Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Rohan can finish a job in 12 days and Ananya in 18 days. Rohan works alone for 4 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 2.Farhan works twice as fast as Zoya. Together they finish a job in 12 days. How many days would Zoya take alone?
- 3.Ananya can finish a job in 8 days and Rohan in 16 days. Ananya works alone for 1 day and then stops. Rohan finishes the rest. How many days does Rohan take?
- 4.Manav and Aarav together finish a job in 6 days. Manav alone takes 8 days. How many days would Aarav take alone?
- 5.Nisha can finish a job in 10 days and Zoya in 12 days. What fraction of the job do they finish if they work together for 3 days? =
- 6.Saanvi works twice as fast as Priya. Together they finish a job in 12 days. How many days would Priya take alone?
- 7.Tara and Nisha together finish a job in 8 days. Tara alone takes 10 days. How many days would Nisha take alone?
- 8.Farhan can finish a job in 12 days and Aarav in 18 days. Farhan works alone for 2 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 9.Isha can finish a job in 4 days and Meera in 12 days. Isha works alone for 3 days and then stops. Meera finishes the rest. How many days does Meera take?
- 10.Tara works three times as fast as Rohan. Together they finish a job in 3 days. How many days would Rohan take alone?
- 11.Farhan works twice as fast as Zoya. Together they finish a job in 11 days. How many days would Zoya take alone?
- 12.Diya and Isha together finish a job in 4 days. Diya alone takes 20 days. How many days would Isha take alone?
- 13.Pooja works three times as fast as Rahul. Together they finish a job in 4 days. How many days would Rahul take alone?
- 14.Rahul works twice as fast as Ishaan. Together they finish a job in 10 days. How many days would Ishaan take alone?
- 15.Aarav can finish a job in 7 days and Karan in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 16.Tara can finish a job in 4 days and Zoya in 8 days. Tara works alone for 3 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 17.Ishaan can finish a job in 20 days and Rohan in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Ananya can finish a job in 5 days and Manav in 20 days. Ananya works alone for 4 days and then stops. Manav finishes the rest. How many days does Manav take?
- 19.Tara can finish a job in 18 days and Ishaan in 19 days. What fraction of the job do they finish if they work together for 3 days? =
- 20.Ishaan works twice as fast as Rohan. Together they finish a job in 5 days. How many days would Rohan take alone?
- 21.Tara can finish a job in 6 days and Kabir in 30 days. Tara works alone for 4 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 22.Sneha can finish a job in 7 days and Rahul in 28 days. Sneha works alone for 4 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 23.Saanvi can finish a job in 17 days and Vivaan in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 24.Diya can finish a job in 20 days and Vivaan in 19 days. What fraction of the job do they finish if they work together for 3 days? =
- 25.Pooja can finish a job in 18 days and Isha in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 26.Manav can finish a job in 2 days and Ishaan in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Manav can finish a job in 3 days and Diya in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Pooja works three times as fast as Manav. Together they finish a job in 2 days. How many days would Manav take alone?
- 29.Rohan can finish a job in 9 days and Saanvi in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 30.Nisha can finish a job in 18 days and Aditya in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Manav works three times as fast as Rohan. Together they finish a job in 7 days. How many days would Rohan take alone?
- 32.Rohan can finish a job in 15 days and Ishaan in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Zoya can finish a job in 20 days and Tara in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Tara can finish a job in 4 days and Arjun in 24 days. Tara works alone for 3 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 35.Kabir can finish a job in 15 days and Meera in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Ishaan can finish a job in 6 days and Karan in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 37.Farhan works three times as fast as Vivaan. Together they finish a job in 6 days. How many days would Vivaan take alone?
- 38.Kabir and Farhan together finish a job in 2 days. Kabir alone takes 4 days. How many days would Farhan take alone?
- 39.Meera can finish a job in 20 days and Aditya in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Rohan can finish a job in 16 days and Diya in 12 days. Rohan works alone for 4 days and then stops. Diya finishes the rest. How many days does Diya take?
Answer key
- 12
- 36
- 14
- 24
- 11/20
- 36
- 40
- 15
- 3
- 12
- 33
- 5
- 16
- 30
- 13/21
- 2
- 60/7
- 4
- 37/114
- 15
- 10
- 12
- 340/37
- 117/380
- 198/29
- 7/4
- 48/19
- 8
- 117/22
- 90/11
- 28
- 30/17
- 80/9
- 6
- 195/28
- 4
- 24
- 4
- 4
- 9