arjun alone takes 6 days. How many days would Kabir take alone?
  24. 24.Rohan can finish a job in 5 days and Karan in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  25. 25.Karan works twice as fast as Aditya. Together they finish a job in 11 days. How many days would Aditya take alone?
  26. 26.Nisha can finish a job in 7 days and Ishaan in 21 days. Nisha works alone for 1 day and then stops. Ishaan finishes the rest. How many days does Ishaan take?
  27. 27.Arjun and Saanvi together finish a job in 4 days. Arjun alone takes 8 days. How many days would Saanvi take alone?
  28. 28.Pooja can finish a job in 15 days and Ishaan in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  29. 29.Saanvi can finish a job in 6 days and Karan in 21 days. Saanvi works alone for 4 days and then stops. Karan finishes the rest. How many days does Karan take?
  30. 30.Nisha and Karan together finish a job in 4 days. Nisha alone takes 5 days. How many days would Karan take alone?
  31. 31.Farhan can finish a job in 6 days and Rahul in 5 days. What fraction of the job do they finish if they work together for 2 days? =
  32. 32.Karan works three times as fast as Diya. Together they finish a job in 2 days. How many days would Diya take alone?
  33. 33.Tara works twice as fast as Farhan. Together they finish a job in 8 days. How many days would Farhan take alone?
  34. 34.Farhan can finish a job in 8 days and Arjun in 14 days. Farhan works alone for 4 days and then stops. Arjun finishes the rest. How many days does Arjun take?
  35. 35.Ishaan and Nisha together finish a job in 10 days. Ishaan alone takes 14 days. How many days would Nisha take alone?
  36. 36.Karan can finish a job in 10 days and Diya in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
  37. 37.Rohan works twice as fast as Zoya. Together they finish a job in 8 days. How many days would Zoya take alone?
  38. 38.Ishaan and Meera together finish a job in 2 days. Ishaan alone takes 4 days. How many days would Meera take alone?
  39. 39.Kabir can finish a job in 8 days and Aarav in 16 days. What fraction of the job do they finish if they work together for 1 day? =
  40. 40.Nisha can finish a job in 17 days and Diya in 15 days. What fraction of the job do they finish if they work together for 1 day? =

Answer key

  1. 22
  2. 11/48
  3. 24
  4. 10/3
  5. 36/5
  6. 3
  7. 10
  8. 6
  9. 27/70
  10. 14
  11. 34/95
  12. 5
  13. 27
  14. 40
  15. 26/153
  16. 4
  17. 5
  18. 36/11
  19. 24
  20. 19/84
  21. 31/76
  22. 14/45
  23. 3
  24. 45/14
  25. 33
  26. 18
  27. 8
  28. 120/23
  29. 7
  30. 20
  31. 11/15
  32. 8
  33. 24
  34. 7
  35. 35
  36. 5/3
  37. 24
  38. 4
  39. 3/16
  40. 32/255